Clear Guidance for Direct Power Purchase Agreements in Vietnam

On March 3, 2025, the government of Vietnam issued Decree No. 57/2025/ND-CP, regulating the direct power purchase agreement (DPPA) mechanism between renewable energy generators and large electricity consumers (“Decree 57”). Decree 57 took immediate effect and replaces Decree No. 80/2024/ND-CP on the same subject. The new regulations enable investors to kickstart their investment plans for DPPAs in Vietnam. Below are the key changes and provisions of Decree 57.

Participants in On-Grid DPPAs

Decree 57 expands the eligibility criteria for participating in DPPAs via the national grid (on-grid DPPAs):

  • Sellers: In addition to wind and solar power generators, biomass energy generators with a capacity of 10 MW or more can now participate.
  • Buyers: Electric vehicle charging businesses are now eligible to participate, broadening the scope beyond just production businesses.

Large Electricity Consumers

Instead of setting definite criteria at the government decree level, Decree 57 defines large electricity consumers based on average electricity consumption as set out in wholesale electricity market regulations to be issued by the Ministry of Industry and Trade (MOIT). Although the threshold for DPPA participation remains for now at 200,000 kWh per month, Decree 57 will allow the MOIT to adjust this threshold as deemed necessary.

Decree 57 also provides specific guidance for large electricity consumers based on their consumption period. To participate in both private off-grid DPPA (selling electricity directly via a grid system separate from the national grid) and on-grid DPPA models, large electricity consumers must meet the minimum threshold for electricity consumption set by the MOIT under the Vietnam wholesale electricity market regulations (“Minimum Consumption Threshold”). Consumers with a consumption history of at least 12 months must have already met the Minimum Consumption Threshold at the time of registration or notification, while those whose consumption period is less than 12 months must commit to meeting the Minimum Consumption Threshold.

For continued participation in the DPPA model in subsequent years, one of the following conditions must be met:

  • The total period of DPPA implementation is less than 12 months; or
  • The consumer’s average electricity consumption between November 1 of the preceding year and October 31 of the current year meets or exceeds the Minimum Consumption Threshold.

Private Off-Grid DPPAs

Decree 57 introduces detailed rules related to private off-grid DPPAs, including, among others, the following:

  • Rooftop solar power generators are entitled to sell surplus electricity provided it does not exceed 20% of the total actual generated electricity.
  • While parties can agree on the selling price of electricity, Decree 57 mandates that the price cannot exceed a ceiling price within the price bracket for the corresponding type of power source. This price bracket (to be approved and published by the MOIT annually) is calculated using a statutory formula that considers average fixed prices, operation and maintenance costs, and other variable expenses.

DPPA Contracts

Decree 57 provides clearer regulations for private off-grid DPPA and on-grid DPPA contracts.

For private off-grid DPPAs, renewable energy generators and large electricity consumers will enter into a power purchase agreement that has no mandatory template, under which the generator will sell electricity to the consumer at a price they both agree upon. The electricity price may be negotiated, but it must fall below the ceiling price for the relevant power source as specified by the price bracket.

In the on-grid DPPA framework, there are three types of contracts:

  • EVN Power Purchase Agreement (EVN PPA): Under this agreement, renewable energy generators will sell their entire generation output to the national power corporation, Vietnam Electricity (EVN), in the spot market, with payments based on the spot price for immediate delivery.
  • Customer Power Purchase Agreement (Customer PPA): This contract between a customer and the power corporation covers the customer’s total electricity needs. The agreement includes charges for electricity (at wholesale spot price), service fees, adjustments, and costs for electricity purchased to cover any shortfall in generation (at retail price). EVN is required to update and report to the MOIT the applicable costs for 2025, including system service usage, clearing settlement, and distribution grid energy loss conversion factors, before the costs are published on the electricity market website. This will facilitate investors to run financial models for investments in on-grid DPPAs.
  • Forward Contract (or Contract for Differences): Renewable energy generators and customers enter into a contract specifying the committed price and consumption ratio. The contract’s revenue is determined by the difference between the committed price and the spot price.

Details of these three contracts are specified in the appendices of Decree 57.

Adding Terms to Statutory Template Contracts

Under Decree 57, renewable energy generators, large electricity consumers, and EVN have the right to supplement the statutory templates for power purchase agreements and other agreements with additional terms and content to clarify the rights and obligations of the parties, provided that such additional terms do not contradict relevant legal provisions.

RELATED INSIGHTS​ 

August 31, 2022
Thailand’s Draft Climate Change Act Countries around the world have given significant attention to climate change legislation, with many national, regional, and global attempts to slow the momentum of climate change. The most notable of these multilateral efforts is the Paris Agreement, a legally binding international treaty on climate change currently adopted by 193 parties. Its goal is to limit the global average temperature to well below 2°C (preferably below 1.5°C) above preindustrial levels, and the treaty’s coordinated efforts to combat climate change are much more ambitious than previous global agreements and discussions. Article 4 of the Paris Agreement requires countries to provide “nationally determined contributions” (NDCs), consisting of their action plans for climate action. Thailand, as a party to the Paris Agreement, has put forth an NDC that pledges to achieve an unconditional greenhouse gas (GHG) emission reduction target of 20% from the business-as-usual projection for 2030, with the possibility of increasing that target to 25% subject to adequate and enhanced access to technology development and transfer, financial resources, and other support. To enable the accomplishment of this pledge, Thailand is looking to enact climate change legislation that functions as a key mechanism for domestic climate action. In 2018, the Office of Natural Resources and Environmental Policy and Planning (ONEP) under the Ministry of Natural Resources and Environment was assigned to prepare a draft Climate Change Act. The draft is now complete, and according to news reports it is set to be submitted to the cabinet for further consideration. The draft Climate Change Act lays out Thailand’s action plan for climate change mitigation and adaptation, including emissions reductions. Some of the key sections in the draft law involve citizen rights, the National Climate Change Policy Committee, and a national GHG database. Rights of Citizens The draft establishes the
August 26, 2022
Thailand’s Board of Investment (BOI) has extended its previously announced period for reduction of import duty on imported raw and essential materials for battery manufacturing for electric vehicles and other applications. The BOI’s announcement No. 5/2565 dated August 8, 2022, extended the reduction period to a maximum of five years. The BOI’s promoted activities list includes two battery-manufacturing business activities: Activity 4.8.3.1 – Battery manufacturing Activity 5.2.6.1 – High energy density battery manufacturing Qualifying battery manufacturers who have cell or module manufacturing processes are eligible for 90% import duty reductions on raw and essential materials that cannot be produced in Thailand. These reductions will be available on an annual basis, and are renewable for five years in total—up from the original two years. Existing projects (i.e., those which have the original two-year duration in their BOI certificate) can also benefit from the extension by preparing a project amendment form, along with a clarification letter and supporting documents, for submission to the BOI office. For more details on these customs duty reductions, or on any aspect of investment promotion in Thailand, please contact Charuwan Charoonchitsathian at [email protected] or +66 2056 5657, or Napassorn Lertussavavivat at [email protected] or +66 2056 5662.
August 16, 2022
On July 21, 2022, Vietnam’s Ministry of Industry and Trade (MOIT) submitted Report No. 126/BC-BCT to the Prime Minister regarding the mechanism for transitional wind and solar power projects. In this report, the MOIT proposed some recommendations to explicitly address difficulties for outstanding wind and solar power projects (“Transitional Projects”) which have been developed under the Prime Minister’s Decision No. 13/2020/QD-TTg dated April 6, 2020, on the development of solar power projects (Decision 13) and Decision No. 37/2011/QD-TTg dated June 29, 2011, on the development of wind power projects (Decision 37), as amended by Decision No. 39/2018/QD-TTg dated September 10, 2018 (Decision 39). The Transitional Projects primarily include those which have completed construction but have not yet been put into operation, and those which have been put into operation but for which the power price has not yet been decided, due to missing the deadline set forth under the aforementioned decisions to be eligible for the feed-in-tariff (FIT). In particular, the MOIT has proposed the following key recommendations to the Prime Minister: Mechanism for Transitional Projects The MOIT proposes two options: Option 1: Developers of the Transitional Projects negotiate and sign power purchase agreements (PPA) with Vietnam Electricity (EVN) within the price framework issued by the MOIT in accordance with the Law on Electricity, the Law on Prices, and their subordinate guiding legislation; or Option 2: The Prime Minister formulates a new decision specifying the mechanism for bidding on the purchase of power produced by the Transitional Projects, estimated to be implemented for the time limit of three years and within the price framework issued by the MOIT. Mechanism for future wind and solar power projects The MOIT proposes to apply the mechanism that developers of future wind and solar projects negotiate the power price and sign the PPA
August 2, 2022
The Ministry of Energy is preparing to open a bidding round for the right to explore and produce petroleum in three offshore exploration blocks in the Gulf of Thailand: Exploration Block Nos. G1/65, G2/65, and G3/65. Announced in April 2022 with an eye toward national energy sustainability and security, this is the first opportunity for exploration of new offshore areas in 15 years. The total area of the three exploration blocks is 35,164.01 square kilometers, and operations in the exploration blocks will be subject to the terms and conditions of the required production sharing contract (PSC). Under the PSC, the Thai government is entitled to receive royalty payments against profits, any applicable cost recovery, and profit petroleum. The government also has the authority to monitor the petroleum operations in collaboration with the successful bidder. On July 27, 2022, the Department of Mineral Fuels (DMF) held a conference for prospective investors in order to clarify general information regarding the petroleum bidding round. Currently, interested investors can request the right to enter the bidding-round data room located at the DMF by emailing [email protected] by September 2, 2022. To participate in the bidding round, interested investors must submit an application together with required documents to the DMF during the period of September 5–16, 2022. For further information on the bidding round, or on any aspect of energy law in Thailand, please contact Tilleke & Gibbins at [email protected] or +66 2056 5555.