The Impact of COVID-19 and Other Extraordinary Events on Contractual Performance

The dawn of the new decade brought with it familiar expectations of prosperity in global and regional commerce. This expectation has resonated throughout the ASEAN region and Thailand in particular, an historical favorite in the region for tourism and business investment. By the close of 2019 tourism numbers were at historic highs and investment in business and infrastructure were on the rebound, with parties to contracts in the region from both within and outside Thailand committing substantial resources to existing or contemplated commercial contracts.

But extraordinary events can disrupt even the most favorable of economic pictures. COVID-19 and its rapid escalation into a global pandemic has had a significant impact, not only on the global economic outlook, but also on regional operators’ business plans. The Thai government, following the lead of the WHO and other regional and global players, has employed measures to limit travel and public gatherings and in some cases has even restricted access to government functions. These measures, along with measures implemented by other countries, have caused unprecedented business disruptions affecting business operators in ways that may significantly impair their ability to meet their commercial contract obligations. But does this and similar global shocks constitute an excuse for nonperformance of commercial contracts? The answer lies largely in an analysis of the law of force majeure  and impossibility.

Force Majeure and Business Disruptions

Force majeure  is defined broadly as an event that could not have been reasonably anticipated and is otherwise beyond a party’s control. This is codified in Thailand’s Civil and Commercial Code. Thai statutory law does not provide a list of specific instances that constitute force majeure , but the Thai Supreme Court has found that a party may be excused from certain contractual obligations in instances of widespread fire, flooding, extreme natural disruptions, extraordinary acts of government, and in periods of significant unrest. What is certain, however, is that the Thai Supreme Court has historically taken a conservative stance and has ruled that a party is excused from performance obligations in only a minority of force majeure  disputes. For this reason, parties wishing to avoid the uncertainty of the courts’ interpretation of force majeure  should consider including specific force majeure  clauses in their contracts.

Many commercial contracts, particularly in construction and supply of goods, contain some form of standard force majeure  clause. These clauses typically include a specific but limited list of events that are not within the control of the contracting parties. These may include events such as acts of God, war, and terrorism; but epidemics or pandemics, while increasingly common, are still not included in many force majeure  clauses. That said, specific force majeure  provisions are typically more inclusive than statutory force majeure  law and, as such, provide more certainty to contracting parties in the case of extraordinary events covered by the provision. While a specific force majeure  provision is preferred, it should be noted that statutory force majeure  law will be applied even where the contract is silent.

Impossibility

Thai statutory law further provides that if a contractual obligation becomes impossible to perform due to a future circumstance for which the party is not responsible, then that party may be excused from performance. For example, if performance becomes impossible due to a force majeure  or similar event, then a party would not be at fault for failure to perform under the contract. Neither would that party be entitled to compensation under the contract.

While there exist exceptions to the rule of impossibility, such as for certain specially ordered and manufactured products, the general rule may apply, provided that a party has done all that is reasonable under the circumstances, has not contributed to the breach, and could not have reasonably anticipated the events resulting in the impossibility of performance.

COVID-19

While the Thai Supreme Court has not specifically addressed the case of a healthcare pandemic as a basis for force majeure , it is widely believed that, given the extraordinary impact COVID-19 has had to date, the pandemic may indeed constitute a force majeure  event on which a party could rely in arguing that it should be excused from its contractual obligations, regardless of specific reference in a contract. The analysis does not end simply with a determination of force majeure , however.

Even where an event qualifies as a force majeure  event under statute or contract, resulting in an impossibility to perform, a dispute must nonetheless be evaluated on a case-by-case basis to determine whether a party should be excused from performance of a given contract. For example, the law requires that a party seeking to avail itself of force majeure  as an excuse for nonperformance has an obligation to take reasonable care in seeking to limit and otherwise mitigate the effect of the force majeure  event. This can mean having contingency plans in place, being reasonably adaptive to developing events, and generally doing all that is reasonably necessary to seek to meet its contractual obligations. It is not enough to simply stand by and claim excuse from contractual obligations due to the unforeseen event. In fact, even some global emergencies may not impair a party’s ability to find alternative means to meet its contractual obligations, while in others the disruptions may indeed make it impossible to perform. Each situation and contract is unique, and these differences and the reactions of parties are critical in determining whether a court will impose some obligation on a party under the contract even where an event is defined clearly as force majeure .

COVID-19 represents an unprecedented shock to the world economy and to individual commercial contract obligations. It also serves as a reminder of the importance of planning, evaluation, and adaptation to limit legal uncertainties for businesses reliant on good-faith agreements with their business partners. This includes regular review of business plans and contractual provisions, such as force majeure  language, to ensure that business operators are best positioned to deal with legal complications from unexpected business disruptions.

RELATED INSIGHTS​ 

March 27, 2026
Thailand’s National Broadcasting and Telecommunications Commission (NBTC) has publicly indicated that it is preparing a new regulatory framework for data center operators that may introduce foreign-ownership restrictions. In particular, the NBTC is considering reclassifying data center operations from a type 1 telecommunications business license to a type 3 license. If implemented, this change would subject data center operators to a significantly more stringent regulatory regime, especially in relation to foreign ownership and control. The NBTC has indicated that it intends to propose a draft framework to the NBTC board. This would be followed by a public hearing process, with a view to implementing the new rules within 2026. Under the Telecommunications Business Act B.E. 2544 (2001), as amended, telecommunications businesses operating under type 3 licenses are subject to foreign ownership restrictions, including a requirement that less than 50% of the total issued shares be held by foreign shareholders. In addition, type 3 licensees are subject to foreign dominance restrictions, which prohibit arrangements that allow foreigners to dominate the business. These foreign dominance restrictions are broad in scope and may capture various forms of direct and indirect control or influence. This includes circumstances in which a foreign national is able to influence or control the formulation of policy, management, or business operations, or the appointment of directors or senior executives. At this stage, the exact scope of the proposed rules remains unclear. Businesses with existing or planned data center operations in Thailand should therefore monitor upcoming NBTC developments in this regard and prepare for the expected public hearing process.
March 23, 2026
In March 2026, the Myanmar Investment Commission (MIC) introduced two regulatory updates affecting investors planning new investments or implementing MIC-approved projects. Minimum Investment Conditions for Tax Incentives MIC Notification No. 1/202 clarifies the minimum conditions for investments in promoted sectors to qualify for tax exemptions or relief under the Myanmar Investment Law. The notification establishes the following requirements: Investors must contribute at least 35% of the total investment amount in cash, as reflected in the relevant proposal or endorsement application. Where an investment involves a foreign loan, the investor must obtain approval from the Central Bank of Myanmar, together with a loan repayment schedule, and provide evidence that both the foreign loan proceeds and the capital contribution have been remitted in cash through an authorized dealer bank. Chinese Yuan Accepted for Investment Capital The MIC also issued Investment News Bulletin No. 1/2026, confirming that Chinese yuan (CNY) is now accepted as foreign investment capital for applications for MIC permits and endorsements, in addition to US dollars (USD). Investment funds contributed in CNY may be remitted through banks authorized to deal in foreign currency in CNY, following the same process currently applied to investments made in USD. These developments may affect how foreign investment capital is structured and remitted, as well as the availability of tax incentives for investments under the MIC framework.
March 20, 2026
Thailand’s Board of Investment (BOI) now requires data center projects to demonstrate measurable benefits for local workforce development, R&D, SME capability, and domestic supply chains to qualify for corporate income tax (CIT) exemptions. BOI Notification No. Por. 3/2569, issued on February 6, 2026, updates the requirements for projects seeking promotion under BOI category 8.2.1 (data centers). All data center projects must now submit and implement plans covering development of Thai human resources and domestic supply chain support before benefiting from any CIT exemption. Human Resources Development Plan The BOI seeks to promote local talent development beyond basic training. Plans must include the following elements: Training for data center design, construction, and operations targeting vocational students, engineering and ICT undergraduates and postgraduates, and energy and building personnel in Thailand. Joint curricula with Thai universities and technical institutes. Collaborative R&D with Thai nationals or institutions in areas including AI, resource allocation, high-performance computing, and data center hardware and systems. Thai SME upskilling in electrical and energy systems and IT services. Domestic Supply Chain Support Plan Plans must demonstrate knowledge transfer in design, construction, cooling, security, and power and water management. Projects must also include usage or installation of domestically manufactured equipment or engage specialist domestic entities. Criteria for BOI Evaluation The BOI will assess data center operators’ eligibility for CIT incentives based on two criteria: Scale requirement: Training and joint-curriculum initiatives must reach a total participants equal to at least 10 times the project headcount and run for the duration of the CIT incentive. If this threshold is not met, the applicant must also implement continuous R&D or SME skills-development plans throughout the incentive period. Substantiality test: Supply-chain plans must be substantive, meet industry standards, and show measurable development of the domestic digital and data center supply base. To ensure compliance,
March 13, 2026
For decades, intellectual property rights holders seeking to eliminate counterfeit goods from the Thai market have relied primarily on criminal raid actions to seize infringing products and hold infringers accountable. The deterrent value of this approach is typically threefold: imposing criminal liability on infringers, removing counterfeit goods from circulation, and subjecting violators to imprisonment and fines. However, these outcomes often fall short of fulfilling brand owners’ broader objectives. In many cases, those prosecuted are merely staff or intermediaries rather than the principals orchestrating the infringing operations. Moreover, any fines imposed are remitted to the Thai government—not to the rights holders who have suffered commercial harm and invested substantial resources in investigation and coordination with law enforcement authorities. As in other jurisdictions worldwide, rights holders seeking monetary compensation for IP infringement in Thailand have traditionally pursued separate civil litigation. Before initiating such proceedings, a brand owner must gather sufficient evidence to establish both the infringement and the resulting damages. Notably, Thai law does not recognize punitive damages; courts award only actual damages proven by the claimant. In the absence of seized infringing goods, the damages awarded in such cases are typically minimal. This all leaves rights holders with limited recourse despite possibly having suffered significant commercial injury. In 2005, Thailand amended its Criminal Procedure Code to introduce Section 44/1, which enables rights holders to claim damages within criminal proceedings at the Intellectual Property and International Trade Court prior to the evidentiary hearing. In practice, this mechanism allows an injured party to submit a petition for civil damages directly within the criminal case initiated by the public prosecutor. Historically, rights holders in Thailand have been reluctant to use Section 44/1 because the compensation awarded by courts was often insufficient to justify the effort. However, recent years have seen a notable shift