February 25, 2026

A New Dawn for Liquidated Damages in Construction Disputes in Vietnam?

In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions.

Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam.

While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam.

What’s New?

Article 86.2 of the 2025 Law on Construction provides (emphasis added):

“Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.”

This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2.

Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the extent of the breaches. This language suggests a narrowing effect on enforceability: Predetermined damages may only be upheld where they are demonstrably linked to the specific breached obligations and proportionate to the degree of the breaches. As a result, predetermined damages agreed by the parties may still be vulnerable to challenge if they are perceived as insufficiently connected to the relevant obligation or excessive in light of the breach.

Thus, while Article 86.2 represents a positive step toward statutory recognition of liquidated damages, the lack of definitional clarity and the correspondence requirement introduce continued uncertainty as to their enforceability, which will likely be clarified only through future judicial and arbitral practice.

Recommendations for Businesses

Contracting parties to construction contracts may now be more comfortable including liquidated damages clauses, given their express recognition under the 2025 Law on Construction. However, as the new law will not come into effect until July 1, 2026, it is too early to assess the practical application of Article 86.2. To mitigate the potential ambiguities and uncertainties discussed above, businesses may consider the following:

  1. Liquidated damages clauses should be carefully tailored on a contract-by-contract basis to align with Article 86.2 of the new law. Standard templates should be revisited to ensure that any pre-agreed compensation amounts are clearly linked to identifiable obligations or the potential level of breach, rather than framed in broad or generic terms detached from specific performance risks.
  2. There remains a risk that the enforceability of a liquidated damages clause may be challenged if it cannot be demonstrated that the agreed damages correspond to the obligations not fulfilled and the extent of the breach. Accordingly, having readily available evidence will be critical. Detailed and contemporaneous records of progress, delays, cost impacts, resulting losses, and mitigation efforts are likely to be decisive, not only in establishing actual loss but also in substantiating the reasonableness and proportionality of any agreed damages.
  3. The agreed-upon liquidated damages amounts should also be realistic, reflecting a considered assessment of foreseeable risks, and the parties should avoid treating such figures as a mere bargaining convenience. Anticipating the likely consequences of nonperformance and anchoring the agreed amounts to those risks will reduce the likelihood of judicial or arbitral adjustment or refusal. Where parties lack sufficient experience, early engagement of technical or cost experts may assist in strengthening contractual positioning and enhancing the defensibility of pre-agreed damages claims.

In all cases, parties are advised to consult Vietnamese legal counsel when drafting construction contracts or managing disputes to ensure compliance with the evolving legal framework under the 2025 Law on Construction.

RELATED INSIGHTS​ 

June 16, 2026
The president of Thailand’s Supreme Court has issued new recommendations providing courts with criminal jurisdiction with a comprehensive framework for identifying and dismissing criminal cases brought in bad faith. Published in the Government Gazette on May 29, 2026, after being signed on May 25, the Recommendations of the President of the Supreme Court Concerning Bad-Faith Litigation in Criminal Cases B.E. 2569 were issued under Section 5 of the Act on the Organization of Courts of Justice. The recommendations took effect upon publication and represent a significant step in Thailand’s efforts to curb abusive criminal litigation, including strategic lawsuits against public participation (SLAPP). Background Section 161/1 of Thailand’s Criminal Procedure Code empowers courts to dismiss criminal cases filed dishonestly or with the intent to harass or take unfair advantage of a defendant. The new recommendations provide detailed guidance that courts previously lacked on identifying and handling such prosecutions. Definition of Bad-Faith Litigation Under recommendation 1, filing a criminal case in bad faith is defined broadly to encompass three categories: Harassment-type filings involving intimidation, threats, or creating unreasonable hardship for the defendant; Coercive filings designed to pressure the defendant into acting or refraining from acting for illegitimate benefit; and False or misleading filings that deliberately assert incorrect material facts or conceal such facts. Circumstances Indicating Bad Faith Recommendation 2 sets out specific circumstances that should raise a court’s suspicion that a filing may violate section 161/1. These include: Filing in a distant court far from the defendant’s domicile without benefiting the adjudication; Retaliation against the defendant’s advocacy for human rights, environmental protection, consumer rights, labor rights, or other public interests—effectively establishing an express anti-SLAPP framework; Retaliation against whistleblowers who disclosed corruption or unlawful conduct; Retaliation against individuals responsible for investigating the plaintiff’s wrongdoing or who concluded such an investigation; Filing multiple
June 10, 2026
For multinational franchisors operating in Thailand, a key risk after franchise termination is that former outlets may continue operating in ways that could easily mislead consumers into believing they remain within the authorized network. To justify such operations, former franchisees often argue that the termination was invalid or ineffective. As a result, these cases are often treated as contractual disputes, making it difficult for franchisors to obtain injunctive relief before a final judgment confirms that the termination was lawful. Franchisors face significant commercial and reputational harm during lengthy proceedings, including consumer confusion, disruption to franchise restructuring, and damage to brand reputation and customer trust. In an encouraging development, the Thai court in a 2025 case responded to the problem of unauthorized post-termination franchise operations by granting interim relief, recognizing broader brand and consumer harm, and awarding substantial damages, highlighting a successful litigation strategy of framing the dispute not merely as a contractual termination issue but as trademark infringement causing ongoing commercial injury. The Subway Case From December 2024 to mid-2025, an unauthorized “Subway®” franchise operation in Thailand attracted substantial public and media attention. Reports and online discussions about unauthorized Subway® stores circulated widely after complaints arose about food quality and customer experience at certain outlets that were allegedly operating after their franchise rights had expired. Because these stores continued to use Subway® trademarks, trade dress, and overall commercial appearance, many consumers were unable to distinguish them from authorized operations, resulting in reputational risks and customer confusion that affected the franchisor’s brand and franchise system in Thailand. Subway treated this matter with the utmost seriousness and moved promptly to protect its brand, franchise system, and customers. It filed a civil action with the IP&IT Court seeking a permanent injunction and damages. During the proceedings, the court granted a preliminary injunction
May 25, 2026
Thailand published new rules on May 1, 2026, establishing clear procedures for how the Anti-Money Laundering Office (AMLO) handles digital assets seized during criminal and money laundering investigations. Taking effect the following day, the Regulation of the Anti-Money Laundering Board on the Custody and Management of Seized or Frozen Assets (No. 3) B.E. 2569 applies to digital asset businesses, cryptocurrency holders, and anyone subject to asset seizure under Thailand’s anti-money laundering laws. For the first time, authorities now have a detailed roadmap for transferring seized digital property from private or foreign control into secure state custody. Digital asset businesses holding customer assets under investigation must be prepared to comply with these rules compelling repatriation of such assets in enforcement actions. Expanded Definition of Digital Assets The regulation defines digital assets to include not only those covered by Thailand’s existing digital asset business law but also any other property that can be stored using the same methods as digital assets. This broad formulation means the custody rules will apply to emerging blockchain-based assets and tokenized property that may not yet fall within the statutory definition of a digital asset business, giving authorities flexibility as the technology evolves. Mandatory Transfer to Domestic Custody When digital assets are held with service providers outside Thailand, AMLO will first attempt to transfer them to an account the office maintains with a licensed domestic digital asset business operator. If the domestic operator does not support that particular asset, the office will instead move the assets to its own cold wallet (offline, internet-isolated storage system). If neither option is feasible, the seizing official will report the situation to the Anti-Money Laundering Committee for alternative instructions. A similar hierarchy governs assets held in an accused party’s private wallet or by any third party that is not a
April 30, 2026
Thailand’s Long-Term Resident (LTR) Visa regime offers an attractive immigration pathway for qualifying foreign nationals, providing a 10-year renewable permission to stay in Thailand. Following amendments under Board of Investment (BOI) Announcement No. Por. 3/2568 dated February 4, 2025, the regime now more explicitly accommodates property investment as a qualifying vehicle—a development of particular relevance to foreign nationals already considering real estate acquisitions in Thailand. The LTR Visa is available to several categories of applicants, including wealthy global citizens with global assets of at least USD 1 million, and wealthy pensioners aged 50 or older with an annual pension or fixed income of at least USD 40,000. Property as a Qualifying Investment For both categories, property investment is recognized as one of three eligible investment types alongside Thai government bonds (with at least five years remaining to maturity) and direct investments in Thai companies or approved venture capital or private equity vehicles. The minimum qualifying property investment is USD 500,000 for wealthy global citizens and USD 250,000 for wealthy pensioners. Eligible property types include freehold condominiums, buildings, or villas, as well as leasehold properties with a remaining lease term of at least 10 years. Health Coverage Requirement Beyond the investment threshold, applicants must demonstrate adequate health coverage. This requirement can be satisfied through a health insurance policy covering at least USD 50,000 in Thai medical expenses with at least 10 months of remaining coverage, evidence of social security benefits covering Thai medical costs, or a bank deposit of at least USD 100,000 retained for 12 months. Practical Considerations For foreign nationals already considering property acquisitions in prime residential markets—where investment values commonly meet or exceed the USD 500,000 threshold—the visa pathway effectively transforms a real estate purchase into a dual-purpose investment, combining asset ownership with long-term residence rights that