Under Thai bankruptcy law, a creditor can file a request for a debtor to be placed under an absolute receivership order and bankruptcy judgment. However, the debtor must be insolvent, and the debt owed to the creditor or creditors must be at least THB 1 million (for a debtor who is a natural person) or THB 2 million (for the debtor who is a juristic person). In order to know whether the latter requirement is met, the debt must be “determinable”—that is, known and monetarily quantifiable.

More specifically, determinable debt is debt (up to the filing date) in an amount that can be calculated, whether the debt is payable immediately or in the future. The debt can be under a loan agreement or under a sale-and-purchase agreement.

One question that sometimes comes up is whether damages arising out of termination of such an agreement are considered determinable debt. According to a number of Supreme Court precedents, if the debt (e.g., rent, fine or penalty) can be calculated as referred to in the agreement, the debt is determinable. Three of these cases are described below.

Supreme Court Case No. 2653/2526

In this case, the defendant made a partial delivery of oil (i.e., not the amount fully expected) to the plaintiff, who claimed that the defendant owed them a fine of almost THB 14.9 million, calculated in accordance with the sale-and-purchase agreement for the oil. The defendant argued that the debt was not determinable because the plaintiff did not prove whether they suffered damage or not. The Supreme Court noted that the agreement for sale and purchase of oil stated clearly that if the defendant could not deliver oil to the plaintiff in full, the plaintiff had the right to terminate the agreement and fine the defendant 25 percent of the price of the oil that was not delivered. The court therefore ruled that the plaintiff was not obligated to prove whether they suffered any damage, and that the debt in question was determinable under the Bankruptcy Act.

Supreme Court Precedent No. 2763/2551

This case concerned outstanding rent payments. The plaintiff claimed that the defendant failed to pay the rent specified in the lease agreement, with the cumulative amount due reaching almost THB 6.9 million. The Supreme Court concluded that since the defendant did not prove otherwise, it was concluded that the defendant did in fact owe this amount to the plaintiff, in accordance with the lease agreement, and confirmed that this was determinable debt.

Supreme Court Precedent No. 6068/2558

The plaintiff in this case claimed that the defendant had breached a lease agreement by failing to pay the rent, withholding tax, land and building tax, and billboard tax as set out in the lease agreement. The plaintiff then terminated the lease agreement and submitted a claim to the Bankruptcy Court for damages of approximately THB 13.5 million. One of the defendant’s arguments was that the plaintiff should have filed a civil court case before filing a bankruptcy claim. The Supreme Court ruled that under the Bankruptcy Act, the plaintiff is not obliged to file a civil action or obtain a civil court judgment prior to filing a bankruptcy claim. In addition, the rent, withholding tax, land and building tax, billboard tax, and fine for breach of the agreement which was specified in the lease agreement were confirmed to be determinable debt.

Conclusion

These three Supreme Court precedents are examples of how a creditor can file a claim at the Bankruptcy Court to request an absolute receivership order and bankruptcy judgment for damages arising out of termination of an agreement. Thus, whether damages arising out of termination of an agreement are considered determinable debt likely depends on whether the claimed damages were debts in accordance with terms in an agreement, and were able to be calculated up to the filing date.

RELATED INSIGHTS​ 

August 20, 2026
As part of its membership in Lex Mundi, Tilleke & Gibbins has released the latest edition of its Guide to Doing Business in Thailand, providing an overview of the legal, regulatory, and commercial considerations for companies establishing or expanding operations in Thailand. The 2026 edition offers practical insight into the country’s business environment, investment framework, and operational requirements. The guide covers a wide range of topics relevant to foreign and domestic investors, including: Investment incentives and promotion schemes Financial facilities and banking regulations Exchange controls and money transfers Import and export regulations Business structures and incorporation options Requirements for establishing a business Operational and compliance considerations Business cessation and insolvency procedures Employment and labor laws Taxation Immigration and visa requirements Prepared by Tilleke & Gibbins lawyers across multiple practice areas, the publication outlines key aspects of doing business in Thailand, including foreign investment restrictions, regulatory compliance obligations, corporate structures, employment requirements, and recent legal and economic developments affecting investors. The publication forms part of Lex Mundi’s Country Guides series, a global collection of jurisdiction-specific reference materials prepared by member firms around the world. Together, these guides help companies evaluate opportunities, compare regulatory environments, and plan international business activities across multiple markets. The full Guide to Doing Business in Thailand 2026 is available through the button below.
August 19, 2026
Arbitration clauses and national court jurisdiction have long existed in a delicate equilibrium, and nowhere is that equilibrium tested more often than in the drafting of multitier dispute resolution clauses. Such clauses—requiring negotiation before arbitration—are ubiquitous in international construction contracts, and they frequently employ permissive vocabulary at the arbitration tier. The formulation “either party may submit the dispute to arbitration” is intended to signal that either side is entitled to initiate proceedings. Yet it is periodically seized upon by claimants who prefer national courts, on the theory that “may” preserves a parallel right to litigate. Each apex-court pronouncement on this question is therefore significant for drafting practice and forum predictability. In 2019, the Thai Supreme Court delivered Thailand’s clearest answer to date (Judgment No. 3427/2562). Reversing an appellate court decision, the Supreme Court held that permissive wording at the point of commencement does not dilute the parties’ antecedent agreement to withdraw their disputes from the courts—doing so in regard to an International Chamber of Commerce (ICC) arbitration clause seated in Singapore, a configuration typical of foreign-invested projects in Thailand. This article examines the court’s reasoning, situates the decision within comparative jurisprudence, and draws out its practical lessons for parties and drafters operating in the Thai market. Background of the Dispute The dispute arose from a subcontract for civil engineering and architectural works concluded on September 25, 2014. Clause 19 of the subcontract governed dispute resolution. Clause 19.1 required the parties, at the request of either, to seek to resolve any dispute “in connection with, arising out of, or relating to” the subcontract through mutual consultation within sixty days of written notice. According to clause 19.2.1, if the dispute could not be resolved within that period, “either party may submit the dispute to arbitration,” to be conducted under the ICC
August 18, 2026
Securing a favorable judgment is often only the midpoint of a dispute. For businesses and investors, the more important commercial question is whether that judgment can be converted into actual recovery. In Thailand, this typically requires the judgment creditor to enforce the judgment through the Legal Execution Department by seizing, attaching, auctioning, or otherwise executing against the judgment debtor’s assets. Thailand’s schedule of these enforcement fees was last revised by an amendment to the Civil Procedure Code that took effect in September 2025. The Civil Procedure Code Amendment Act (No. 33) B.E. 2568 (2025) updated the schedule of execution officer fees listed in table 5 of the Civil Procedure Code. While the amendment did not eliminate the costs associated with enforcement, it lowered several key execution officer fees and abolished certain fees that previously applied even where enforcement did not ultimately result in the sale or disposition of assets. The reform is intended to reduce the financial burden associated with judgment enforcement and remove unnecessary obstacles to settlement once enforcement proceedings have commenced. As a result, it has practical implications not only for judgment creditors seeking to maximize recovery, but also for debtors considering settlement after enforcement has begun and for businesses and investors assessing litigation and credit risk in Thailand. Key Changes The amendment introduced several changes to the execution officer fee structure. First, where seized or attached assets are sold by public auction or otherwise disposed of, the execution officer fee has been reduced from 3% to 2% of the sale or disposition proceeds. This fee remains separate from announcement costs and other out-of-pocket expenses incurred during the enforcement process. Second, where seized or attached funds are paid to a judgment creditor, the execution officer fee has been reduced from 2% to 1% of the amount recovered.
August 11, 2026
Cambodia’s Ministry of Justice has launched a new platform on its official website to publish notices of forced sales issued by each municipal and provincial court of first instance. The platform’s stated purpose is to inform the public and facilitate greater participation in forced-sale auctions conducted in connection with court-ordered enforcement proceedings. How the Platform Works The platform publishes forced-sale notices from courts of first instance across Cambodia’s municipalities and provinces and includes a link where the public can view properties currently subject to forced sale. To participate in a forced-sale auction, individuals can download Khmer-language bidding application forms through links provided on the platform. The form typically requires the applicant’s name, sex, year of birth, identity card number and issue date, and address, together with details identifying the immovable property (including its ownership certificate number), the relevant enforcement case number and date, and the reference to the public auction or tender announcement issued by the court. Completed application forms must be submitted directly to the specific municipal or provincial court that issued the forced sale. For further inquiries about a particular forced sale, interested parties should likewise contact the relevant municipal or provincial court. Forced Sale of Immovable Property in Cambodia The publication of these notices relates to the forced sale procedure for immovable property under Cambodia’s Code of Civil Procedure (CPC). Unlike property seizure by a court, a forced sale is a compulsory execution proceeding—a subsequent enforcement step that arises only after an underlying dispute has been adjudicated and a debtor fails to pay the debt or outstanding amount due under a final and binding judgment or other enforceable title of execution. For the purposes of this procedure, the term “immovable property” under the CPC refers to land, registered buildings, jointly held shares of such property, registered