EPC Agreements: Devising a Sound Contractual Framework for Renewable Energy Projects

Informed Counsel

The development of a renewable energy project requires, among a range of factors, engineers to design the facility, state-of-the-art equipment, and a reliable construction firm to implement the project. A key factor in a renewable energy project’s long-term success is devising an appropriate contractual framework to construct the facilities. This is a particularly important consideration, given the scale of many renewable energy projects and the financial sums at stake.  

An engineering, procurement, and construction (EPC) agreement provides a contractual framework whereby a contractor agrees to engineer, procure, and construct a specified structure. It is often referred to as a “turnkey” agreement, since it requires the sponsor or project company to simply “turn a key” to commence operations of the constructed facility.

Advantages of the EPC Structure

From a project sponsor’s perspective, a main benefit of having an EPC agreement in place is that it provides a single point of contact and responsibility for the development of a particular project. For a project company, this avoids both the logistical confusion of coordinating among separate design and construction firms, as well as the necessity to allocate risk among various parties in terms of delayed or defective performance.

With an EPC agreement in place, the contractor is essentially tasked with designing the renewable energy project, procuring the materials necessary to build the structure, and then actually building it. While, in practice, it is not uncommon for an EPC contractor to hire one or more subcontractors to carry out certain construction works, the EPC contractor will remain directly liable to the project company for ultimate performance.

EPC Agreements vs. Fragmented Structures

A main advantage of an EPC agreement over a fragmented structure—where there are separate design, supply, and construction agreements—is its attractiveness to commercial lenders. In traditional limited recourse financing, lenders will be looking for guarantees that the project will be operational, and therefore generating revenue, within prescribed timelines. Since the EPC structure usually includes performance guarantees, such as a guaranteed minimum output capacity, it is generally considered as preferable to separate agreements where no single contractor will be able to provide such guarantees.

The contractual framework for the development of a renewable energy project will be as unique to that project as its technical aspects. It is not strictly necessary for developers to engage a single contractor to engineer, procure, and construct the facilities. Many developers of large-scale private sector wind and solar farms have inhouse engineering capabilities, as well as a network of global supply chains which can provide wind turbines or photovoltaic panels. Some developers will therefore choose to procure the necessary equipment from their own suppliers and engage design and construction firms separately.

In the case of dedicated biomass projects, one of the main technical considerations is the supplier of the boiler or combustor. Since this is a highly specified technical aspect of a biomass project, which will have a significant impact on the overall performance of the power plant, developers often procure the boiler themselves. If an EPC structure is used for the design and construction of a dedicated biomass power plant, meaning that the EPC contractor is willing to accept the technological risk associated with procuring the boiler, developers and project lenders frequently require a list of approved suppliers of the boiler to be included in the EPC agreement.

Key Provisions of EPC Agreements

There are a number of key provisions in an EPC agreement for a renewable energy project. The sponsor should obtain a security or performance bond for a certain percentage of the contract price from the contractor, to be called upon in the event of nonperformance or inadequate performance. The amount, form, and issuer of the bond should be considered. The timing and amount of liquidated damages, either in relation to delayed construction or inadequate performance, should be devised. It is important to draft these clauses precisely in order to clearly identify under what circumstances the liquidated damages must be paid and ensure that they are not excessive in the circumstances.

For solar and wind power projects, it is important to properly consider aspects of output measurement. Unlike power plant projects, which rely on steady sources of fuel such as biomass, wind and solar power plants rely on freely available fuel supplies. The EPC contractor must take notice of the testing regime provisions and ensure that these provisions coincide with the related clauses of the power purchase agreement between the project company and the offtaker.

Split Agreements

A variation of the standard EPC agreement is the “split agreement.” Many EPC contracts in the renewable sector contain both offshore and onshore agreements, whereby the design and procurement phases of the EPC contractor’s work take place offshore. The onshore company, which carries out the construction work, can either be an affiliate, a joint-venture company in which the offshore EPC contractor has a stake, or an unrelated third-party construction firm which has entered into a consortium with the offshore contractor to complete the renewable energy project.

In renewable energy projects where the offshore and onshore works are to be split, the drafters of the EPC agreements must be mindful of the division of responsibilities between the offshore and onshore contractors. The sponsors of the project should ensure that both the offshore and onshore contractors agree to be held jointly liable for any damages that result from delayed or defective performance. The division of tasks should be clearly outlined in the offshore and onshore agreements. The liquidated damages clauses should reflect the commercial bargain. If construction is stalled because of a delayed shipment, or if the power facility is not capable of generating the rated capacity, the offshore and onshore agreements should clearly stipulate how much the sponsor or project company is entitled to claim.

Given the scale of many renewable energy projects, as well as the financial sums involved, it is vital that the contractual structure for the design and construction of the facilities is properly considered, negotiated, understood, and agreed upon between the parties.

RELATED INSIGHTS​ 

January 25, 2023
Thailand’s Energy Regulatory Commission (ERC) has issued four new regulations under the Energy Business Act B.E. 2550 (2007) setting forth competition regimes to control both anticompetitive conduct and market structure in the energy business sector. The regulations were published in the Government Gazette on December 19, 2022, and took effect the following day. The key provisions of these ERC competition regulations largely mirror those articulated in the Trade Competition Act B.E. 2560 (2017) and its subordinate legislation. The most significant features of these competition regulations are summarized below. Market Definition Regulation The ERC’s market definition regulation (officially the ERC Regulation re: Market Definition and Relevant Market of Related Energy Services B.E. 2565) outlines the general framework for defining relevant markets in the energy sector. The factors to be taken into consideration include types of energy licenses, geographical areas, competition conditions, and interchangeability of energy services. In the annex to this regulation, the ERC has classified the relevant energy service markets as follows: Power business activities include power generation, power transmission system services, power distribution system services, power distribution services, and power system control services. Natural gas business activities include natural gas transmission through pipelines via natural gas transmission systems, natural gas procurement and wholesale via natural gas distribution systems, natural gas retail via natural gas distribution systems, and storage and regasification of liquefied natural gas. The ERC will review its market definitions and relevant energy service markets from time to time, taking into account changes in technology and competition conditions as well as feedback from public hearings. Market Dominance Regulation Under the ERC’s market dominance regulation (officially the ERC Regulation re: Criteria on Business Operator having a Market Dominance B.E. 2565), the ERC is empowered to proactively determine and declare which license-holding energy business operators have a dominant position
August 31, 2022
Thailand’s Draft Climate Change Act Countries around the world have given significant attention to climate change legislation, with many national, regional, and global attempts to slow the momentum of climate change. The most notable of these multilateral efforts is the Paris Agreement, a legally binding international treaty on climate change currently adopted by 193 parties. Its goal is to limit the global average temperature to well below 2°C (preferably below 1.5°C) above preindustrial levels, and the treaty’s coordinated efforts to combat climate change are much more ambitious than previous global agreements and discussions. Article 4 of the Paris Agreement requires countries to provide “nationally determined contributions” (NDCs), consisting of their action plans for climate action. Thailand, as a party to the Paris Agreement, has put forth an NDC that pledges to achieve an unconditional greenhouse gas (GHG) emission reduction target of 20% from the business-as-usual projection for 2030, with the possibility of increasing that target to 25% subject to adequate and enhanced access to technology development and transfer, financial resources, and other support. To enable the accomplishment of this pledge, Thailand is looking to enact climate change legislation that functions as a key mechanism for domestic climate action. In 2018, the Office of Natural Resources and Environmental Policy and Planning (ONEP) under the Ministry of Natural Resources and Environment was assigned to prepare a draft Climate Change Act. The draft is now complete, and according to news reports it is set to be submitted to the cabinet for further consideration. The draft Climate Change Act lays out Thailand’s action plan for climate change mitigation and adaptation, including emissions reductions. Some of the key sections in the draft law involve citizen rights, the National Climate Change Policy Committee, and a national GHG database. Rights of Citizens The draft establishes the
August 26, 2022
Thailand’s Board of Investment (BOI) has extended its previously announced period for reduction of import duty on imported raw and essential materials for battery manufacturing for electric vehicles and other applications. The BOI’s announcement No. 5/2565 dated August 8, 2022, extended the reduction period to a maximum of five years. The BOI’s promoted activities list includes two battery-manufacturing business activities: Activity 4.8.3.1 – Battery manufacturing Activity 5.2.6.1 – High energy density battery manufacturing Qualifying battery manufacturers who have cell or module manufacturing processes are eligible for 90% import duty reductions on raw and essential materials that cannot be produced in Thailand. These reductions will be available on an annual basis, and are renewable for five years in total—up from the original two years. Existing projects (i.e., those which have the original two-year duration in their BOI certificate) can also benefit from the extension by preparing a project amendment form, along with a clarification letter and supporting documents, for submission to the BOI office. For more details on these customs duty reductions, or on any aspect of investment promotion in Thailand, please contact Charuwan Charoonchitsathian at [email protected] or +66 2056 5657, or Napassorn Lertussavavivat at [email protected] or +66 2056 5662.
August 16, 2022
On July 21, 2022, Vietnam’s Ministry of Industry and Trade (MOIT) submitted Report No. 126/BC-BCT to the Prime Minister regarding the mechanism for transitional wind and solar power projects. In this report, the MOIT proposed some recommendations to explicitly address difficulties for outstanding wind and solar power projects (“Transitional Projects”) which have been developed under the Prime Minister’s Decision No. 13/2020/QD-TTg dated April 6, 2020, on the development of solar power projects (Decision 13) and Decision No. 37/2011/QD-TTg dated June 29, 2011, on the development of wind power projects (Decision 37), as amended by Decision No. 39/2018/QD-TTg dated September 10, 2018 (Decision 39). The Transitional Projects primarily include those which have completed construction but have not yet been put into operation, and those which have been put into operation but for which the power price has not yet been decided, due to missing the deadline set forth under the aforementioned decisions to be eligible for the feed-in-tariff (FIT). In particular, the MOIT has proposed the following key recommendations to the Prime Minister: Mechanism for Transitional Projects The MOIT proposes two options: Option 1: Developers of the Transitional Projects negotiate and sign power purchase agreements (PPA) with Vietnam Electricity (EVN) within the price framework issued by the MOIT in accordance with the Law on Electricity, the Law on Prices, and their subordinate guiding legislation; or Option 2: The Prime Minister formulates a new decision specifying the mechanism for bidding on the purchase of power produced by the Transitional Projects, estimated to be implemented for the time limit of three years and within the price framework issued by the MOIT. Mechanism for future wind and solar power projects The MOIT proposes to apply the mechanism that developers of future wind and solar projects negotiate the power price and sign the PPA