Decommissioning Offshore Oil and Gas Installations in Thailand

Informed Counsel

Thailand’s Ministry of Energy promulgated the Ministerial Regulation Prescribing Plan and Estimated Cost and Security for Decommissioning of Installations Used in the Petroleum Industry B.E. 2559 (2016) earlier this year. As the specific rules and procedures governing the end of the life cycle for upstream petroleum projects had been somewhat uncertain, the decommissioning regulation adds a great deal of clarity on legal obligations for concessionaires.

Unlike businesses with perpetual growth potential, upstream petroleum production has a limited project life cycle—since oil and gas are not renewable resources, every project will have a finite timetable. The tail end of the production cycle is also generally when fewer barrels of oil are being produced, which, to the detriment of petroleum producers, coincides with the capital-intensive task of decommissioning various installations.

A common misconception about offshore drilling rigs is that at the end of the production cycle they will retain some monetary value. This seems intuitive, since it can be assumed that, at the very least, the metal which has been used to construct the installations could be melted down for scrap. But these materials have endured the corrosive effects of seawater over several decades, and the logistical expenses of retrieving the salvageable material are extraordinary. The reality is that the decommissioning of offshore rigs is extremely costly and does not generally enable the petroleum producer to realize any return on the physical assets.

Since the costly endeavor of decommissioning will occur precisely at the moment in the production cycle when revenues will be decreasing, petroleum producers and governments must design appropriate procedures to ensure that decommissioning work is properly carried out. Policy issues of major concern for host governments include protecting the environment, minimizing the impact on fisheries, and ensuring that shipping lanes remain clear of any obstacles. Although offshore petroleum production has been occurring around the world for decades, decommissioning is increasing in importance globally as more projects near the end of their life cycles. Accordingly, lawmakers everywhere are still in the process of learning what processes are best employed to achieve the desired policy objectives.

In Thailand, the Petroleum Act was amended in 2007, introducing two sections which provide the Director General of the Department of Mineral Fuels with the authority to prescribe regulations concerning decommissioning activities. Section 80/1 of the Petroleum Act outlines the general rule that the concessionaire will be responsible for decommissioning works, while Section 80/2 is concerned with the requirement of the concessionaire to make a security deposit to ensure that it will be financially responsible for those decommissioning works. The specific procedures, rules, and timelines outlined under Sections 80/1 and 80/2 of the Petroleum Act are to be in accordance with Ministerial Regulations.

The decommissioning regulation requires the concessionaire to submit a Decommissioning Plan (divided into an Initial Decommissioning Plan and a Final Decommissioning Plan), an Estimate of Decommissioning Costs, a Decommissioning Environmental Assessment Report, and a Best Practical Environmental Option Report to the Director General within prescribed timelines.

The obligation of the concessionaire to begin the decommissioning process will be triggered by any of the following:

  1. when the concessionaire does not use the installations continuously for more than one year;
  2. when petroleum reserves of the concession are less than 40 percent of the sum of the accumulated petroleum production and the petroleum reserves;
  3. when the remaining time for petroleum production as specified in the concession is five years; or
  4. if the concessionaire wishes to commence decommissioning activities.

The Estimated Decommissioning Costs and Decommissioning Plan must be audited by authorized third parties based on qualifications prescribed by the Director General and published in the Government Gazette. The Director General has the authority to accept the decommissioning reports or request clarifications and/or amendments if the reports are not in compliance with the prescribed rules.

The concessionaire will be obligated to make a security deposit to the Director General, which may be in the form of cash or a cashier check payable by a bank, Thai government bonds, a letter of guarantee issued by a bank, an irrevocable standby letter of credit, or any other security prescribed by the Director General and announced in the Government Gazette. The security deposit will be for an amount approved by the Director General which must not be less than the Estimated Decommissioning Cost. Failure to make a complete security deposit will result in a written warning from the Director General, and exposure to a surcharge of 2 percent per month of the unpaid amount.

The decommissioning regulation leaves a few rules and procedures open, to be determined later by the Director General. In addition, depending on how the decommissioning regulation is implemented in practice, there may still be room for further minor amendments. In general, the decommissioning regulation provides a great deal of clarity and certainty for petroleum producers working on concessions which are nearing the end of their production lifespan.

RELATED INSIGHTS​ 

August 2, 2022
The Ministry of Energy is preparing to open a bidding round for the right to explore and produce petroleum in three offshore exploration blocks in the Gulf of Thailand: Exploration Block Nos. G1/65, G2/65, and G3/65. Announced in April 2022 with an eye toward national energy sustainability and security, this is the first opportunity for exploration of new offshore areas in 15 years. The total area of the three exploration blocks is 35,164.01 square kilometers, and operations in the exploration blocks will be subject to the terms and conditions of the required production sharing contract (PSC). Under the PSC, the Thai government is entitled to receive royalty payments against profits, any applicable cost recovery, and profit petroleum. The government also has the authority to monitor the petroleum operations in collaboration with the successful bidder. On July 27, 2022, the Department of Mineral Fuels (DMF) held a conference for prospective investors in order to clarify general information regarding the petroleum bidding round. Currently, interested investors can request the right to enter the bidding-round data room located at the DMF by emailing [email protected] by September 2, 2022. To participate in the bidding round, interested investors must submit an application together with required documents to the DMF during the period of September 5–16, 2022. For further information on the bidding round, or on any aspect of energy law in Thailand, please contact Tilleke & Gibbins at [email protected] or +66 2056 5555.
February 28, 2022
On February 9, 2022, the Director-General of the Department of Mineral Fuels (DMF) stated that the DMF is planning to request that the Deputy Prime Minister and the Minister of Energy sign an invitation to open bids for Petroleum Exploration and Production Licenses in the Gulf of Thailand for the first time in 15 years. The DMF’s Chief Department expects that this auction, which will cover three offshore areas, could increase Thailand’s petroleum reserves, and it could lead to the possible discovery of new sources of petroleum for Thailand, which would boost the country’s energy resources, and reduce losses from energy imports. The plots in the Gulf of Thailand that will be auctioned in the 24th bid round are as follows: Plot No. G1/65 with a total area of 8,487 square kilometers. This area is divided into 2 sub-areas: Area A totaling 8,298.49 square kilometers, and Area B totaling 188.71 square kilometers; Plot G2/65 with a total area of 15,030 square kilometers; and Plot No. G3/65 with a total area of 11,646.67 square kilometers. This area is divided into 2 sub-areas: Area A totaling 11,028.22 square kilometers, and Area B totaling 618.45 square kilometers. Generally, Thailand initiates its concession and production sharing contract process with the announcement of an exploration area or a plot in the Government Gazette. Thereafter, the DMF Committee will consider and announce the invitation, so that private sector firms can submit their applications to receive respective rights. The DMF’s sub-committee will consider the applications by: checking the qualifications stipulated under Section 24 of the Petroleum Act; assessing the suitability of the exploration project; and determining the benefits which are offered by the applicant. After considering the requests, the DMF’s sub-committee will consider the petroleum laws and regulations, before submitting the matter to the Petroleum Committee—under
February 22, 2022
The many new and unique challenges in recent years—from epidemics, to travel restrictions, to supply chain disruptions and energy-related reactions to all of the above, we have all had to adjust to a new status quo. The energy industry has felt these impacts acutely, and as the industry seeks to meet the current challenges and move forward toward a more sustainable future, it is helpful to take stock of where things stand and where they might be headed in the coming years. In the midst of this uncertainty, Energy Law in Southeast Asia by the Tilleke & Gibbins Energy Industry Team seeks to provide clarity on the legal and regulatory environment surrounding energy industry activities. Each chapter of Energy Law in Southeast Asia takes the reader through the essential information surrounding energy and environmental regulations in general and the specific laws and practices for the major areas of energy projects—both in terms of the current energy mix and the sources taking on a larger role as we transition toward a lower-carbon future. These chapter subsections are: Regulatory Structure Oil and Gas Coal Solar Wind Hydropower Biomass and Biogas Environmental Regulations In providing this legal overview of major areas across the spectrum of energy projects in Southeast Asia, we have sought to create a resource for all involved in the energy industry, regardless of their specific area of interest or the different obstacles or challenges they seek to resolve. Energy Law in Southeast Asia is written by specialists on Tilleke & Gibbins’ Energy Industry Team, who together have over 200 years of accumulated energy experience. Spread throughout Tilleke & Gibbins’ offices in Southeast Asia, they function both as an integrated regional team to advise multinational enterprises on their regional energy project portfolios, and as experts for investors and companies looking
January 27, 2022
The Energy Generating Authority of Thailand (EGAT) has launched a pilot project to study the energy consumption and the economic, social, and environmental impact of electric motorcycle taxis, as well as the behavior of drivers and passengers. The project, which was launched on December 27, 2021, as part of EGAT’s Carbon Neutrality Policy, will continue for a year, after which EGAT will consider the data and decide whether electric motorcycle taxis should be introduced nationwide. EGAT is also currently encouraging the use of electric bikes within their own organization, and they initially expect this to help reduce annual carbon dioxide emissions by 37 tons and prevent the release of about 838,000 milligrams of dust per year. EGAT expects additional significant reductions from electric motorcycle taxi pilot projects in multiple locations. A study conducted in Kenya in 2015 by that country’s energy regulator found that sub-150cc motorcycles emit approximately 46.5 grams of carbon dioxide per kilometer, and these emissions increase proportionally in accordance with engine size. According to Thailand’s Office of Industrial Economics, citing data collected by the Federation of Thai Industries Automotive Industry Group, a total of 1,516,096 motorcycles were sold in Thailand in 2020—a surprisingly robust figure in light of the impact of the COVID-19 pandemic. Assuming that public motorcycles travel an average of 15,000 kilometers per year, each motorcycle is therefore producing approximately 0.7 tons of carbon dioxide per year. If Thailand is able to change 50% of its yearly sales of standard motorcycle to electric motorcycles, annual carbon dioxide emissions could decrease by approximately 530,000 tons. Furthermore, since 28.8% of carbon dioxide emissions in Thailand are generated from the transport sector, the transition to electric mobility vehicles looks to be one of the most promising solutions for lowering carbon dioxide emissions in the country. Considering developments