Decommissioning Offshore Oil and Gas Installations in Thailand

Informed Counsel

Thailand’s Ministry of Energy promulgated the Ministerial Regulation Prescribing Plan and Estimated Cost and Security for Decommissioning of Installations Used in the Petroleum Industry B.E. 2559 (2016) earlier this year. As the specific rules and procedures governing the end of the life cycle for upstream petroleum projects had been somewhat uncertain, the decommissioning regulation adds a great deal of clarity on legal obligations for concessionaires.

Unlike businesses with perpetual growth potential, upstream petroleum production has a limited project life cycle—since oil and gas are not renewable resources, every project will have a finite timetable. The tail end of the production cycle is also generally when fewer barrels of oil are being produced, which, to the detriment of petroleum producers, coincides with the capital-intensive task of decommissioning various installations.

A common misconception about offshore drilling rigs is that at the end of the production cycle they will retain some monetary value. This seems intuitive, since it can be assumed that, at the very least, the metal which has been used to construct the installations could be melted down for scrap. But these materials have endured the corrosive effects of seawater over several decades, and the logistical expenses of retrieving the salvageable material are extraordinary. The reality is that the decommissioning of offshore rigs is extremely costly and does not generally enable the petroleum producer to realize any return on the physical assets.

Since the costly endeavor of decommissioning will occur precisely at the moment in the production cycle when revenues will be decreasing, petroleum producers and governments must design appropriate procedures to ensure that decommissioning work is properly carried out. Policy issues of major concern for host governments include protecting the environment, minimizing the impact on fisheries, and ensuring that shipping lanes remain clear of any obstacles. Although offshore petroleum production has been occurring around the world for decades, decommissioning is increasing in importance globally as more projects near the end of their life cycles. Accordingly, lawmakers everywhere are still in the process of learning what processes are best employed to achieve the desired policy objectives.

In Thailand, the Petroleum Act was amended in 2007, introducing two sections which provide the Director General of the Department of Mineral Fuels with the authority to prescribe regulations concerning decommissioning activities. Section 80/1 of the Petroleum Act outlines the general rule that the concessionaire will be responsible for decommissioning works, while Section 80/2 is concerned with the requirement of the concessionaire to make a security deposit to ensure that it will be financially responsible for those decommissioning works. The specific procedures, rules, and timelines outlined under Sections 80/1 and 80/2 of the Petroleum Act are to be in accordance with Ministerial Regulations.

The decommissioning regulation requires the concessionaire to submit a Decommissioning Plan (divided into an Initial Decommissioning Plan and a Final Decommissioning Plan), an Estimate of Decommissioning Costs, a Decommissioning Environmental Assessment Report, and a Best Practical Environmental Option Report to the Director General within prescribed timelines.

The obligation of the concessionaire to begin the decommissioning process will be triggered by any of the following:

  1. when the concessionaire does not use the installations continuously for more than one year;
  2. when petroleum reserves of the concession are less than 40 percent of the sum of the accumulated petroleum production and the petroleum reserves;
  3. when the remaining time for petroleum production as specified in the concession is five years; or
  4. if the concessionaire wishes to commence decommissioning activities.

The Estimated Decommissioning Costs and Decommissioning Plan must be audited by authorized third parties based on qualifications prescribed by the Director General and published in the Government Gazette. The Director General has the authority to accept the decommissioning reports or request clarifications and/or amendments if the reports are not in compliance with the prescribed rules.

The concessionaire will be obligated to make a security deposit to the Director General, which may be in the form of cash or a cashier check payable by a bank, Thai government bonds, a letter of guarantee issued by a bank, an irrevocable standby letter of credit, or any other security prescribed by the Director General and announced in the Government Gazette. The security deposit will be for an amount approved by the Director General which must not be less than the Estimated Decommissioning Cost. Failure to make a complete security deposit will result in a written warning from the Director General, and exposure to a surcharge of 2 percent per month of the unpaid amount.

The decommissioning regulation leaves a few rules and procedures open, to be determined later by the Director General. In addition, depending on how the decommissioning regulation is implemented in practice, there may still be room for further minor amendments. In general, the decommissioning regulation provides a great deal of clarity and certainty for petroleum producers working on concessions which are nearing the end of their production lifespan.

RELATED INSIGHTS​ 

January 27, 2025
Thailand’s Ministry of Energy (MOE) has announced the launch of the 25th bidding round for petroleum exploration and production. This round offers nine greenfield onshore blocks—seven in northeastern Thailand and two in central Thailand—encompassing over 33,000 km². The bids can be submitted from July 1 to July 16, 2025. The sizes and locations of these blocks are: Northeast Thailand Block L1/66: 3,223.51 km² (Khon Kaen, Nong Bua Lam Phu, Udon Thani) Block L2/66: 3,917.03 km² (Kalasin, Sakon Nakhon, Udon Thani) Block L3/66: 3,918.22 km² (Kalasin, Khon Kaen, Maha Sarakham, Udon Thani) Block L4/66: 3,656.65 km² (Amnat Charoen, Mukdahan, Nakhon Phanom, Yasothon) Block L5/66: 3,436.01 km² (Chaiyaphum, Khon Kaen, Nakhon Ratchasima) Block L7/66: 3,438.51 km² (Buri Ram, Maha Sarakham, Nakhon Ratchasima, Roi Et, Surin, Khon Kaen) Block L9/66: 3,885.44 km² (Nakhon Ratchasima) Central Thailand Block L6/66: 3,966.86 km² (Chaiyaphum, Lop Buri, Phetchabun) Block L8/66: 3,957.41 km² (Kanchanaburi, Nakhon Pathom, Ratchaburi, Suphan Buri) Bidding Process Interested companies must submit their bids to the Department of Mineral Fuels (DMF) between July 1 and July 16, 2025. Bids should include: Application form (ChorThor/Por1) Proof of eligibility: Corporate documentation, audited financial statements, and proof of resources Technical and commercial proposals: Exploration plans, geological surveys, financial and work commitments, and special benefits such as signing bonuses of at least USD 100,000. There is a nonrefundable THB 50,000 application fee per block, and applicants must provide a bid bond of THB 3 million per block via an unconditional bank guarantee from a commercial bank with branches in Thailand, valid for at least one year from the bidding submission date. The guarantee will be returned to unsuccessful bidders upon request and to successful bidders upon the signing of the concession agreement. Eligibility Bidders must meet the following main eligibility criteria: Bidders must be limited companies with the following qualifications: The company must have the objective of
January 23, 2025
In 2023, compliance inspections by Vietnam’s Government Inspectorate identified several violations of policies and laws in the management and implementation of planning and investment in renewable energy projects. Since then, many renewable energy enterprises and projects have encountered significant operational challenges. In December 2024, the Ministry of Industry and Trade (MOIT) issued two reports, Report 321/BC-BCT and Report 345/BC-BCT, to implement the 2023 Inspection Conclusion of the Government Inspectorate and address obstacles faced by renewable energy enterprises, Investors in renewable energy projects in Vietnam should carefully consider the potential impacts of proposed solutions in these reports. The reports re-emphasize the types of violations related to renewable energy projects identified in the Inspection Conclusion, with a significant expansion in the number of affected projects. Key violations include: (i) misapplication of FIT (feed-in tariff) incentives; (ii) recognition of COD (commercial operation date) and receipt of FIT prices without written approval of construction acceptance; (iii) overlap with mineral planning, irrigation planning, national defense land use, or other restricted land uses; (iv) incomplete land procedures and documentation; and (v) installation of rooftop solar on agricultural and forestry land used for farming and aquaculture models. Further, these reports mention the government’s solutions to resolve difficulties for renewable energy projects, which include: Allowing additional planning where projects do not violate national security. Allowing rectification of projects’ violations in land and construction process as per law. For projects violating planning on minerals, irrigation, or defense, socio-economic efficiency will be assessed for adjustments or integration. Adjusting electricity prices and recovering incorrect FIT prices for projects not meeting conditions. Requiring rooftop solar projects on non-farming land to comply with regulations or, if land violations occur, FIT prices will be revoked, and electricity prices must be redetermined and recovered. For items (iv) and (v), the authority will issue regulations
January 14, 2025
Thailand’s Department of Industrial Works (DIW) has issued a new regulation (Ministerial Regulation Re: Designation of Type, Kind, and Size of Factories (No. 3) B.E. 2567 (2024)), which removes the factory license requirement for electricity generation from solar energy installations on rooftops, roof decks, or any part of a building used for residential or other purposes, regardless of capacity. The new rules took effect on December 28, 2024. Under the previous regulations, solar rooftop installations had to seek approval from the DIW if their capacity exceeded 1,000 kW (1 MW), which added time and administrative costs when adopting renewable energy solutions. Benefits and Further Compliance The updated regulation benefits industrial operators by facilitating faster installation times and lower costs, as solar rooftops can now be installed without the need for prior approval of a factory license from the DIW. Operators can now more easily contribute to environmental sustainability and carbon reduction efforts. Despite the lifting of the factory licensing requirement, other compliance obligations, such as an energy business license (or exemption from an energy business license), a controlled energy production license, and a construction permit, may still apply. Reason for the Change Removing the classification of rooftop or building-installed solar power plants as factories aligns with Thailand’s renewable energy goals and reduces regulatory burdens for industrial operators. Additionally, it supports the achievement of energy policies aligned with the UN’s Sustainable Development Goals and Thailand’s international commitments to reduce greenhouse gas emissions through the participation of all sectors. For further details on how this change affects business operations or to explore strategies for renewable energy implementation, please contact Supasit Boonsanong at [email protected], Charuwan Charoonchitsathian at [email protected], or Phareeya Yongpanich at [email protected].
December 4, 2024
Thailand Legal Basics, a valuable primer for foreign investors, explores all aspects of living and doing business in Thailand. Written by specialists at Tilleke & Gibbins in Bangkok, it is the only comprehensive English-language guide to the Thai legal system with a focus on the concerns of foreign business and investment.