August 26, 2016

Decommissioning Offshore Oil and Gas Installations in Thailand

Informed Counsel

Thailand’s Ministry of Energy promulgated the Ministerial Regulation Prescribing Plan and Estimated Cost and Security for Decommissioning of Installations Used in the Petroleum Industry B.E. 2559 (2016) earlier this year. As the specific rules and procedures governing the end of the life cycle for upstream petroleum projects had been somewhat uncertain, the decommissioning regulation adds a great deal of clarity on legal obligations for concessionaires.

Unlike businesses with perpetual growth potential, upstream petroleum production has a limited project life cycle—since oil and gas are not renewable resources, every project will have a finite timetable. The tail end of the production cycle is also generally when fewer barrels of oil are being produced, which, to the detriment of petroleum producers, coincides with the capital-intensive task of decommissioning various installations.

A common misconception about offshore drilling rigs is that at the end of the production cycle they will retain some monetary value. This seems intuitive, since it can be assumed that, at the very least, the metal which has been used to construct the installations could be melted down for scrap. But these materials have endured the corrosive effects of seawater over several decades, and the logistical expenses of retrieving the salvageable material are extraordinary. The reality is that the decommissioning of offshore rigs is extremely costly and does not generally enable the petroleum producer to realize any return on the physical assets.

Since the costly endeavor of decommissioning will occur precisely at the moment in the production cycle when revenues will be decreasing, petroleum producers and governments must design appropriate procedures to ensure that decommissioning work is properly carried out. Policy issues of major concern for host governments include protecting the environment, minimizing the impact on fisheries, and ensuring that shipping lanes remain clear of any obstacles. Although offshore petroleum production has been occurring around the world for decades, decommissioning is increasing in importance globally as more projects near the end of their life cycles. Accordingly, lawmakers everywhere are still in the process of learning what processes are best employed to achieve the desired policy objectives.

In Thailand, the Petroleum Act was amended in 2007, introducing two sections which provide the Director General of the Department of Mineral Fuels with the authority to prescribe regulations concerning decommissioning activities. Section 80/1 of the Petroleum Act outlines the general rule that the concessionaire will be responsible for decommissioning works, while Section 80/2 is concerned with the requirement of the concessionaire to make a security deposit to ensure that it will be financially responsible for those decommissioning works. The specific procedures, rules, and timelines outlined under Sections 80/1 and 80/2 of the Petroleum Act are to be in accordance with Ministerial Regulations.

The decommissioning regulation requires the concessionaire to submit a Decommissioning Plan (divided into an Initial Decommissioning Plan and a Final Decommissioning Plan), an Estimate of Decommissioning Costs, a Decommissioning Environmental Assessment Report, and a Best Practical Environmental Option Report to the Director General within prescribed timelines.

The obligation of the concessionaire to begin the decommissioning process will be triggered by any of the following:

  1. when the concessionaire does not use the installations continuously for more than one year;
  2. when petroleum reserves of the concession are less than 40 percent of the sum of the accumulated petroleum production and the petroleum reserves;
  3. when the remaining time for petroleum production as specified in the concession is five years; or
  4. if the concessionaire wishes to commence decommissioning activities.

The Estimated Decommissioning Costs and Decommissioning Plan must be audited by authorized third parties based on qualifications prescribed by the Director General and published in the Government Gazette. The Director General has the authority to accept the decommissioning reports or request clarifications and/or amendments if the reports are not in compliance with the prescribed rules.

The concessionaire will be obligated to make a security deposit to the Director General, which may be in the form of cash or a cashier check payable by a bank, Thai government bonds, a letter of guarantee issued by a bank, an irrevocable standby letter of credit, or any other security prescribed by the Director General and announced in the Government Gazette. The security deposit will be for an amount approved by the Director General which must not be less than the Estimated Decommissioning Cost. Failure to make a complete security deposit will result in a written warning from the Director General, and exposure to a surcharge of 2 percent per month of the unpaid amount.

The decommissioning regulation leaves a few rules and procedures open, to be determined later by the Director General. In addition, depending on how the decommissioning regulation is implemented in practice, there may still be room for further minor amendments. In general, the decommissioning regulation provides a great deal of clarity and certainty for petroleum producers working on concessions which are nearing the end of their production lifespan.

RELATED INSIGHTS​ 

June 25, 2025
In April 2025, a massive power outage plunged Portugal, Spain, and parts of southwestern France into darkness for up to ten hours. As Thailand advances its energy transition by increasing renewable integration and regional interconnections, the European blackout serves as a stark reminder of the grid vulnerabilities that still exist. In this first article of a three-part series, energy specialists from Tilleke & Gibbins examine the root causes of the outage in the Iberian Peninsula.
May 28, 2025
Tilleke & Gibbins attorneys in Vietnam have contributed the 2025 edition of Doing Business in Vietnam, a comprehensive Q&A-style resource from Thomson Reuters Practical Law that provides essential insights for companies navigating business operations in Vietnam. The guide presents a detailed overview of the country’s legal framework and regulatory environment, reflecting recent updates in Vietnamese legislation and practice. This annually updated guide offers key information on the following areas: Legal system: Structure of the Vietnamese judiciary and the role of codified law. Foreign investment: Conditions for market access, licensing requirements, foreign ownership restrictions, and investment incentives. Business vehicles: Formation and operation of legal entities, including limited liability companies, joint-stock companies, and representative offices. Employment: Employment contracts, social insurance, labor rights, and procedures for hiring foreign nationals. Tax: Overview of corporate income tax, personal income tax, value-added tax, and other tax obligations. Intellectual property: Procedures for protecting and enforcing patents, trademarks, copyrights, and other IP rights. Data protection: Compliance requirements under Vietnam’s data privacy laws, including the Personal Data Protection Decree. Competition law: Antitrust rules and regulatory oversight under the Law on Competition. Anti-bribery and corruption: Legal framework and enforcement practices aimed at curbing corrupt activities. E-commerce and digital business: Regulations governing online platforms, digital content, and cross-border services. Marketing and advertising: Laws and guidelines on advertising standards and consumer protection. Product regulation and liability: Safety requirements, product liability issues, and roles of relevant authorities. Doing Business in Vietnam is part of Practical Law’s global series of legal guides designed to support international practitioners and businesses. To access the most recent edition of the Vietnam guide, visit the Practical Law website and sign up for a free trial.
May 2, 2025
Attorneys from Tilleke & Gibbins have updated the latest edition of Doing Business in Thailand, a Q&A-style guide from Thomson Reuters Practical Law that offers an overview of key legal considerations for companies operating in jurisdictions worldwide. The contribution outlines the country’s legal and regulatory framework for foreign investment and business operations and reflects the latest legislative developments. The chapter addresses the following core topics: Legal system: Structure of the courts and the codified nature of Thai law. Foreign investment: Business restrictions under the Foreign Business Act, sector-specific regulations, exchange control rules, and investment incentives. Business vehicles: Overview of partnerships, private and public limited companies, and other legal entities. Employment: Labor protections, employment contracts, foreign worker requirements, and termination procedures. Tax: Corporate and personal income tax, indirect taxes, and tax obligations for residents and non-residents. Intellectual property: Registration and enforcement of patents, trademarks, designs, and copyrights. Data protection: Key provisions of the Personal Data Protection Act and related compliance obligations. Competition law: Regulatory framework under the Trade Competition Act. Anti-bribery and corruption: Relevant legislation and enforcement mechanisms. E-commerce and digital business: Legal regime for online transactions and digital platforms. Marketing and advertising: Consumer protection laws and regulations affecting advertising and marketing practices. Product regulation and liability: Safety standards, liability regimes, and roles of enforcement authorities. Practical Law, a legal reference resource from Thomson Reuters, publishes a range of guides for hundreds of jurisdictions and practice areas. The insurance and reinsurance guide is a valuable resource for legal practitioners, covering numerous jurisdictions worldwide. To view the latest version of the guide, please visit the Practical Law website and enroll in the free Practical Law trial to gain full access.
April 10, 2025
On March 3, 2025, the government of Vietnam issued Decree No. 57/2025/ND-CP, regulating the direct power purchase agreement (DPPA) mechanism between renewable energy generators and large electricity consumers (“Decree 57”). Decree 57 took immediate effect and replaces Decree No. 80/2024/ND-CP on the same subject. The new regulations enable investors to kickstart their investment plans for DPPAs in Vietnam. Below are the key changes and provisions of Decree 57. Participants in On-Grid DPPAs Decree 57 expands the eligibility criteria for participating in DPPAs via the national grid (on-grid DPPAs): Sellers: In addition to wind and solar power generators, biomass energy generators with a capacity of 10 MW or more can now participate. Buyers: Electric vehicle charging businesses are now eligible to participate, broadening the scope beyond just production businesses. Large Electricity Consumers Instead of setting definite criteria at the government decree level, Decree 57 defines large electricity consumers based on average electricity consumption as set out in wholesale electricity market regulations to be issued by the Ministry of Industry and Trade (MOIT). Although the threshold for DPPA participation remains for now at 200,000 kWh per month, Decree 57 will allow the MOIT to adjust this threshold as deemed necessary. Decree 57 also provides specific guidance for large electricity consumers based on their consumption period. To participate in both private off-grid DPPA (selling electricity directly via a grid system separate from the national grid) and on-grid DPPA models, large electricity consumers must meet the minimum threshold for electricity consumption set by the MOIT under the Vietnam wholesale electricity market regulations (“Minimum Consumption Threshold”). Consumers with a consumption history of at least 12 months must have already met the Minimum Consumption Threshold at the time of registration or notification, while those whose consumption period is less than 12 months must commit to