Cambodia Issues Environmental Code and Guidelines Benefiting Rooftop Solar Projects

Cambodia has the potential to be one of the top countries in the world for generating renewable energy through solar, based on the average amount of sunlight hours available per day and the consistent sunshine throughout the year.

The Cambodian government has recognized this potential and has made major updates to its energy policies in recent years. Solar power is now taking over a much larger portion of the total energy mix in Cambodia, especially as a number of utility-scale solar power plants have come online in recent years.

The long-term Power Development Master Plan 2022–2040 sets out the long-term energy policy for Cambodia and requires a bigger role for renewables. The use of solar power will play a key role in this aim to increase the role of renewables, with the plan foreseeing almost 30% of all national power generated through solar technologies by 2040.

Two of the latest legislative and regulatory steps by the government are the Ministry of Mines and Energy’s guidelines for rooftop solar systems, and most recently the long-awaited Environment and Natural Resources Code, which was enacted on June 29, 2023.

Rooftop Solar Projects

Many companies, from small startups to multinationals, are exploring the potential for rooftop solar in Cambodia. However, despite the favorable natural factors, the regulatory framework was not always clear or friendly to rooftop solar, hampering investment.

This started slowly changing with the adoption of the first solar energy regulation in 2018, which provided the country’s first official guidance on both solar power plants and rooftop solar. It provided some much-needed clarity, but the 2018 solar energy regulation—and especially the subsequent electricity tariff schemes—often kept rooftop projects from being financially viable.

Many players in the industry voiced their doubts about the regulations and tariffs, focusing especially on the capacity charge—a monthly electricity charge based on the total capacity of the rooftop solar project, not on consumption. Another point of contention was capacity restrictions, which limit projects in scale and therefore in profitability.

The restrictions and the capacity charge made rooftop solar much less competitive when compared to other energy sources. In many cases, rooftop solar would make the price of electricity even more expensive than purchasing it from the national grid without having rooftop solar. These factors put a serious damper on investment into rooftop solar in Cambodia.

The 2023 Solar Guidelines and the Environmental Code

Noticing the lack of investment in rooftop solar, Cambodia’s Ministry of Mines and Energy recently issued new guidelines (the “2023 Solar Guidelines”) in a bid to change this.

The 2023 Solar Guidelines (formally the “Principles for Permitting the Use of Rooftop Solar Power in Cambodia”) are the result of a study by an interinstitutional committee formed specifically for this purpose, working in close cooperation with the United Nations Development Programme.

In addition to the 2023 Solar Guidelines, the government has included references to solar, rooftop solar, and renewable energy in the Environment and Natural Resources Code (the “Environmental Code”), which was adopted on June 29, 2023.

The Environmental Code was years in the making, and after going through various drafting stages the adopted version consists of 865 articles addressing a range of topics, including environmental impact assessments, environmental management and conservation, energy management, waste and pollution management, disaster risk reduction management, and many others. The section on renewable energy specifically addresses the management of rooftop solar systems, tax incentives, and other important issues.

Some of the solar and rooftop solar provisions from the 2023 Solar Guidelines and the Environmental Code are discussed below.

Feeding Excess Power into the National Grid

The 2023 Solar Guidelines, in contrast to the 2018 Solar Regulations, allow for approved rooftop solar projects to feed excess power into the national grid.

This may help companies with their offset goals and commitments to reduce their carbon footprint, and is therefore a favorable and much-needed development. Feeding-in is subject to an approval quota, permitting, and a technical assessment by authorities prior to approval.

No feed-in tariff or net-metering has yet been set, so although feed-in approval may be granted, there is not yet a clear financial benefit to feeding excess power into the national grid.

However, this is very likely to change in the near future, as the Environmental Code provides that the relevant government authorities must establish a pilot project for a preferential tariff system for renewable energy. The system must include a fixed rate for the purchase of power coming from solar or other renewables, and a cost reduction mechanism.

This wording will likely lead to a feed-in tariff, and possibly a net-metering approach, to ensure that excess power fed into the grid leads to either fixed financial compensation or a reduction in electricity costs through net metering.

It appears the 2023 Solar Guidelines are laying the groundwork for this pilot project proscribed for in the Environmental Code, so related developments on this are expected soon.

Compensation Tariff for Variable Energy from Rooftop Solar

Removing the much-debated capacity charge, the 2023 Solar Guidelines require the tariff regulator to set a new tariff for rooftop solar based on a prescribed formula. The new tariff must be based on actual consumption of electricity, not on the total capacity of the project.

Regardless of the formula and numbers that the regulator will use to calculate the new tariff, consumers with rooftop solar will not have to pay a higher rate when compared to the general tariff applicable to users without solar, as per the 2023 Solar Guidelines.

Initial responses by the local solar industry welcomed the removal of the capacity charge and the introduction of the tariff limit for solar. However, businesses are hesitant about whether the new tariff scheme will spur immediate investment in rooftop solar, as the hard numbers for the new tariff have not been issued.

The formula for the “Compensation Tariff for Variable Energy from Rooftop Solar” provided under the 2023 Solar Guidelines is designed to be fair to “all parties”—including existing utility companies and investments that are impacted by solar and thus require compensation. As stated above, the 2023 Solar Guidelines have not set the tariff price; they merely set a formula following guidelines and principles. The actual tariff is for the regulator to determine, and to do so it will include calculations on the leveled cost of electricity (LCOE) and grid loss to compensate parties that may be impacted by solar.

Potential Tax Incentives

The Environmental Code provides that “all materials used for the installation of renewable technologies” are to be given tax incentives.

Although the article does not further clarify the specifics of such incentives, the clear obligation to provide a tax incentive should be warmly welcomed by businesses. We expect the tax regulator to further clarify these tax incentives in the near future.

A Bright Future

The 2023 Solar Guidelines provide the solar industry and government institutions with principles and guidelines related to rooftop solar. We expect that these principles and guidelines will eventually lead to clear rights and obligations as they are implemented through legislation and official policy in the coming years. The basis for incentivizing and promoting solar is clearly provided under the 2023 Solar Guidelines.

The Environmental Code sets clear rights and obligations, applying both directly to citizens, companies, and to government institutions that have to implement and honor them. Addressing solar in such a major piece of legislation marks a great step forward for the country. Providing clear and direct obligations for government institutions to promote and incentivize renewables such as solar will surely have a positive effect on industry and the environment.

RELATED INSIGHTS​ 

February 11, 2025
On January 24, 2025, the prime minister of Vietnam issued Decision No. 232/QD-TTg, approving the proposal for establishment and development of a carbon market in Vietnam. The decision establishes a compliance mechanism for greenhouse gas (GHG) emitters and creates opportunities for investors interested in carbon trading in Vietnam. Market Development Roadmap Decision 232 establishes a phased approach to developing Vietnam’s carbon market, with the following ambitious milestones: Before June 2025 (preparation period): The legal framework for trading of emissions quotas and carbon credits and a carbon-credit offset exchange mechanism will be developed, along with the necessary infrastructure for organization and operation of the carbon-credit market. From June 2025 to the end of December 2028 (pilot period): A pilot domestic carbon exchange will be launched, with continued legal refinements. From 2029 (official launch period): The carbon market will be fully operational. Carbon Market Structure and Trading Mechanisms Vietnam’s carbon market will function as a centralized, government-regulated exchange, trading two main assets: GHG emissions quotas (allowances) allocated to regulated emitters, which can be traded or auctioned; and Carbon credits generated from domestic and international projects that are certified for trading. The carbon credits generated from international projects include those originating from international exchange or offset-crediting mechanisms such as the Clean Development Mechanism (CDM), the Joint Credit Mechanism (JCM), and Article 6 of the Paris Agreement. The National Registration System for GHG emissions quotas and carbon credits will be primarily developed and operated by the Ministry of Natural Resources and Environment. Transactions of GHG emissions quotas and carbon credits will occur on the domestic carbon exchange, managed by the Hanoi Stock Exchange, and will follow a centralized process where verified quotas and credits receive unique domestic codes for trading and participants must have depository accounts. The Vietnam Securities Depository and Clearing Corporation
January 27, 2025
Thailand’s Ministry of Energy (MOE) has announced the launch of the 25th bidding round for petroleum exploration and production. This round offers nine greenfield onshore blocks—seven in northeastern Thailand and two in central Thailand—encompassing over 33,000 km². The bids can be submitted from July 1 to July 16, 2025. The sizes and locations of these blocks are: Northeast Thailand Block L1/66: 3,223.51 km² (Khon Kaen, Nong Bua Lam Phu, Udon Thani) Block L2/66: 3,917.03 km² (Kalasin, Sakon Nakhon, Udon Thani) Block L3/66: 3,918.22 km² (Kalasin, Khon Kaen, Maha Sarakham, Udon Thani) Block L4/66: 3,656.65 km² (Amnat Charoen, Mukdahan, Nakhon Phanom, Yasothon) Block L5/66: 3,436.01 km² (Chaiyaphum, Khon Kaen, Nakhon Ratchasima) Block L7/66: 3,438.51 km² (Buri Ram, Maha Sarakham, Nakhon Ratchasima, Roi Et, Surin, Khon Kaen) Block L9/66: 3,885.44 km² (Nakhon Ratchasima) Central Thailand Block L6/66: 3,966.86 km² (Chaiyaphum, Lop Buri, Phetchabun) Block L8/66: 3,957.41 km² (Kanchanaburi, Nakhon Pathom, Ratchaburi, Suphan Buri) Bidding Process Interested companies must submit their bids to the Department of Mineral Fuels (DMF) between July 1 and July 16, 2025. Bids should include: Application form (ChorThor/Por1) Proof of eligibility: Corporate documentation, audited financial statements, and proof of resources Technical and commercial proposals: Exploration plans, geological surveys, financial and work commitments, and special benefits such as signing bonuses of at least USD 100,000. There is a nonrefundable THB 50,000 application fee per block, and applicants must provide a bid bond of THB 3 million per block via an unconditional bank guarantee from a commercial bank with branches in Thailand, valid for at least one year from the bidding submission date. The guarantee will be returned to unsuccessful bidders upon request and to successful bidders upon the signing of the concession agreement. Eligibility Bidders must meet the following main eligibility criteria: Bidders must be limited companies with the following qualifications: The company must have the objective of
January 23, 2025
In 2023, compliance inspections by Vietnam’s Government Inspectorate identified several violations of policies and laws in the management and implementation of planning and investment in renewable energy projects. Since then, many renewable energy enterprises and projects have encountered significant operational challenges. In December 2024, the Ministry of Industry and Trade (MOIT) issued two reports, Report 321/BC-BCT and Report 345/BC-BCT, to implement the 2023 Inspection Conclusion of the Government Inspectorate and address obstacles faced by renewable energy enterprises, Investors in renewable energy projects in Vietnam should carefully consider the potential impacts of proposed solutions in these reports. The reports re-emphasize the types of violations related to renewable energy projects identified in the Inspection Conclusion, with a significant expansion in the number of affected projects. Key violations include: (i) misapplication of FIT (feed-in tariff) incentives; (ii) recognition of COD (commercial operation date) and receipt of FIT prices without written approval of construction acceptance; (iii) overlap with mineral planning, irrigation planning, national defense land use, or other restricted land uses; (iv) incomplete land procedures and documentation; and (v) installation of rooftop solar on agricultural and forestry land used for farming and aquaculture models. Further, these reports mention the government’s solutions to resolve difficulties for renewable energy projects, which include: Allowing additional planning where projects do not violate national security. Allowing rectification of projects’ violations in land and construction process as per law. For projects violating planning on minerals, irrigation, or defense, socio-economic efficiency will be assessed for adjustments or integration. Adjusting electricity prices and recovering incorrect FIT prices for projects not meeting conditions. Requiring rooftop solar projects on non-farming land to comply with regulations or, if land violations occur, FIT prices will be revoked, and electricity prices must be redetermined and recovered. For items (iv) and (v), the authority will issue regulations
January 14, 2025
Thailand’s Department of Industrial Works (DIW) has issued a new regulation (Ministerial Regulation Re: Designation of Type, Kind, and Size of Factories (No. 3) B.E. 2567 (2024)), which removes the factory license requirement for electricity generation from solar energy installations on rooftops, roof decks, or any part of a building used for residential or other purposes, regardless of capacity. The new rules took effect on December 28, 2024. Under the previous regulations, solar rooftop installations had to seek approval from the DIW if their capacity exceeded 1,000 kW (1 MW), which added time and administrative costs when adopting renewable energy solutions. Benefits and Further Compliance The updated regulation benefits industrial operators by facilitating faster installation times and lower costs, as solar rooftops can now be installed without the need for prior approval of a factory license from the DIW. Operators can now more easily contribute to environmental sustainability and carbon reduction efforts. Despite the lifting of the factory licensing requirement, other compliance obligations, such as an energy business license (or exemption from an energy business license), a controlled energy production license, and a construction permit, may still apply. Reason for the Change Removing the classification of rooftop or building-installed solar power plants as factories aligns with Thailand’s renewable energy goals and reduces regulatory burdens for industrial operators. Additionally, it supports the achievement of energy policies aligned with the UN’s Sustainable Development Goals and Thailand’s international commitments to reduce greenhouse gas emissions through the participation of all sectors. For further details on how this change affects business operations or to explore strategies for renewable energy implementation, please contact Supasit Boonsanong at [email protected], Charuwan Charoonchitsathian at [email protected], or Phareeya Yongpanich at [email protected].