January 10, 2024

Cambodia: All Solar Power Systems Must be Reported

On December 15, 2023, the Electricity Authority of Cambodia (EAC) issued a notification requiring all owners of solar power systems to report their systems to their local electricity supplier by January 31, 2024. Systems that have already been reported under existing regulations are exempt from this requirement.

Systems that remain unreported after the deadline will be deemed illegal and subject to penalties, including possible disconnection from the national grid.

The rationale for the reporting requirement is that the EAC expects to adopt a new solar power regulation soon. Electricite du Cambodge (the main state-owned utility provider in Cambodia) and EAC-licensed private electricity providers are now gathering data on the current use of solar power systems in order to prepare for, adopt, and execute the upcoming regulation. The reporting requirement is to facilitate this gathering of data.

The upcoming regulation, planned for early 2024 according to the notification, follows last year’s Prakas No. 159, which contained the Ministry of Mines and Energy’s guidelines and principles for rooftop solar systems. The EAC now needs to issue implementing regulations that are in line with the ministry’s guidelines and principles.

Although stand-alone solar power systems that did not have a connection to the national grid were previously not regulated and did not require any authorizations, the EAC is now stating that all types of solar power systems need to adhere to the reporting requirement under the notification. According to the EAC, the upcoming regulation will address all types of systems, and the December 15 notification clearly announces that all types of solar power systems will need to obtain EAC approval under the upcoming regulation.

Solar power system operators in Cambodia should report their systems to their local electricity providers by January 31, 2024, to avoid any penalties, while remaining vigilant for the upcoming regulation, which will likely include a requirement to obtain EAC authorization for any solar power systems.

For more information on complying with Cambodia’s requirements for solar power systems, please contact David Mol at [email protected].

RELATED INSIGHTS​ 

August 4, 2017
The pace of Thailand’s infrastructure development has continued to grow in the past few years, bringing numerous opportunities for engineering, procurement, and construction (EPC) firms based overseas that are looking for ways to participate in a project in Thailand. However, potential investors will need to have a solid understanding of the country’s legal and regulatory framework prior to investing significant time, energy, and capital.
June 30, 2017
On June 17, 2017, the Petroleum Act (No. 7) B.E. 2560 and the Petroleum Income Tax Act (No. 7) B.E. 2560 were both enacted, amending their predecessor laws. The amendments to both statutes entered into force on June 23, 2017. The amendments had been anticipated for some time, introducing production sharing agreements (PSAs) and service contracts as alternative host government instruments by which upstream oil and gas producers may invest in Thailand.
May 5, 2017
As part of its membership in Lex Mundi, Tilleke & Gibbins has published an updated edition of its Guide to Doing Business in Thailand for 2019.This guide offers a broad introduction to all of the key factors for starting and operating a business in the Thai market. Issues covered include:
April 28, 2017
As the costs of solar photovoltaic (PV) panels decrease, new business opportunities are emerging. In addition to the traditional model of independent power producers establishing large-scale power generating facilities to sell electricity directly to public utilities, a new dynamic model of direct electricity selling is beginning to take shape.