February 25, 2026

A New Dawn for Liquidated Damages in Construction Disputes in Vietnam?

In December 2025, the National Assembly of Vietnam enacted a new Law on Construction, replacing the 2014 Law on Construction as amended in 2020. The 2025 Law on Construction will, in principle, take effect on July 1, 2026, subject to certain exceptions.

Among its notable reforms, one development has attracted particular attention from both legal practitioners and market participants: the introduction of a statutory framework governing predetermined damages, commonly referred to as “liquidated damages.” This marks the first time liquidated damages have been expressly recognized at the level of primary legislation in Vietnam.

While liquidated damages clauses have long been a common feature of construction contracts in practice, their legal enforceability has historically been subject to uncertainty. Although the new provision appears to represent a positive step toward greater legal clarity, it remains an open question whether it is sufficient, on its own, to provide a solid legal basis for the enforceability of liquidated damages clauses in construction disputes in Vietnam.

What’s New?

Article 86.2 of the 2025 Law on Construction provides (emphasis added):

“Compensation for damages shall be determined on the basis of actual damages [or] predetermined damages corresponding to obligations under the construction contracts that are breached [and] the extent of such breaches.”

This provision is significant in that it expressly recognizes predetermined damages, or liquidated damages, as a lawful basis for determining compensation for damage. However, the new law does not define “predetermined damages.” The absence of a statutory definition creates potential ambiguity as to the scope and nature of this concept and may give rise to disputes over how—and whether—a particular contractual clause qualifies as predetermined damages for the purposes of Article 86.2.

Further, Article 86.2 qualifies the application of predetermined damages by requiring that such damages correspond to the obligations not fulfilled and the extent of the breaches. This language suggests a narrowing effect on enforceability: Predetermined damages may only be upheld where they are demonstrably linked to the specific breached obligations and proportionate to the degree of the breaches. As a result, predetermined damages agreed by the parties may still be vulnerable to challenge if they are perceived as insufficiently connected to the relevant obligation or excessive in light of the breach.

Thus, while Article 86.2 represents a positive step toward statutory recognition of liquidated damages, the lack of definitional clarity and the correspondence requirement introduce continued uncertainty as to their enforceability, which will likely be clarified only through future judicial and arbitral practice.

Recommendations for Businesses

Contracting parties to construction contracts may now be more comfortable including liquidated damages clauses, given their express recognition under the 2025 Law on Construction. However, as the new law will not come into effect until July 1, 2026, it is too early to assess the practical application of Article 86.2. To mitigate the potential ambiguities and uncertainties discussed above, businesses may consider the following:

  1. Liquidated damages clauses should be carefully tailored on a contract-by-contract basis to align with Article 86.2 of the new law. Standard templates should be revisited to ensure that any pre-agreed compensation amounts are clearly linked to identifiable obligations or the potential level of breach, rather than framed in broad or generic terms detached from specific performance risks.
  2. There remains a risk that the enforceability of a liquidated damages clause may be challenged if it cannot be demonstrated that the agreed damages correspond to the obligations not fulfilled and the extent of the breach. Accordingly, having readily available evidence will be critical. Detailed and contemporaneous records of progress, delays, cost impacts, resulting losses, and mitigation efforts are likely to be decisive, not only in establishing actual loss but also in substantiating the reasonableness and proportionality of any agreed damages.
  3. The agreed-upon liquidated damages amounts should also be realistic, reflecting a considered assessment of foreseeable risks, and the parties should avoid treating such figures as a mere bargaining convenience. Anticipating the likely consequences of nonperformance and anchoring the agreed amounts to those risks will reduce the likelihood of judicial or arbitral adjustment or refusal. Where parties lack sufficient experience, early engagement of technical or cost experts may assist in strengthening contractual positioning and enhancing the defensibility of pre-agreed damages claims.

In all cases, parties are advised to consult Vietnamese legal counsel when drafting construction contracts or managing disputes to ensure compliance with the evolving legal framework under the 2025 Law on Construction.

RELATED INSIGHTS​ 

December 4, 2024
Thailand Legal Basics, a valuable primer for foreign investors, explores all aspects of living and doing business in Thailand. Written by specialists at Tilleke & Gibbins in Bangkok, it is the only comprehensive English-language guide to the Thai legal system with a focus on the concerns of foreign business and investment.
November 27, 2024
In Thailand, a business rehabilitation plan in court-supervised rehabilitation proceedings is a crucial element of the business rehabilitation process that outlines how a debtor’s assets will be managed. It also provides guidance for resolving a debtor’s business challenges so that the business can survive and continue to generate returns, increasing the likelihood that its creditors will be repaid. Key Plan Components The Bankruptcy Act B.E. 2483 sets forth the following components to be covered in a rehabilitation plan: The reasons for rehabilitation; Details about the debtor’s assets, liabilities, and other binding obligations at the time the court-ordered rehabilitation; Principles and methods of the rehabilitation; Redemption of collateral when there are secured creditors and guarantor liabilities; Ways to resolve problems arising from a temporary lack of liquidity during plan implementation; Action to be taken when a claim or debt is assigned; Name, qualifications, and letter of consent of the plan administrator, as well as information on compensation; Appointment and release of the plan administrator; Period in which the plan will be implemented (maximum of five years); and Refusal of the debtor’s assets or refusal of contractual rights if the debtor’s assets or contractual rights have obligations that exceed the benefits they yield. Considering the diverse nature and challenges of each debtor’s business, the details listed here are only general guidelines for what should be included in a rehabilitation plan. The planner has the flexibility to create a plan with different details or guidelines than those outlined above to best suit the nature and challenges of the debtor’s business. The planner can also omit some of the mentioned requirements if they are not relevant to the debtor’s business. Concerns of Relevance Court approval of the rehabilitation plan. Once the plan is approved by a meeting of the creditors, it is necessary
November 15, 2024
Vietnam’s new Decree No. 147/2024/ND-CP on the management, provision, and use of internet services and online information (“Decree 147”), which will come into effect on December 25, 2024, replacing Decree No. 72/2013/ND-CP (“Decree 72”), introduces several changes to the regime for domain name dispute resolution. The new decree aims to clarify the legal framework and address some longstanding inconsistencies between Vietnam’s laws on intellectual property and information technology. The main changes related to domain name dispute resolution under Decree 147 are summarized below. Removal of Prescriptive Actions Decree 147 no longer lists specific actions for resolving domain name disputes. Decree 72 had outlined three methods: negotiation/mediation, arbitration, and court. However, IP practitioners had long criticized this approach, arguing it conflicted with the IP Law, which additionally allows administrative action. By omitting these methods, the new decree implies an acceptance of administrative action as provided in the IP Law. However, Decree 147 remains silent on establishing a dispute resolution forum aligned with the CPTPP’s requirement for a UDRP-like model. Currently, Vietnam’s available forums do not fully conform to the UDRP framework. An anticipated circular may provide further guidance on this aspect. Deactivation of Domain Names Decree 72 does not have any provision on the deactivation of a domain name. However, Decree 147 has stipulated some situations where domain names will be deactivated, such as when there is a request from an authority, or when it is discovered that incorrect information was used for registration. Clearer Criteria for Dispute Resolution Article 16 of Decree 147 sets out three clear criteria that must be met for domain name dispute resolution to proceed: (i) confusing similarity with the plaintiff’s trademark, trade name, or personal name; (ii) the defendant’s lack of legitimate rights or interests in the domain name; and (iii) bad faith. Previously,
October 21, 2024
Thailand’s Central Intellectual Property and International Trade (IP&IT) Court has delivered a favorable ruling for Sumitomo Rubber Industries, Ltd., a major player in the tire manufacturing industry, regarding the registration of its motorcycle tire design patent. In this case, Tilleke & Gibbins represented Sumitomo in successfully advocating for recognition of the unique design elements in the company’s motorcycle tire products. Case Overview The case revolved around Sumitomo’s two design patent applications for motorcycle tire designs, which were initially rejected by the Department of Intellectual Property (DIP) on the grounds that they were similar to prior art. Based on an examination of the design elements, primarily focusing on the tire tread patterns, the DIP’s Patent Board had concluded that Sumitomo’s designs were not sufficiently unique to warrant patent protection, as the tread patterns of the new designs were deemed too similar to one found in prior art for tire products. In response, Tilleke & Gibbins filed a complaint with the IP&IT Court on behalf of Sumitomo, seeking a revocation of the Patent Board’s decision and requesting that the court compel the DIP, as the defendant, to proceed with the registration of Sumitomo’s design patents. The complaint emphasized that the designs were novel and distinct, warranting patent protection under Thai law. Legal Strategy The firm’s legal argument focused on the interpretation of Thai patent law, particularly regarding the protection of a product’s external appearance, and emphasized that the determination of a design’s novelty must consider the product’s overall appearance rather than isolating individual features. This approach is consistent with international guidelines on design patents, which require the evaluation of novelty and distinctiveness based on how an informed user would perceive the design as a whole. While Sumitomo’s tire tread patterns may share some superficial similarities to existing designs, the overall impression