Investment Incentives for Solar and Wind Energy Projects in Vietnam

Informed Counsel

Solar and wind energy are clean, renewable sources that are becoming increasingly popular in many countries, especially in developing economies such as Vietnam. Realizing the importance, advantages, and benefits of such sustainable sources of energy, and facing an increasing demand for electricity supply for further economic development (with consistent annual electricity consumption increases of 10–15 percent), Vietnam decided recently to give greater scrutiny to studying, surveying, encouraging, and supporting investors, both foreign and domestic, investing in renewable energy projects.

Development of new and renewable energy was included in Vietnam’s national energy development strategy through 2020, with a vision towards 2050, as promulgated in Decision 1855. This strategy sets specific targets to increase the proportion of new and renewable energy sources to 3 percent of total commercial primary power by 2010, 5 percent by 2020, and 11 percent by 2050. To reach these targets, Decision 1855 also guides the direction and orientation for development together with policies, incentives, and governmental support to attract investors. These goals are reflected in various pieces of legislation.

Advantages for Investors

Under current legislation, investors are entitled to maximum incentives for every aspect related to solar or wind energy projects, such as land or water surface lease terms and fees, corporate income tax, value-added tax, import and export duties, land site clearance, and depreciation of fixed assets, among others. In addition, solar and wind power projects are considered clean investments under the country’s clean development mechanism (see Decision 130). Accordingly, investors are subsidized by the state through the Environmental Protection Fund of Vietnam for the difference between the real input costs and the sales price of power as agreed to in the contract to provide power generated by solar or wind energy (see Decree 58).

Challenges for Investors

Although enjoying a variety of incentives, investors also face several challenges when investing in these kinds of projects. First, at present, Vietnam has not yet conducted any official or comprehensive surveys, studies, or assessments on the potential of solar or wind energy in Vietnam. Thus, prospective investors may lack necessary information when seeking investment opportunities.

Second, Vietnam does not have a cohesive legal framework governing policies related to solar or wind energy projects. Such policies are now stipulated separately in various statutes. In some instances, there are conflicting rules and regulations between different laws governing the same issues. To overcome these difficulties, the deputy prime minister recently requested and assigned the Ministry of Industry and Trade to fast-track a draft decision of the prime minister’s office on the strategy and general planning for development of renewable energy in Vietnam up to 2030, with a vision towards 2050. The draft plan is awaiting the prime minister’s approval.

Third, and most importantly, Vietnam lacks an effective and feasible mechanism for investor financing as it relates to the sales price of wind power. Currently, the Vietnam Electricity Group (EVN) is the exclusive transmitter, purchaser, and distributor of power. The sales price for power in Vietnam is always the highest hurdle for investors to overcome, and in practice, the set prices for power purchase by the EVN monopoly are always much lower than the actual input costs. As encouragement, the state assists investors by providing a subsidy for the difference in contract price (see Decision 130). But these subsidies are often insufficient and limited to the amount set aside in the state fund. As a result, investors remain cautious of their risks when investing in this field.

To calm investors’ anxieties, the Ministry of Industry and Trade very recently completed and submitted to the government, for its consideration and approval, a draft decision on promulgating regulations on investment and construction of wind power projects in Vietnam. The draft indicates EVN will assist in the connection of wind-generated power to the power grid and be liable for purchasing and distributing all products from wind power projects. In particular, EVN will pay VND 1,317 (approximately USD 0.07) for each kilowatt of wind-generated power, and the state will subsidize an amount of VND 185 (approximately USD 0.01).

Furthermore, under the draft plan, wind power investors will enjoy import tax exemption on machinery and equipment, corporate income tax at 10 percent for the life of the project, land-use tax exemption for the duration of the project, and access loans up to 80 percent of the total investment capital along with preferential interest rates.

Project Restrictions

At present, there are no statutory prohibitions relating to the development of coastal areas as it pertains to energy investors, either foreign or Vietnamese. Legislation on investments only prohibits projects that:

  • Are detrimental to national defense and security and/or the public interest.
  • Are detrimental to historical and cultural traditions and ethics, and Vietnamese fine customs.
  • Harm the people’s health, or destroy natural resources and the environment.
  • Treat toxic wastes brought into Vietnam, or are projects for the manufacture of any type of toxic chemicals or for the use of chemical agents prohibited by international treaties.

Subject to the above exceptions, investors enjoy the right to invest in other projects without restrictions as to location within Vietnam, provided that the investor satisfies all conditions and procedures in accordance with the law.

Wind Projects in Vietnam

Among alternative energy sources, wind power may represent the strongest growth opportunity in Vietnam. Surveys have shown that approximately 85 percent of Vietnam’s land has an elevation and average wind speed that is suitable for generating wind power. Experts from the World Bank have concluded that Vietnam has the ability to generate 513,360 megawatts annually through wind power—10 times the projected national electricity capacity for 2020.

The coastal provinces of Binh Thuan and Ninh Thuan, in particular, are considered to have the greatest potential for wind power in large plots of land that are arid and not agriculturally fertile. At present, there are more than 20 wind power projects in Vietnam, mainly located in Binh Thuan (12 projects on the mainland and Phu Quy Island District), Ninh Thuan, Binh Dinh, Phu Yen, and Con Dao Island District of Ba Ria-Vung Tau province, where the volume and average wind speed are highest compared to the rest of the country.

Of these, the wind power projects in Binh Thuan and Ninh Thuan of the Vietnam Renewable Energy Joint Stock Company (REVN) stand out because of their size. REVN is the owner of Tuy Phong Wind Power Factory located in Binh Thanh commune, Tuy Phong district, Binh Thuan province. Phase 1, consisting of 20 turbines, was just completed with a capacity of 30 megawatts. The project was put into operation (i.e., began generating power) as of March 2011 with a total investment capital of VND 1.5 billion. REVN is now carrying out phase 2 of this project at both Binh Thanh and Chi Cong communes, with an anticipated capacity of 90 megawatts, and total investment capital of VND 4.5 billion. The project, which is now being implemented,will be concluded by 2015.

In Ninh Thuan province, REVN is building Wind Power Factory 1 located at Phuoc Minh commune, Thuan Nam district, with an anticipated capacity of 30 megawatts, including 15 turbines, and a total investment capital of VND 1.35 billion. Operations are expected to begin in 2012. All remaining projects are either in the surveying stage or under construction.

Outlook

Based on projected energy consumption levels, Vietnam will need to secure new sources of energy to maintain its economic growth. The state has given positive signals that it is committed to solar and wind energy over the long term, and these signals have been backed up by the implementation of a wide range of incentives and commitments to a more cohesive plan for renewable energy development in the years to come. As this legal framework develops, solar and wind projects may emerge as one of the most attractive fields for foreign investment in Vietnam.

RELATED INSIGHTS​ 

January 3, 2024
Thailand’s Energy Regulatory Commission (ERC) has issued the Notification on the Criteria for Regulating the Licensed Pool Manager B.E. 2566 (2023), which took effect on November 30, 2023. It followed an earlier notification, which took effect on October 13, 2023, that added the new license for the country’s pool gas manager. The new notification aims to regulate natural gas sale agreements and promote competition among players in the regulated natural gas market—that is, those who utilize natural gas for electricity generation under the Electricity Generating Authority of Thailand (EGAT) scheme, including industrial and NGV (natural gas for vehicles) consumers who rely on natural pool gas. The establishment of the pool gas scheme is aimed at encouraging new shippers to enter the market and providing new natural gas shippers with fair opportunities to compete with existing shippers, as all licensed shippers in the regulated market are subject to the same natural gas costs under this new scheme. Under this pool gas scheme, the pool manager plays a critical part in reselling natural gas in the country. Some of its responsibilities include the following: Purchasing natural gas or liquid natural gas (LNG) from licensed shippers in the regulated market at the rate at which the shippers procured the natural gas, including incidental expenses such as pipeline transportation and LNG station fees; Collecting data on the quantity and price of the gas purchased from the licensed shippers and calculating the pool gas price as specified in the ERC-approved manual, which is basically the average price of the natural gas procurement cost of all shippers in the pool; and Reselling natural gas or LNG to licensed shippers at the pool gas pricing rate in the quantity distributed to the pool by each shipper. Apart from its function in facilitating the primary procedures of
December 15, 2023
As part of its membership in Lex Mundi, Tilleke & Gibbins has published an updated edition of its Guide to Doing Business in Thailand for 2023. This guide outlines the key factors for starting and operating a business in the Thai market. Issues covered include: Investment incentives Financial facilities Exchange controls Import and export regulations Structures for doing business Requirements for the Establishment of a Business Operation of the Business Cessation or Termination of the Business Labor legislation, relations, and supply Tax Immigration requirements This publication is part of Lex Mundi’s Country Guides series prepared by member firms in more than 100 jurisdictions worldwide. The guides serve as a useful resource for planning international business strategy and researching new markets. The full Guide to Doing Business in Thailand is available through the button below.
July 25, 2023
Thailand’s Energy Regulatory Commission (ERC) is in the process of reviewing a draft regulation that updates the nationality qualifications for the ultimate shareholders and directors of applicants for an energy business license. The draft ERC Regulation Re: Qualifications, Documents and Application for Electricity Business—which is intended to replace the ERC Regulation Re: Application and Permission for Electricity Business B.E. 2551 and its amendments—is likely to be adopted soon and will affect licensed companies that are foreign majority owned when they apply for or renew their energy business licenses. The draft regulation requires partnerships, limited companies, and public limited companies to have the following qualifications unless there is an international agreement granting national treatment for a specific commitment (mode 3 or mode 4) or exemption by other laws: Juristic persons must be established under Thai law or registered in Thailand with the objective of carrying out electricity business; For private limited companies, foreign ultimate shareholders must not hold more than 49% of the total shares, and the number of the foreign shareholders must not exceed half of all shareholders; At least half of all directors must have Thai nationality; and Any authorized directors must have Thai nationality. When the draft regulation is adopted, it will not take retroactive effect on previously granted energy business licenses, which will continue to be valid until they expire if there is no material change to the license as defined by the draft regulation. Once the license is up for renewal (energy business licenses are normally issued for a specific period of time), it will be subject to the draft regulation. All license applications submitted prior to the effective date of the draft regulation and under consideration will be deemed applications for a license under the draft regulation. As noted above, the new qualification requirements
July 7, 2023
Cambodia has the potential to be one of the top countries in the world for generating renewable energy through solar, based on the average amount of sunlight hours available per day and the consistent sunshine throughout the year. The Cambodian government has recognized this potential and has made major updates to its energy policies in recent years. Solar power is now taking over a much larger portion of the total energy mix in Cambodia, especially as a number of utility-scale solar power plants have come online in recent years. The long-term Power Development Master Plan 2022–2040 sets out the long-term energy policy for Cambodia and requires a bigger role for renewables. The use of solar power will play a key role in this aim to increase the role of renewables, with the plan foreseeing almost 30% of all national power generated through solar technologies by 2040. Two of the latest legislative and regulatory steps by the government are the Ministry of Mines and Energy’s guidelines for rooftop solar systems, and most recently the long-awaited Environment and Natural Resources Code, which was enacted on June 29, 2023. Rooftop Solar Projects Many companies, from small startups to multinationals, are exploring the potential for rooftop solar in Cambodia. However, despite the favorable natural factors, the regulatory framework was not always clear or friendly to rooftop solar, hampering investment. This started slowly changing with the adoption of the first solar energy regulation in 2018, which provided the country’s first official guidance on both solar power plants and rooftop solar. It provided some much-needed clarity, but the 2018 solar energy regulation—and especially the subsequent electricity tariff schemes—often kept rooftop projects from being financially viable. Many players in the industry voiced their doubts about the regulations and tariffs, focusing especially on the capacity charge—a monthly