EPC Agreements: Devising a Sound Contractual Framework for Renewable Energy Projects

Informed Counsel

The development of a renewable energy project requires, among a range of factors, engineers to design the facility, state-of-the-art equipment, and a reliable construction firm to implement the project. A key factor in a renewable energy project’s long-term success is devising an appropriate contractual framework to construct the facilities. This is a particularly important consideration, given the scale of many renewable energy projects and the financial sums at stake.  

An engineering, procurement, and construction (EPC) agreement provides a contractual framework whereby a contractor agrees to engineer, procure, and construct a specified structure. It is often referred to as a “turnkey” agreement, since it requires the sponsor or project company to simply “turn a key” to commence operations of the constructed facility.

Advantages of the EPC Structure

From a project sponsor’s perspective, a main benefit of having an EPC agreement in place is that it provides a single point of contact and responsibility for the development of a particular project. For a project company, this avoids both the logistical confusion of coordinating among separate design and construction firms, as well as the necessity to allocate risk among various parties in terms of delayed or defective performance.

With an EPC agreement in place, the contractor is essentially tasked with designing the renewable energy project, procuring the materials necessary to build the structure, and then actually building it. While, in practice, it is not uncommon for an EPC contractor to hire one or more subcontractors to carry out certain construction works, the EPC contractor will remain directly liable to the project company for ultimate performance.

EPC Agreements vs. Fragmented Structures

A main advantage of an EPC agreement over a fragmented structure—where there are separate design, supply, and construction agreements—is its attractiveness to commercial lenders. In traditional limited recourse financing, lenders will be looking for guarantees that the project will be operational, and therefore generating revenue, within prescribed timelines. Since the EPC structure usually includes performance guarantees, such as a guaranteed minimum output capacity, it is generally considered as preferable to separate agreements where no single contractor will be able to provide such guarantees.

The contractual framework for the development of a renewable energy project will be as unique to that project as its technical aspects. It is not strictly necessary for developers to engage a single contractor to engineer, procure, and construct the facilities. Many developers of large-scale private sector wind and solar farms have inhouse engineering capabilities, as well as a network of global supply chains which can provide wind turbines or photovoltaic panels. Some developers will therefore choose to procure the necessary equipment from their own suppliers and engage design and construction firms separately.

In the case of dedicated biomass projects, one of the main technical considerations is the supplier of the boiler or combustor. Since this is a highly specified technical aspect of a biomass project, which will have a significant impact on the overall performance of the power plant, developers often procure the boiler themselves. If an EPC structure is used for the design and construction of a dedicated biomass power plant, meaning that the EPC contractor is willing to accept the technological risk associated with procuring the boiler, developers and project lenders frequently require a list of approved suppliers of the boiler to be included in the EPC agreement.

Key Provisions of EPC Agreements

There are a number of key provisions in an EPC agreement for a renewable energy project. The sponsor should obtain a security or performance bond for a certain percentage of the contract price from the contractor, to be called upon in the event of nonperformance or inadequate performance. The amount, form, and issuer of the bond should be considered. The timing and amount of liquidated damages, either in relation to delayed construction or inadequate performance, should be devised. It is important to draft these clauses precisely in order to clearly identify under what circumstances the liquidated damages must be paid and ensure that they are not excessive in the circumstances.

For solar and wind power projects, it is important to properly consider aspects of output measurement. Unlike power plant projects, which rely on steady sources of fuel such as biomass, wind and solar power plants rely on freely available fuel supplies. The EPC contractor must take notice of the testing regime provisions and ensure that these provisions coincide with the related clauses of the power purchase agreement between the project company and the offtaker.

Split Agreements

A variation of the standard EPC agreement is the “split agreement.” Many EPC contracts in the renewable sector contain both offshore and onshore agreements, whereby the design and procurement phases of the EPC contractor’s work take place offshore. The onshore company, which carries out the construction work, can either be an affiliate, a joint-venture company in which the offshore EPC contractor has a stake, or an unrelated third-party construction firm which has entered into a consortium with the offshore contractor to complete the renewable energy project.

In renewable energy projects where the offshore and onshore works are to be split, the drafters of the EPC agreements must be mindful of the division of responsibilities between the offshore and onshore contractors. The sponsors of the project should ensure that both the offshore and onshore contractors agree to be held jointly liable for any damages that result from delayed or defective performance. The division of tasks should be clearly outlined in the offshore and onshore agreements. The liquidated damages clauses should reflect the commercial bargain. If construction is stalled because of a delayed shipment, or if the power facility is not capable of generating the rated capacity, the offshore and onshore agreements should clearly stipulate how much the sponsor or project company is entitled to claim.

Given the scale of many renewable energy projects, as well as the financial sums involved, it is vital that the contractual structure for the design and construction of the facilities is properly considered, negotiated, understood, and agreed upon between the parties.

RELATED INSIGHTS​ 

May 19, 2023
On May 15, 2023, Vietnam’s Deputy Prime Minister Tran Hong Ha signed Decision No. 500 of the Prime Minister approving the National Power Development Plan for the period 2021-2030, with a vision to 2050 (“PDP VIII”), following extensive public consultations and multiple rounds of review since the first draft version was circulated in 2021. The plan was approved in the context that in the past few years, a number of large power projects have been behind schedule for operation, while new projects have not been able to be implemented due to waiting for additional planning. PDP VIII is the master plan for the development of the power source and transmission grid at 220kV or higher; services in renewable energy and new energy in Vietnam; and works connecting the power grids of Vietnam and neighboring countries. We set out below some quick updates regarding PDP VIII. 1. Development Targets Key development targets are summarized in the table below: Investors in coal, domestic gas, and LNG projects may need to have a conversion plan ready given the 2050 targets to convert to other sources of energy. 2. Solar Projects A list of 27 solar power projects that were planned for the period of 2021-2030 but which have not been assigned to investors are not allowed to be deployed but can be considered after 2030, except in the case of deployment in the form of self-production and self-consumption (Appendix IV). These projects represent 4,136.25 MW of capacity that will be left on the sidelines until 2030. 3. Hydropower Projects A list of 14 potential hydropower projects can be considered if economic and technical conditions allow for more hydropower development (Appendix III). These projects represent 1,244 MW of capacity that can be added to the hydropower targets for 2030. 4. Projects Prioritized for
March 22, 2023
Attorneys from Tilleke & Gibbins have contributed the Cambodia, Laos, Myanmar, and Vietnam sections to DLA Piper’s Global Government Contracting Country by Country guide, which provides essential information for businesses in 75 jurisdictions on how to source and enter into government contracting opportunities. The guide provides procurement information for jurisdictions in Africa, the Americas, Asia-Pacific, Europe, and the Middle East, and includes information on how to find procurement opportunities, the structure of procurement laws, and in-country resources and relevant publications. Each jurisdictional section includes valuable information on procedures for government tenders, bidding, and contract execution, as well as an overview of the legal and regulatory framework governing government procurement. Businesses can refer to the guide to gain a better understanding of procurement processes and regulations in each jurisdiction, which can help them identify potential opportunities and make informed decisions when pursuing government contracts. The guide’s procurement information for Cambodia, Laos, Myanmar, and Vietnam, combined with the online platform’s comprehensive resources, provides businesses and governments with a valuable tool to navigate the complex regulatory landscape of government contracting in the region. The full Global Contracting Country-by-Country guide is available on the DLA Piper website.
February 20, 2023
On December 20, 2022, the Notification re: Rules, Procedures, and Conditions on Transfer of Energy Licenses of the Thailand Energy Regulatory Commission (ERC) became effective. The notification sets out the new standard and procedure for transferring licenses for energy industry operation. The notable changes in the notification are provided below. Anti-Competition Consideration and Impact Assessment Report In considering the transfer of a license, in addition to ensuring the transferee meets all the qualifications for an applicant for the license, the ERC will consider if the transfer would (1) create a monopoly, reduce or restrict competition, or result in market dominance; (2) affect the contracting parties of the transferors or energy users; or (3) affect energy security or the public interest. In this respect, the vetting process for an application for license transfer would be separated into two different approaches. If the ERC believes that the transfer of the energy license would affect competition, energy users, energy security, or the public interest, the transferor will need to submit an impact assessment report on the license transfer to the ERC. In this regard, the ERC may establish a sub-committee or an independent consultant to contemplate the transfer at the transferor’s expense. However, if the ERC believes that the transfer of license would not lead to any impact, the transferor will not be required to submit the impact assessment. Also, if the license transfer is related to any transactions specified under the ERC’s Regulation re: Rules and Procedures on Merger and Cross-Shareholding in Energy Businesses, B.E. 2565, the ERC can combine the license transfer application with the M&A application. After approval, the ERC might require the transferee to periodically report to the ERC and comply with measures stipulated by the ERC. Therefore, an energy license holder which plans to carry out M&A
February 3, 2023
The Federation of Thai Industries (FTI) announced on January 16, 2023, the opening of registration for carbon credit trading on its Renewable Energy and Carbon Credit Exchange Platform. This new online platform supports the domestic carbon market and provides Thai exporters with the ability to purchase carbon credits, allowing them to address demands from importing nations to conform to carbon emission reduction regulations. This is expected to be a positive step forward for the current practice in Thailand, in which the carbon market operates as a voluntary and unregulated buy-sell platform, free from government regulation. Developed in partnership with the Thailand Greenhouse Gas Management Organization (TGO), the FTI: CC/RE/REC X Platform, or FTIX, is intended to increase the promotion of national carbon credits, renewable energy, and renewable energy certificates, thus improving the country’s efforts to mitigate climate change. Entrepreneurs interested in registering for carbon credit trading on the FTIX can do so through the FTIX website at fti-cc.com. The platform initially supports carbon credit trading through over-the-counter methods. In the near future, the FTIX will be developed to support 100% renewable energy (i.e., RE100 energy) and renewable energy certificate trading. However, the related tax and carbon pricing policies have not yet been issued. The TGO is currently in discussions with the Fiscal Policy Office and the Ministry of Finance regarding fiscal policy for the FTIX. For more information on the FTIX, or on any aspect of renewable energy activities in Thailand, please contact Charuwan Charoonchitsathian at [email protected], Napassorn Lertussavavivat at [email protected], or Ratchapat Triteeyaputranonta at [email protected].