February 25, 2026

A New Dawn for Liquidated Damages in Construction Disputes in Vietnam?

In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions.

Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam.

While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam.

What’s New?

Article 86.2 of the 2025 Law on Construction provides (emphasis added):

“Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.”

This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2.

Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the extent of the breaches. This language suggests a narrowing effect on enforceability: Predetermined damages may only be upheld where they are demonstrably linked to the specific breached obligations and proportionate to the degree of the breaches. As a result, predetermined damages agreed by the parties may still be vulnerable to challenge if they are perceived as insufficiently connected to the relevant obligation or excessive in light of the breach.

Thus, while Article 86.2 represents a positive step toward statutory recognition of liquidated damages, the lack of definitional clarity and the correspondence requirement introduce continued uncertainty as to their enforceability, which will likely be clarified only through future judicial and arbitral practice.

Recommendations for Businesses

Contracting parties to construction contracts may now be more comfortable including liquidated damages clauses, given their express recognition under the 2025 Law on Construction. However, as the new law will not come into effect until July 1, 2026, it is too early to assess the practical application of Article 86.2. To mitigate the potential ambiguities and uncertainties discussed above, businesses may consider the following:

  1. Liquidated damages clauses should be carefully tailored on a contract-by-contract basis to align with Article 86.2 of the new law. Standard templates should be revisited to ensure that any pre-agreed compensation amounts are clearly linked to identifiable obligations or the potential level of breach, rather than framed in broad or generic terms detached from specific performance risks.
  2. There remains a risk that the enforceability of a liquidated damages clause may be challenged if it cannot be demonstrated that the agreed damages correspond to the obligations not fulfilled and the extent of the breach. Accordingly, having readily available evidence will be critical. Detailed and contemporaneous records of progress, delays, cost impacts, resulting losses, and mitigation efforts are likely to be decisive, not only in establishing actual loss but also in substantiating the reasonableness and proportionality of any agreed damages.
  3. The agreed-upon liquidated damages amounts should also be realistic, reflecting a considered assessment of foreseeable risks, and the parties should avoid treating such figures as a mere bargaining convenience. Anticipating the likely consequences of nonperformance and anchoring the agreed amounts to those risks will reduce the likelihood of judicial or arbitral adjustment or refusal. Where parties lack sufficient experience, early engagement of technical or cost experts may assist in strengthening contractual positioning and enhancing the defensibility of pre-agreed damages claims.

In all cases, parties are advised to consult Vietnamese legal counsel when drafting construction contracts or managing disputes to ensure compliance with the evolving legal framework under the 2025 Law on Construction.

RELATED INSIGHTS​ 

February 26, 2025
Thailand ratified the New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards on December 21, 1959, with the Convention coming into force on March 20, 1960. This ratification was a significant step in aligning Thailand’s arbitration framework with international standards, facilitating the recognition and enforcement of foreign arbitral awards in the country. In Thailand, the enforcement of both domestic and international arbitral awards is governed by the Arbitration Act B.E. 2545 (2002), which is based on the first version of the UNCITRAL Model Law on International Commercial Arbitration of 1985 (as opposed to the latest version from 2006). However, unlike Australia, Hong Kong, and Singapore, Thailand is not an UNCITRAL Model Law country. While Thailand’s Arbitration Act is influenced by the UNCITRAL Model Law, it incorporates certain local contexts that require interpretation alongside Thai court rulings. The Arbitration Act also confirms the authority of arbitral tribunals to grant interim measures, reinforcing tribunals’ power in managing disputes effectively. Additionally, the act incorporates principles from the New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards (1958). This article explores the key procedural steps, timeframes, and practical challenges associated with the enforcement of arbitral awards under Thailand’s legal framework. Procedures for Enforcement of Arbitral Awards in Thailand The enforcement of arbitral awards in Thailand follows the procedures outlined in the Arbitration Act: Application to the competent court: Under the Arbitration Act, parties seeking enforcement must submit a petition to the Thai courts within three years of the award having become enforceable. The application must include the original or certified copies of the arbitral award and the arbitration agreement, along with translations if necessary. In Thailand, the choice of court for filing the arbitral award depends on the nature of the disputed contract. If the contract concerns
February 21, 2025
As Vietnam continues its government restructuring, including the merging of several key ministries, the country is signaling that mergers of provinces could be next. Conclusion 126-KL/TW of the Politburo and Secretariat, issued on February 14, 2025, sets out several tasks for continuing to streamline the political system in 2025, notably including, among others, the following: Elimination of intermediate administrative levels, and mergers of provincial units: The Government Party Committee is tasked with researching and planning for the elimination of intermediate administrative levels (district levels); reorganizing the commune level with structures, functions, duties, powers, and responsibilities aligned with the new organizational model; and proposing the merging of some provincial administrative units. A report to the Politburo is required by Q3 2025. Reorganization of police structure: The Central Public Security Party Committee is tasked with leading and coordinating the implementation of a three-tier police organization, eliminating the district-level police. Judicial system reforms: The Central Party Committees of the Supreme People’s Court and the Supreme People’s Procuracy are tasked with researching and advising on the organizational model for courts and procuracies, and proposing amendments and supplements to relevant party mechanisms and state laws, with the aim of eliminating the district level. A report to the Politburo is required by Q2 2025. Implications of Merging Provinces The merging of provinces could bring positive impacts as well as new challenges. The expected benefits include: Administrative efficiency and cost saving: Reducing the number of administrative units could lead to more efficient governance and decision-making processes, as well as lower administrative costs due to fewer government offices and personnel. Economic development: Larger administrative areas can benefit from better allocation of resources and infrastructure development. Larger provinces may also attract more investment due to increased economic potential and market size. Improved service delivery: Public services could improve
January 21, 2025
A proposal to establish a specialized Intellectual Property Court in Vietnam has been a topic of significant interest among IP practitioners for the past 20 years. It was thus a major breakthrough when the new Law on the Organization of People’s Courts was ratified in 2024, stipulating in Article 4.1(dd) that the Vietnamese court system would include a specialized first-instance IP Court. The new law took effect on January 1, 2025, replacing the Law on the Organization of People’s Courts of 2014, A groundbreaking law This breakthrough can be viewed from multiple perspectives. First of all, in terms of organization, this is the first time, after numerous considerations, that Vietnam has officially recognized the importance of the IP field and the need to establish a specialized adjudicative body due to the field’s unique nature. The establishment of a specialized first-instance IP Court is expected to lead to fundamental changes in the practice of developing and applying IP law. While the establishment of IP rights such as trademarks, patents, and plant varieties is managed by administrative agencies such as the Intellectual Property Office, the Copyright Office, and the Crop Production Department, which seem unlikely to change their functions and tasks, there could be significant changes in the enforcement of these rights, which has been a persistent issue in Vietnam’s IP law system. Thus far, in practice, the enforcement of IP rights in Vietnam has relied overwhelmingly on administrative measures over civil measures. Civil measures, typically involving court proceedings under which the matter will be submitted to a court for settlement, are not appealing to disputing parties, especially IP rights owners. The absence of a specialized court has led to many IP cases being handled by judges without any knowledge or experience in this specialized field, resulting in confusion, misconceptions about
January 16, 2025
On January 13, 2025, Thailand’s cabinet approved in principle the draft Entertainment Complex Act, as proposed by the Ministry of Finance. This landmark legislative proposal, which would allow casinos as part of larger “entertainment complexes,” will now proceed through further parliamentary review and approval. Key provisions of the draft act are described below. Corporate structure: Entertainment complexes must be operated by Thai-registered limited companies or public limited companies with a minimum paid-up capital of THB 10 billion. Directors of the licensed entity must be individuals and have the qualifications and none of the prohibited characteristics specified in the draft act. The draft act does not impose restrictions on foreign-majority ownership structures; however, it is worth monitoring whether any amendments addressing this matter are introduced during the legislative process. Operating conditions: Each entertainment complex must be located in an area designated under a royal decree. It must also include at least four types of entertainment businesses listed in the annex to the draft act (e.g., shopping mall, hotel, sports stadium, amusement park), along with a casino. The allocation of casino space must comply with regulations to be specified at a later date. Licensing conditions: Licenses will be valid for 30 years, renewable in increments of up to 10 years. The license issuance fee is THB 5 billion, the annual fee is THB 1 billion, and the renewal fee is THB 5 billion. The Entertainment Complex Policy Committee, chaired by the prime minister, will review and approve applications. Online gambling restrictions: Licensees are prohibited from offering gambling through internet-connected systems or electronic devices that allow access from outside the casino premises. Labor requirements: Thai and foreign employee ratios must adhere to prescribed regulations. Land privileges: Lease agreements for land use are limited to 50 years. Renewal is permitted for up to