The Impact of COVID-19 and Other Extraordinary Events on Contractual Performance

The dawn of the new decade brought with it familiar expectations of prosperity in global and regional commerce. This expectation has resonated throughout the ASEAN region and Thailand in particular, an historical favorite in the region for tourism and business investment. By the close of 2019 tourism numbers were at historic highs and investment in business and infrastructure were on the rebound, with parties to contracts in the region from both within and outside Thailand committing substantial resources to existing or contemplated commercial contracts.

But extraordinary events can disrupt even the most favorable of economic pictures. COVID-19 and its rapid escalation into a global pandemic has had a significant impact, not only on the global economic outlook, but also on regional operators’ business plans. The Thai government, following the lead of the WHO and other regional and global players, has employed measures to limit travel and public gatherings and in some cases has even restricted access to government functions. These measures, along with measures implemented by other countries, have caused unprecedented business disruptions affecting business operators in ways that may significantly impair their ability to meet their commercial contract obligations. But does this and similar global shocks constitute an excuse for nonperformance of commercial contracts? The answer lies largely in an analysis of the law of force majeure  and impossibility.

Force Majeure and Business Disruptions

Force majeure  is defined broadly as an event that could not have been reasonably anticipated and is otherwise beyond a party’s control. This is codified in Thailand’s Civil and Commercial Code. Thai statutory law does not provide a list of specific instances that constitute force majeure , but the Thai Supreme Court has found that a party may be excused from certain contractual obligations in instances of widespread fire, flooding, extreme natural disruptions, extraordinary acts of government, and in periods of significant unrest. What is certain, however, is that the Thai Supreme Court has historically taken a conservative stance and has ruled that a party is excused from performance obligations in only a minority of force majeure  disputes. For this reason, parties wishing to avoid the uncertainty of the courts’ interpretation of force majeure  should consider including specific force majeure  clauses in their contracts.

Many commercial contracts, particularly in construction and supply of goods, contain some form of standard force majeure  clause. These clauses typically include a specific but limited list of events that are not within the control of the contracting parties. These may include events such as acts of God, war, and terrorism; but epidemics or pandemics, while increasingly common, are still not included in many force majeure  clauses. That said, specific force majeure  provisions are typically more inclusive than statutory force majeure  law and, as such, provide more certainty to contracting parties in the case of extraordinary events covered by the provision. While a specific force majeure  provision is preferred, it should be noted that statutory force majeure  law will be applied even where the contract is silent.

Impossibility

Thai statutory law further provides that if a contractual obligation becomes impossible to perform due to a future circumstance for which the party is not responsible, then that party may be excused from performance. For example, if performance becomes impossible due to a force majeure  or similar event, then a party would not be at fault for failure to perform under the contract. Neither would that party be entitled to compensation under the contract.

While there exist exceptions to the rule of impossibility, such as for certain specially ordered and manufactured products, the general rule may apply, provided that a party has done all that is reasonable under the circumstances, has not contributed to the breach, and could not have reasonably anticipated the events resulting in the impossibility of performance.

COVID-19

While the Thai Supreme Court has not specifically addressed the case of a healthcare pandemic as a basis for force majeure , it is widely believed that, given the extraordinary impact COVID-19 has had to date, the pandemic may indeed constitute a force majeure  event on which a party could rely in arguing that it should be excused from its contractual obligations, regardless of specific reference in a contract. The analysis does not end simply with a determination of force majeure , however.

Even where an event qualifies as a force majeure  event under statute or contract, resulting in an impossibility to perform, a dispute must nonetheless be evaluated on a case-by-case basis to determine whether a party should be excused from performance of a given contract. For example, the law requires that a party seeking to avail itself of force majeure  as an excuse for nonperformance has an obligation to take reasonable care in seeking to limit and otherwise mitigate the effect of the force majeure  event. This can mean having contingency plans in place, being reasonably adaptive to developing events, and generally doing all that is reasonably necessary to seek to meet its contractual obligations. It is not enough to simply stand by and claim excuse from contractual obligations due to the unforeseen event. In fact, even some global emergencies may not impair a party’s ability to find alternative means to meet its contractual obligations, while in others the disruptions may indeed make it impossible to perform. Each situation and contract is unique, and these differences and the reactions of parties are critical in determining whether a court will impose some obligation on a party under the contract even where an event is defined clearly as force majeure .

COVID-19 represents an unprecedented shock to the world economy and to individual commercial contract obligations. It also serves as a reminder of the importance of planning, evaluation, and adaptation to limit legal uncertainties for businesses reliant on good-faith agreements with their business partners. This includes regular review of business plans and contractual provisions, such as force majeure  language, to ensure that business operators are best positioned to deal with legal complications from unexpected business disruptions.

RELATED INSIGHTS​ 

May 26, 2025
On September 6, 2024, Laos’ Ministry of Agriculture and Forestry (MOAF) issued Decision No. 4565/MAF on Forest Carbon Management. This decision, which took effect on October 29, 2024, enables Laos to participate in both domestic and international carbon markets. It outlines comprehensive guidelines for forest carbon activities, including investment procedures, carbon credit trading, and benefit allocation. The Department of Forestry (DOF), under the MOAF, oversees these activities and grants relevant permissions. Definitions The decision defines key terms related to forest carbon management: Forest carbon: Carbon dioxide (CO₂) absorbed by forests, calculated in tonnes per hectare. Forest carbon credit: Quantity of CO₂ reduction, absorption, and storage, measured in tonnes of carbon dioxide equivalent (tCO2e), achieved through various projects or activities. These credits are verified for the reduction, absorption, and storage of CO₂ to mitigate greenhouse gas emissions. They can be exchanged and traded in accordance with established standards for greenhouse gas emissions. Forest carbon trading: An agreement between a buyer (domestic or foreign legal entity or government) and a seller (the owner of a forest carbon project) to trade tCO2e . This trading allows the buyer to offset greenhouse gas emissions that exceed the emission allowances set out in the Paris Agreement on climate change. The forest carbon sold becomes the property of the buyer. Forest Carbon Business Operations According to the decision forest carbon business operations include: Cooperation between the government and development partners: This involves bilateral and multilateral cooperation based on international agreements and treaties. The use of carbon credits from this cooperation is not market-based but agreement-based, contributing to Laos’ national climate change goals. Forest carbon investment: This includes direct government investments and joint investments with the private sector, international organizations, or communities. These investments aim to create forest carbon credits without granting exclusive rights to forest
May 2, 2025
Attorneys from Tilleke & Gibbins have updated the latest edition of Doing Business in Thailand, a Q&A-style guide from Thomson Reuters Practical Law that offers an overview of key legal considerations for companies operating in jurisdictions worldwide. The contribution outlines the country’s legal and regulatory framework for foreign investment and business operations and reflects the latest legislative developments. The chapter addresses the following core topics: Legal system: Structure of the courts and the codified nature of Thai law. Foreign investment: Business restrictions under the Foreign Business Act, sector-specific regulations, exchange control rules, and investment incentives. Business vehicles: Overview of partnerships, private and public limited companies, and other legal entities. Employment: Labor protections, employment contracts, foreign worker requirements, and termination procedures. Tax: Corporate and personal income tax, indirect taxes, and tax obligations for residents and non-residents. Intellectual property: Registration and enforcement of patents, trademarks, designs, and copyrights. Data protection: Key provisions of the Personal Data Protection Act and related compliance obligations. Competition law: Regulatory framework under the Trade Competition Act. Anti-bribery and corruption: Relevant legislation and enforcement mechanisms. E-commerce and digital business: Legal regime for online transactions and digital platforms. Marketing and advertising: Consumer protection laws and regulations affecting advertising and marketing practices. Product regulation and liability: Safety standards, liability regimes, and roles of enforcement authorities. Practical Law, a legal reference resource from Thomson Reuters, publishes a range of guides for hundreds of jurisdictions and practice areas. The insurance and reinsurance guide is a valuable resource for legal practitioners, covering numerous jurisdictions worldwide. To view the latest version of the guide, please visit the Practical Law website and enroll in the free Practical Law trial to gain full access.
April 29, 2025
To foster foreign investment and attract leading international universities to establish campuses in Vietnam, the government has recently adopted several regulations, including Decree No. 124/2025 on foreign cooperation and investment in the field of education, Decree No. 125/2024 on regulatory requirements for educational investment and operation, and Decision No. 452/QD-TTg approving the Planning of the Network of University and Teaching Institutions for the Period 2021–2030, with a Vision to 2050 (the “University Network Plan”). However, foreign investors and private higher educational institutions must still navigate regulatory complexities, build strong academic reputations, and ensure financial sustainability to compete effectively in an increasingly competitive landscape. Below are highlights of recent developments in university-related regulations that may open new opportunities for foreign investment in Vietnam. Adopting the University Network Plan The University Network Plan encourages the development of private higher education institutions (“HEIs”), especially not-for-profit ones, and welcomes top foreign HEIs to open their own foreign branch campuses (“FBCs”) in Vietnam, with the following targets. Until 2030: Encouraging new establishment and expansion of the network of private HEIs (including their branch campuses) and FBCs of top foreign HEIs, especially those offering training majors of science, engineering, and technology. Developing regional HEI networks along economic corridors centered on large cities—not only the traditional economic hubs of Hanoi and Ho Chi Minh City, but also other provinces and cities throughout the country such as Hai Phong, Nghe An (Vinh), Thanh Hoa, Hue, Da Nang, Khanh Hoa (Nha Trang), Binh Đinh (Quy Nhon), Dak Lak (Buon Ma Thuot), Lam Dong (Da Lat), Binh Duong, and Can Tho. Vision to 2050: Increasing the number and proportion of private HEIs, especially not-for-profit ones. Having private HEIs account for about 50% of learners. Requirements for Foreign Investment in Higher Education Foreign investors can engage in higher education business
April 29, 2025
Tilleke & Gibbins recently assisted Bitmain, a leading manufacturer of cryptocurrency mining hardware, in successful cancellation action lawsuits against BITMAIN and ANTMINER trademarks that were unlawfully registered by a local party in Indonesia. Background Founded in 2013, Bitmain is a leading manufacturer of digital currency mining servers, marketed under their BITMAIN and ANTMINER brands. The company has maintained a strong global market share, with customers in over 100 countries and regions. In Indonesia, Bitmain has held the BITMAIN trademark registration in classes 35, 36, 41, and 42 since 2018. However, the company was unable to register the trademark in other classes because a local party had already registered the mark in the desired classes. Bitmain also discovered that their ANTMINER brand had been registered by the same local party, which impeded Bitmain’s application to register the ANTMINER trademark in Indonesia. Bitmain had been using these trademarks and products worldwide long before the local party’s registration in Indonesia, and had also secured trademark registrations in various countries. However, the local party exploited Indonesia’s first-to-file principle, securing the BITMAIN and ANTMINER trademarks before Bitmain could file. This was a classic example of trademark squatting, where a party registers a foreign trademark in a jurisdiction where the original owner has not yet filed, with the intent to profit from the brand’s success. Initial Approach Upon discovering that the local party had made these trademark applications, Bitmain found that one of these applications was still in the publication period. We advised and assisted Bitmain to file opposition against the application, but this opposition was subsequently refused because the local party had already obtained identical BITMAIN trademarks in other classes. Consequently, the application was registered in the Trademark Office database. Following the unfavorable opposition decision, we initially worked with Bitmain to seek a mutually