June 3, 2024

Highlights of Implementation Plan for Vietnam’s Latest Power Development Plan

Nearly a year after Vietnam’s issuance of its National Power Development Plan for 2021-2030, with a vision to 2050 (“PDP VIII”), the Prime Minister issued Decision No. 262/QD-TTg dated April 1, 2024, approving the Implementation Plan for PDP VIII (“Implementation Plan”). Among other contents, the Implementation Plan sets forth the list of prioritized power source projects through 2030, and the capacity of renewable energy sources through 2030, as detailed below.

Prioritized Power Source Projects through 2030

The Implementation Plan lists out six types of power source projects prioritized for development through 2023 according to the capacity approved under PDP VIII. They include:

  • Domestic gas-fired power (14,930 MW)
  • LNG-fired power (22,400 MW)
  • Coal-fired power (30,127 MW)
  • Cogeneration power using residual heat, blast furnace gas, and by-products of technological lines in industrial facilities (2,700 MW)
  • Hydropower (29,346 MW)
  • Pumped storage hydropower (2,400 MW)

With respect to each type, the Implementation Plan provides details of projects by location and their operational progress. Such information is set out in Schedule III of the Implementation Plan.

For power source projects not included in this list, the provincial People’s Committees will consult with the Ministry of Industry and Trade (“MOIT”) and relevant agencies on compliance with the planning prior to appraisal and issuance of in-principle investment approval.

Renewable Energy Projects through 2030

The Implementation Plan allocates the capacity of the following renewable energy sources by locality/region:

  • Offshore wind power (6,000 MW)
  • Onshore wind power (21,880 MW)
  • Hydroelectric power (29,346 MW)
  • Biomass electricity (1,088 MW)
  • Electricity produced from waste (1,182 MW)
  • Rooftop solar power for self-production and self-consumption (2,600 MW)
  • Battery storage (300 MW)

With respect to each renewable energy source, the Implementation Plan provides a list of certain renewable energy projects through 2030, including the expected life cycle of the projects, and the allocated capacity for various localities/regions. For the remaining capacity, the provincial People’s Committees were tasked to propose a list of additional projects, and the MOIT was to finalize and submit it to the Prime Minister for approval before April 30, 2024. To date, however, we are not aware of any decision of the Prime Minister approving additional projects to meet the capacity of renewable energy sources allocated under the Implementation Plan.

Other Notes

The Implementation Plan sets out that from 2023 to 2025, the authorities will prioritize developing the following legal framework:

  • Pricing framework for various types of power sources. The purpose is to complete the electricity price management mechanism according to the market mechanism with State regulation.
  • Direct electricity trading mechanism.
  • Mechanism to encourage the development of distributed/rooftop solar power projects for self-production and self-consumption purposes.
  • Electricity Law (amended).
  • Law on Economical and Efficient Use of Energy (amended).
  • Mechanism to develop the carbon credit market.

The MOIT is responsible for promulgating transmission prices for transmission grid projects in the form of socialization investment to encourage the private sectors to invest in power grid infrastructure.

The Ministry of Planning and Investment is tasked with (i) proposing regulations on the authority to decide investment policies for offshore wind power projects, hydrogen/ammonia production projects using offshore wind power, and offshore wind power export projects and (ii) developing a public and transparent bidding mechanism to select investors to implement power projects and provide guidance to localities for implementation.

RELATED INSIGHTS​ 

February 23, 2021
As many are already aware, following the change of government in Myanmar on February 1, 2021, a draft Cyber Security Law was proposed which attracted widespread criticism. However, less attention has been paid to significant amendments to two existing laws, some of which have a similar effect to parts of the draft Cyber Security Law. In other words, while the draft Cyber Security Law has not progressed further and is under public scrutiny, significant elements of it have found their way into law in Myanmar by other routes. Because these amendments are already law, it is very important that individuals and businesses in Myanmar understand their implications. Amendments to the Law Protecting the Privacy and Security of Citizens The Law Protecting the Privacy and Security of Citizens (2017), or the “Privacy Law,” was amended on February 13, 2021, less than two weeks after the military government came into power. These amendments chiefly address the power of the government to conduct searches, seizures, and arrests; to extend detention without judicial oversight; and to carry out broad surveillance and investigation activities that could intrude on individual privacy. The amendments accomplish this by suspending various sections of the Privacy Law for as long as the State Administration Council (the military body now governing Myanmar) is in power. The suspended sections include the following: Section 5: Search, seizure, and arrest without civilian observation The relevant part of Section 5 of the Privacy Law states, “The responsible authorities shall … when acting in accordance with existing law, not enter into a person’s residence or a room used as a residence, or a building, compound or building in a compound, for the purpose of search, seizure, or arrest, unless accompanied by minimum of two witnesses who should comprise Ward or Village Tract Administrators…”. The suspension
February 22, 2021
Following the recent imposition of sanctions on Myanmar individuals and companies by the US, the UK and Canada have now imposed new sanctions. As with the US sanctions, these new measures impact UK and Canadian citizens and companies, and non-UK and non-Canadian companies and citizens with interests in those jurisdictions. The EU has indicated that it is planning to issue similar sanctions in the near future. New UK Sanctions In addition to the 16 individuals already sanctioned by the UK government, on February 18, 2021, the UK government announced that three individuals have been sanctioned for serious human rights violations and are now subject to asset freezes and travel bans. The full list of Myanmar individuals and companies sanctioned by the UK is available on the website of the Office of Financial Sanctions Implementation. Breaches of UK financial sanctions are criminal offences punishable in the UK by up to 7 years imprisonment and heavy fines. New Canadian Sanctions Also on February 18, timed to coincide with the UK sanctions, new Canadian sanctions were imposed on nine individuals. As with the UK, Canada already had a number of individuals in the Myanmar military on its sanctions list, and the new additions bring the total number of individuals sanctioned by Canada to 54. All assets of these individuals in Canada are now frozen, and they are banned from travelling to Canada. Canadian businesses or entities may not do business with any of the 54 individuals. Full details of the impact of the sanctions are available on the Government of Canada’s website, as is a database of the Myanmar individuals and companies subject to them. Breach of Canadian sanctions carries with it up to 5 years’ imprisonment in Canada and/or a large fine. Other Countries The EU is reportedly drawing up sanctions
February 18, 2021
As you will no doubt know, on February 1, 2021, the Myanmar military declared a state of emergency in Myanmar for a period of one year. State Counsellor Daw Aung Sang Su Kyi was detained, as were the president and various significant political and civil leaders. Min Aung Hlaing, commander-in-chief of the Tatmadaw (Myanmar armed forces) has installed himself as chairman of the State Administration Council, the current administration. New sanctions The reaction of the Biden administration has been swift. On February 10, 2021, President Biden issued Executive Order 14014, which provides bases to impose sanctions on individuals and companies deemed by the US to, among other things: operate in the defense sector of Myanmar; be responsible for policies that undermine democratic processes in Myanmar; have taken actions to undermine democratic processes or institutions, or prohibit, limit, or penalize the exercise of free speech, in Myanmar; or be a spouse or child of the foregoing. On the next day, February 11, the US Office of Foreign Assets Control (OFAC), imposed sanctions under the new executive order on ten individuals—including General Min Aung Hlaing—and three companies, including Cancri Gems & Jewelry Co, Myanmar Imperial Jade Co, and Myanmar Ruby Enterprise.  All such individuals and companies have now been designated on the US list of specially designated nationals (SDNs). Effect of sanctions As a result of such sanctions, the property of these individuals or companies that is located in the US or is under the possession or control of US companies and citizens is frozen, and US companies and citizens are generally prohibited from dealing deal with any such property.  Reportedly, roughly USD 1 billion of funds belonging to the individuals and companies blocked on February 11 are located in the US and thus now frozen. The SDN list As many
February 2, 2021
The application period for very small power producers (VSPPs) aiming to participate in the community power plant project is fast drawing to a close, with the deadline set for February 4, 2021. February 4 is also the closing date of the period for public comments on the two draft regulations outlining the pilot project to procure electricity from community power plants. These draft regulations are being finalized by the Energy Regulation Commission (ERC)  as part of an effort to boost the economy at a grassroots level. The community power plant project will procure 150 MW from VSPPs producing electricity from either biomass or biogas. 75 MW will be obtained from biomass VSPPs, with a limit of 6 MW to each biomass VSPP, while 75 MW of the electricity procurement will be obtained from biogas VSPPs with a limit of 3 MW each. VSPPs wishing to apply for the community power plant project must be 90%-owned by a private company, while 10% of ownership must be under a community enterprise or community enterprise network—consisting of at least 200 households—registered with the Department of Agricultural Extension. Furthermore, the fuel used by the VSPP must be either biogas or biomass obtained from the community enterprise or community enterprise network, and must not include fossil fuels. Once VSPPs have submitted their applications, they will be subject to a technical assessment to determine power production readiness, and will undergo a process of competitive bidding. VSPPs will be compared and selected based on a number of factors, including power production capacity, ability to operate for duration of the 20-year project, and the proposed fixed feed-in tariff (FiT). VSPPs that are chosen to participate in this pilot project will be subject to the following FiTs per unit of electricity, based on the type of fuel and