Informed Counsel

Interim measures are necessary to protect the interests of a claimant in arbitral proceedings when speed is required in obtaining emergency interim relief. In many cases, urgent situations occur even before the filing of a notice of arbitration and the appointment of arbitrators. The institutional rules of the International Chamber of Commerce (ICC), Singapore International Arbitration Centre (SIAC), and Hong Kong International Arbitration Centre include provisions for the appointment of an emergency arbitrator (EA) to handle such emergency situations, and the EA is able to grant interim measures in situations where the arbitrator or the parties have not yet appointed an arbitral tribunal.

Emergency Arbitrator under Thai Arbitration Law   

The concept of an EA has not been incorporated into the rules of the Thai arbitral institutions, the Thailand Arbitration Institute (TAI) and the Thailand Arbitration Center (THAC). However, Thailand’s Arbitration Act B.E. 2545 (2002), which governs both domestic and international arbitration, does provide an interim mechanism under section 16, which allows arbitral applicants who have not yet filed a notice of arbitration to petition the court for interim measures, under the condition that, if the court orders accordingly, the applicant has to proceed with the arbitration within 30 days of the date of the order. Failure to initiate the arbitration causes the interim measures to be automatically revoked. Section 16 also allows an arbitral party that requires protection of their interests during pending proceedings to obtain interim measures. Thai courts will apply the Civil Procedure Code in respect of interim measures or emergency injunctions when considering whether to issue interim measures for the requesting party in the arbitration case, and if the court does grant interim measures, the requesting party will likely be ordered to put up a security fund accordingly.

Issuing Interim Measures in Thailand

Section 16 of the Thai Arbitration Act clearly states that the competent Thai court can issue interim measures, but the law is silent on whether an arbitral tribunal can do the same. To our knowledge, arbitrators have never granted an order or provisional award for interim measures in Thailand, regardless of the institutional rules being used in the arbitration. There could be two reasons. One is that the parties may have gone straight to the court to make such a request, as stipulated in section 16 of the Thai Arbitration Act; or the arbitrator could have recommended that the requesting party seek assistance from the court, which has the power to enforce interim measures as well, whereas the Supreme Court has apparently never ruled on the enforcement of an arbitral tribunal’s order on interim measures.

In the international context, the UNCITRAL Model Law on International Commercial Arbitration confirms that “an interim measure issued by an arbitral tribunal shall be recognized as binding and, unless otherwise provided by the arbitral tribunal, enforced upon application to the competent court, irrespective of the country in which it was issued.” It is very common for an arbitral tribunal to issue interim measures, which the local court can enforce accordingly. This seems to be contrary to Thailand’s situation, where the court holds the power to issue interim measures in the arbitral proceedings and enforce them.

In 2017, the TAI issued a new version of its arbitration rules. Article 39 of the 2017 TAI Arbitration Rules stipulates clearly that an arbitral tribunal may grant interim measures upon a party’s request. Article 39 also provides that a request to the arbitral tribunal for interim measures does not affect the right of the party to petition a court for interim measures as well. This is the first official indication that section 16 of the Thai Arbitration Act does not prevent the arbitral tribunal from issuing interim measures—in other words, that an arbitral tribunal in Thailand can issue interim measures. A local practitioner, though, would still recommend petitioning the court for interim measures. This would save time, since the court can enforce its order for interim measures at the same time. Although the arbitral tribunal’s order would be recognizable and enforceable, it could be challenged by the opposing party and revoked by the court.    

Unlike in Thailand, SIAC stipulates the authority of an EA in clause 12 of schedule 1. This clause also precludes the possibility of challenging the EA’s interim order in the local courts. This prevents a party from employing the tactic of using a local court to intervene in the arbitral tribunal’s discretion to issue an interim order. 

On the issue of whether Thailand should use an EA in cases involving the need for urgent interim measures before the appointment of the arbitral tribunal, one could argue that an EA is not necessary, because a court could grant an interim order, even before any party submits an application to initiate arbitration proceedings, under section 16 of the Thai Arbitration Act. However, the court would have to apply sections 253–270 of the Civil Procedure Code to issue emergency interim measures, and unlike the interim order of a SIAC EA, the interim order of a Thai court of first instance can be appealed by the opposing party and revoked or changed under section 45 of the Thai Arbitration Act. Thus, obtaining an interim order through a Thai court will use the same domestic litigation procedure. This could create complications and delays, and would not be confidential. Thus, having an EA would protect the interests of the requesting party in a timely and confidential manner, because the EA’s interim order could not be appealed. 

Concluding Thoughts

EAs do not yet exist in Thailand. Under section 16 of the Thai Arbitration Act, any party under an arbitration agreement may seek interim measures through the courts even before initiating a notice of arbitration. An interesting question to consider is whether an EA could be appointed and grant an interim order if an ICC or SIAC arbitration is conducted in Thailand, and whether that order would be considered enforceable by a Thai court.

Section 16 of the Thai Arbitration Act does not address the authority of an arbitral tribunal to issue interim measures. Article 39 of the recent TAI Arbitration Rules seems to indicate that an arbitral party can request an interim measure from either or both the arbitral tribunal and the court. Nevertheless, the Thai Arbitration Act and TAI rules do not provide for the appointment of an EA if emergency interim measures are needed before the arbitral tribunal is appointed. The amendment of section 16 of the Thai Arbitration Act to allow an EA to be appointed and issue interim orders would be a substantive change in Thailand’s arbitration law, but it would help boost the efficiency of arbitration proceedings.

RELATED INSIGHTS​ 

February 25, 2026
In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions. Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam. While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam. What’s New? Article 86.2 of the 2025 Law on Construction provides (emphasis added): “Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.” This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2. Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the
February 20, 2026
Thailand’s Supreme Administrative Court has issued a decisive ruling annulling the Ministry of Labor’s notification that had granted an exemption for foreign pilots to fly domestic routes under wet‑lease arrangements. A wet lease is a leasing arrangement in which the aircraft is provided together with its foreign flight crew, including pilots, and related operational support, rather than the airline supplying its own pilots. The judgment, delivered on November 17, 2025, and published in the Government Gazette on January 30, 2026, follows a legal challenge brought by the Thai Pilots Association, which argued that the exemption unlawfully enabled foreign workers to assume a role traditionally reserved for Thai nationals. The notification in question, dated December 13, 2024, authorized foreign pilots who came as part of wet‑leased aircraft to fly domestic routes. The Thai Pilots Association disputed the legality of this rationale, asserting that the exemption was triggered by a private airline’s request rather than by any statutory necessity. The Ministry of Labor justified this measure by relying on aircraft‑specific approvals issued by the Ministry of Transport and by enabling the Department of Employment to issue corresponding work permits. Arguments Presented in the Case The Thai Pilots Association argued that the exemption undermined the interests of domestic pilots and conflicted with the policy intent of Thailand’s foreign‑worker regulatory framework. The lawsuit emphasized that the notification arose directly from a private airline company’s request to operate two A320 aircraft under a wet lease and that the measure had the practical effect of displacing Thai pilots who remained unemployed. Meanwhile, the Ministry of Labor defended the exemption as a temporary and necessary response to industry shortages and part of national efforts to support tourism and restore aviation capacity. Legal Framework Thai law establishes a general prohibition against foreign nationals piloting domestic aircraft. Section
February 9, 2026
When unauthorized credit card transactions occur, who bears responsibility—the cardholder or the issuing bank? In Thailand, a landmark 2025 ruling by the country’s Supreme Court has clarified this question, establishing a stricter standard for banks in fraud disputes and significantly strengthening consumer protections. The case centered on disputed charges where a customer claimed their credit card had been used without authorization. The bank sued to recover the amount, and both the court of first instance and the Court of Appeal ruled in favor of the bank. However, the Supreme Court overruled their judgments and decided that the customer did not need to pay for the unauthorized transactions, placing liability squarely on the bank. This ruling was based on three key findings, which are outlined below. Finding 1: Insufficient Expert Testimony In this case, the bank bore the burden of proving matters related to the credit card system’s manufacture, design, security, and operation, as required under the Consumer Case Procedure Act B.E. 2551 (2008). To meet this requirement, the bank presented testimony from two employees in its credit card department regarding ’security measures and issuance procedures. However, the Supreme Court found these witnesses unqualified as experts, as they did not present technical or academic evidence and did not possess specialized expertise in credit card technology. As a result, their testimony failed to establish that the bank’s credit card technology was sufficiently secure against fraudulent misuse. Finding 2: Contradictory Terms and Conditions The bank’s own credit card terms and conditions included a provision acknowledging that despite the card’s EMV security standards, cardholders must still exercise caution to prevent unauthorized access. The Supreme Court interpreted this clause as an explicit admission that credit card systems remain vulnerable to hacking and fraud, even with high-level security measures in place. This acknowledgment undermined the
February 3, 2026
Thailand’s alternative dispute resolution (ADR) landscape has evolved significantly over the past decade. Legislative reforms such as the Dispute Mediation Act and expanded court‑annexed mediation have strengthened non‑litigious options, while institutional choices have broadened. Parties can now choose between the Thai Arbitration Institute (TAI), the Thailand Arbitration Center (THAC), and a growing number of sector‑specific dispute forums. For businesses, these choices matter. Each forum has different rules, administration, costs, speed, and enforcement mechanisms. These factors can directly impact commercial leverage, recovery outcomes, and business continuity. Choosing the right forum and drafting an effective dispute resolution clause can materially influence how a dispute is resolved. This article outlines the practical differences between Thailand’s leading alternative dispute resolution forums, explains when each is likely to deliver the most value, and offers drafting and strategy tips to embed those advantages into your dispute resolution clauses. Why ADR Is Gaining Traction in Thailand Thai policy increasingly supports the resolution of civil and commercial disputes through ADR. Recent amendments to the Civil Procedure Code now provide for court-supervised pre-action and in-case mediation. This type of mediation has its advantages: it suspends limitation periods, involves no court fees, and can conclude with a consent judgment that is immediately enforceable and subject to only limited grounds of appeal. In parallel, the Mediation Act supports out‑of‑court mediation for qualifying disputes within defined subject‑matter and monetary thresholds. Valid settlement agreements reached under this law may be enforced through a streamlined court process. Thailand’s arbitration framework has also matured into a reliable, pro‑enforcement framework under the Arbitration Act, which closely follows the UNCITRAL Model Law and applies to both domestic and international cases, so cross‑border users see familiar rules. As Thailand is a signatory to the New York Convention, Thai courts generally recognize and enforce foreign awards subject only