A New Dawn for Liquidated Damages in Construction Disputes in Vietnam?

In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions.

Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam.

While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam.

What’s New?

Article 86.2 of the 2025 Law on Construction provides (emphasis added):

“Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.”

This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2.

Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the extent of the breaches. This language suggests a narrowing effect on enforceability: Predetermined damages may only be upheld where they are demonstrably linked to the specific breached obligations and proportionate to the degree of the breaches. As a result, predetermined damages agreed by the parties may still be vulnerable to challenge if they are perceived as insufficiently connected to the relevant obligation or excessive in light of the breach.

Thus, while Article 86.2 represents a positive step toward statutory recognition of liquidated damages, the lack of definitional clarity and the correspondence requirement introduce continued uncertainty as to their enforceability, which will likely be clarified only through future judicial and arbitral practice.

Recommendations for Businesses

Contracting parties to construction contracts may now be more comfortable including liquidated damages clauses, given their express recognition under the 2025 Law on Construction. However, as the new law will not come into effect until July 1, 2026, it is too early to assess the practical application of Article 86.2. To mitigate the potential ambiguities and uncertainties discussed above, businesses may consider the following:

  1. Liquidated damages clauses should be carefully tailored on a contract-by-contract basis to align with Article 86.2 of the new law. Standard templates should be revisited to ensure that any pre-agreed compensation amounts are clearly linked to identifiable obligations or the potential level of breach, rather than framed in broad or generic terms detached from specific performance risks.
  2. There remains a risk that the enforceability of a liquidated damages clause may be challenged if it cannot be demonstrated that the agreed damages correspond to the obligations not fulfilled and the extent of the breach. Accordingly, having readily available evidence will be critical. Detailed and contemporaneous records of progress, delays, cost impacts, resulting losses, and mitigation efforts are likely to be decisive, not only in establishing actual loss but also in substantiating the reasonableness and proportionality of any agreed damages.
  3. The agreed-upon liquidated damages amounts should also be realistic, reflecting a considered assessment of foreseeable risks, and the parties should avoid treating such figures as a mere bargaining convenience. Anticipating the likely consequences of nonperformance and anchoring the agreed amounts to those risks will reduce the likelihood of judicial or arbitral adjustment or refusal. Where parties lack sufficient experience, early engagement of technical or cost experts may assist in strengthening contractual positioning and enhancing the defensibility of pre-agreed damages claims.

In all cases, parties are advised to consult Vietnamese legal counsel when drafting construction contracts or managing disputes to ensure compliance with the evolving legal framework under the 2025 Law on Construction.

RELATED INSIGHTS​ 

September 25, 2025
In the Thailand contribution to Labor and Employment Disputes 2026, four members of Tilleke & Gibbins’ Bangkok labor and employment team outline key aspects of dispute resolution in Thailand. Their analysis, part of Lexology Panoramic’s comparative guide covering jurisdictions worldwide, addresses the following areas: Pre-action considerations: key requirements, third-party funding, contingency fee arrangements Issuing a claim: forum, territorial jurisdiction, standing, commencing claims, fees, service, defendants and legal personality, types of claims, time limits, counterclaims Case management: procedure, rules, amendments to claims, adding parties, consolidating proceedings, class and collective actions, evidence, witnesses, tactical considerations Interim relief: availability, requirements Trial: hearings conduct and time frames, confidentiality and public access, media reporting, elements of successful claims and burden of proof Alternative dispute resolution: available types, requirements and expectations, enforcement Collective employment and labor rights: enforcement and standing Remedies and enforcement: available remedies, assessing compensation, enforcement mechanisms Appeals: procedure, time frames, other means of challenge Updates and trends: recent cases and developments, technology developments, other issues The complete Thailand chapter can be downloaded below. Tilleke & Gibbins also contributed the Cambodia and Vietnam chapters to Labor and Employment Disputes 2026. Readers can also gain 30 days of complementary access to the full Labor and Employment Disputes 2026 guide and the rest of Lexology Panoramic’s varied offerings through this link.
September 25, 2025
Four of Tilleke & Gibbins’ labor and employment specialists in Phnom Penh have authored the Cambodia chapter of Labor and Employment Disputes 2026, the latest edition of Lexology Panoramic’s global guide to handling labor and employment disputes. The chapter provides practical insights on a wide range of dispute resolution issues, including: Pre-action considerations: key requirements, third-party funding, contingency fee arrangements Issuing a claim: forum, territorial jurisdiction, standing, commencing claims, fees, service, defendants and legal personality, types of claims, time limits, counterclaims Case management: procedure, rules, amendments to claims, adding parties, consolidating proceedings, class and collective actions, evidence, witnesses, tactical considerations Interim relief: availability, requirements Trial: hearings conduct and time frames, confidentiality and public access, media reporting, elements of successful claims and burden of proof Alternative dispute resolution: available types, requirements and expectations, enforcement Collective employment and labor rights: enforcement and standing Remedies and enforcement: available remedies, assessing compensation, enforcement mechanisms Appeals: procedure, time frames, other means of challenge Updates and trends: recent cases and developments, technology developments, other issues The full Cambodia chapter is available for download below. Tilleke & Gibbins also contributed the Thailand and Vietnam chapters to Labor and Employment Disputes 2026. Readers can also gain 30 days of complementary access to the full Labor and Employment Disputes 2026 guide and the rest of Lexology Panoramic’s varied offerings through this link.
September 19, 2025
Over the past two years—particularly since Thailand announced incentives for EVs, including tax exemptions and reductions—there has been a clear trend of manufacturers relocating their facilities to Thailand. This shift is reshaping the country’s industrial landscape and creating significant opportunities in the real estate sector for companies looking to establish or expand EV manufacturing operations in Southeast Asia. Incentive-Driven Market Transformation The government’s tax exemptions and reductions have proven effective in attracting foreign investment, with Chinese manufacturers currently dominating the market. Most EV parts and car manufacturers operating in Thailand are from China, reflecting the prominence of Chinese EV brands that have already established a presence in the country. The sector encompasses manufacturers of electrical equipment as well as companies seeking to establish facilities for producing electric vehicle components, parts, and accessories. The surge in activity is evident across Thailand’s EV manufacturing sector, with legal practices handling these transactions experiencing unprecedented demand. Industrial Real Estate Framework and Market Dynamics Thailand’s industrial real estate framework provides compelling advantages for foreign manufacturers, who typically face restrictions on foreign land ownership under the Land Code. However, foreign investors can benefit from exemptions to these restrictions if the land is located within industrial real estate zones designated by the Industrial Estate Authority of Thailand (IEAT) or they obtain investment promotion from the Board of Investment (BOI) if the land is located outside an industrial estate area governed by the IEAT. Both the IEAT and BOI provide special tax and nontax incentives, including foreign land ownership, with even greater incentives available for land situated within the country’s Eastern Economic Corridor (EEC). This regulatory advantage has sparked a parallel trend in land development. Industrial real estate developers in the EEC are actively consolidating land into large plots to develop new industrial estate projects, recognizing that
September 10, 2025
Under Thai law, authorized directors stand as a company’s mind and will and, as such, may incur personal criminal liability for acts or omissions committed in the course of company business. When allegations surface, directors must be prepared for the practical reality that, before guilt or innocence is ever adjudicated, they could be deprived of liberty unless bail release is promptly achieved through the competent legal authority. When Bail Can Be Granted Two procedural moments trigger the need to consider bail. The first arises during the investigative phase, when a claim is lodged against a director with the competent law enforcement authorities. Upon receipt of a complaint, the assigned inquiry officer summons the director for questioning, compiles evidence, and ultimately forwards a prosecution or nonprosecution recommendation to the public prosecutor. Although the public prosecutor retains ultimate discretion to indict an accused director, the police or prosecutor may conclude that pretrial detention is necessary and may therefore apply to the court for an order to hold the director in court custody. The second moment occurs after a criminal case is filed directly with the court. This occurs once a court accepts a criminal case filed by a prosecutor against a director or, alternatively, when the court accepts a case filed by an individual for trial. For cases filed by individuals, the plaintiff presents prima facie evidence at the preliminary hearing, and the court will accept the complaint if it finds sufficient grounds, thereby conferring upon the director the status of a criminal defendant. Upon acceptance of the criminal case, the court then has the inherent authority to order custody pending trial unless the defendant secures bail release. Procedural Considerations Experienced litigants typically prepare bail security in advance and submit a bail petition at the earliest possible time. While there are