The European Power Outage: What Happened and Why It Matters for Thailand

On April 28, 2025, a massive power outage swept across the Iberian Peninsula, plunging Portugal, Spain, and parts of southwestern France into darkness for up to ten hours. As Thailand advances its energy transition by increasing renewable integration and regional interconnections, the European blackout serves as a stark reminder of the grid vulnerabilities that still exist.

This article marks the first installment of From Crisis to Clarity, a three-part series analyzing the recent European blackout and its implications for Thailand. In this article, we examine the root causes of the outage in the Iberian Peninsula. The second article will assess the likelihood of a similar event occurring in Thailand, considering the country’s current energy infrastructure and its increasing reliance on renewables. The final article will present key lessons and recommendations that Thailand can adopt to strengthen its energy system and prevent comparable disruptions in the future.

Root Causes of the European Power Outage

At approximately 12:30 p.m. on April 28, 2025, Spain experienced a sudden and severe drop in electricity generation, with output falling from around 27 gigawatts to slightly over 12 gigawatts. While investigations are still ongoing, preliminary reports suggest a cascading failure triggered by a fault in a high-voltage cross-border transmission line. The abrupt and precipitous drop in supply created significant instability in the national grid, which relies on maintaining a constant frequency of 50 hertz to ensure operational balance. The resulting frequency deviation triggered automatic safety systems. As a result, some power plants, including nuclear plants, were disconnected. This also led to the disconnection of the interconnection line between Spain and France via the Pyrenees. Ultimately, these events caused a complete collapse of Spain’s power system for up to ten hours.

Speculation persists about the exact cause of the Iberian blackout. While Spanish authorities have ruled out a cyberattack, one possible contributor is a lack of so-called “grid inertia”—the property of a power grid that enables it to resist changes in frequency, typically provided by the rotating mass of conventional generators. In other words, grid inertia is the grid’s ability to keep the frequency stable. Traditional grids powered by gas and nuclear plants have high inertia, making them more resistant to frequency changes. In contrast, grids with a high share of renewables, such as wind and solar, have low inertia unless specific measures are taken to compensate.

On May 1, 2025, the Association of European Transmission System Operators (ENTSO-E) announced the establishment of a panel of experts tasked with conducting a thorough inquiry into the causes and consequences of the blackout. This panel is expected to deliver a final report within six months of the incident. Interim publications, including event analyses, developing conclusions, and recommendations, are scheduled to be released at the end of each two-month period following the incident, providing updates on the investigation’s progress. Spain and Portugal have been given three months to submit their data, reflecting the complexity and scale of the event.

Takeaways

The recent European blackout demonstrates how quickly low-inertia power systems can spiral out of control when frequency stability is compromised. This scenario is increasingly relevant to Thailand, whose traditionally gas-based, centrally managed grid still benefits from a buffer of rotational inertia but is rapidly integrating renewable energy sources and expanding interconnections with neighboring countries. As Bangkok looks toward a future where renewables may account for more than half of installed capacity, the Iberian lesson highlights that strengthening and enhancing the reliability of the grid are no longer optional.

 

For more on this topic, read the second article in the series: “Could a Similar Outage Happen in Thailand?

RELATED INSIGHTS​ 

May 25, 2026
After several years of policy discussion and continued efforts led by the Ministry of Commerce (MOC) to relax the list of reserved businesses under the Foreign Business Act B.E. 2542 (1999) (FBA), the reform process has now reached a significant milestone. On May 12, 2026, the Thai cabinet approved in principle two draft subordinate legislative instruments aimed at delisting certain reserved business activities under the FBA and reducing licensing requirements for foreign business operators. These developments signal a renewed and concrete effort by the government to modernize Thailand’s business regulatory framework in order to attract foreign investment and boost Thailand’s competitiveness in the global market. Nine Businesses Set for FBA Delisting Below is a list of the nine businesses that are being targeted for delisting from the FBA’s restrictions. A draft ministerial regulation would delist the first eight reserved businesses, while a royal decree has been drafted to delist the ninth business: Telecommunications services (Type 1 license only, covering operators without their own telecommunications infrastructure), under the supervision of the Office of the National Broadcasting and Telecommunications Commission. Treasury center services subject to the Foreign Exchange Control Act B.E. 2485 and under the supervision of the Bank of Thailand. Securities-collateralized lending, pursuant to the laws governing securities and exchange and derivatives regulated by the Securities and Exchange Commission. Agency, dealer, advisory, or fund management services relating to derivatives where the underlying assets fall outside the scope of the Derivatives Act B.E. 2546 (2003) Intra-group shared services, including administrative, human resources, and IT functions Intra-group domestic debt guarantee services Leasing of partial space for installation of financial service machines and automatic vending machines for employee use Petroleum drilling services Trading of agricultural product derivatives through a futures exchange, with physical delivery or receipt of agricultural products at a futures exchange–designated
February 10, 2026
Data center and cloud investments are forming a major focus of private-sector investment in Thailand, with tech giants like Amazon, Google, Microsoft, and TikTok, as well as numerous telecom and data center companies, committing significant outlays to data center and cloud development. The country’s Board of Investment (BOI) approved projects worth THB 1.87 trillion in 2025, and THB 746 billion of this was from planned data center investments—by far the largest amount from any single industry. Thailand’s swift rise as a regional data center hub is fueled by surging demand for cloud, AI, and digital services, as well as large-scale investments from global tech firms. The country’s strategic location, competitive power costs, robust fiber infrastructure, expanding IT talent, and supportive government policies—including BOI incentives and streamlined approvals—have made it an attractive destination for scalable and sustainable digital infrastructure investments. The BOI’s proactive approach in updating promoted categories and providing both tax and non-tax incentives further ensures Thailand’s continued growth in this sector. 2025 BOI Changes for Data Centers In the middle of 2025, the BOI responded to the remarkable trend by updating investment‑promotion categories across various sectors (e.g., machinery and electrical equipment, public utilities, digital and innovative industries) to accommodate growing investment in data‑center projects. Before the change, which was detailed in a notification that has applied to investment promotion applications submitted from July 1, 2025, onward, data‑center projects under BOI promotion were granted a single A1 incentive (an eight‑year corporate income‑tax exemption) and subject to one uniform set of conditions. The July 2025 notification restructured promotion for data centers into two categories based on power‑usage efficiency: high‑efficiency data centers and other data centers. Under these rules, qualified high‑efficiency data centers are eligible for an eight‑year corporate income tax (CIT) exemption, while for other data centers this exemption is
November 21, 2025
On November 17, 2025, Thailand’s Ministry of Interior introduced significant regulatory changes to make rooftop solar adoption easier and more cost-effective for property owners. Ministerial Regulation No. 72 B.E. 2568 (2025), issued under the Building Control Act B.E. 2522 (1979), was published in the Government Gazette on November 19, 2025, with immediate effect. Background Under the Building Control Act (BCA), any alteration made to a building requires either notification of the relevant authority or application for a building alteration permit—unless the alteration falls under a separate list of exceptions specified in the ministerial regulations issued under the BCA. In 2015, installation of solar rooftops on any residential building under 160 square meters was added to this list of exceptions, subject to inspection and notification requirements. The newly enacted regulation now eliminates many of these requirements and introduces a broader and more permissive framework to promote solar adoption nationwide. Key Changes Specifically, the regulation introduces three major changes: Expanded exemption from the definition of “building alteration”: The installation of solar panels on any building roof—regardless of the type of building or the total area of the installation—is no longer considered a building alteration under the BCA, provided that the total weight of the installation does not exceed 20 kg/m2. Removal of structural integrity certification requirement: The new regulation eliminates the obligation to obtain a structural stability certificate from a licensed civil engineer. Removal of notification requirement: Property owners or possessors are no longer required to notify the local authority before installation of a solar rooftop. Impact This significant streamlining of requirements for solar rooftop installation is expected to accelerate the adoption of renewable energy in the country, particularly for residential and commercial properties—similar to the way Thailand’s December 2024 removal of licensing requirements for factory solar rooftop installations encouraged such
September 25, 2025
Tilleke & Gibbins’ labor and employment team in Hanoi and Ho Chi Minh City has contributed the Vietnam chapter to Labor and Employment Disputes 2026. Drawing on the expertise of three of the firm’s employment specialists, the chapter provides practical guidance for navigating employment disputes in Vietnam and covers: Pre-action considerations: key requirements, third-party funding, contingency fee arrangements Issuing a claim: forum, territorial jurisdiction, standing, commencing claims, fees, service, defendants and legal personality, types of claims, time limits, counterclaims Case management: procedure, rules, amendments to claims, adding parties, consolidating proceedings, class and collective actions, evidence, witnesses, tactical considerations Interim relief: availability, requirements Trial: hearings conduct and time frames, confidentiality and public access, media reporting, elements of successful claims and burden of proof Alternative dispute resolution: available types, requirements and expectations, enforcement Collective employment and labor rights: enforcement and standing Remedies and enforcement: available remedies, assessing compensation, enforcement mechanisms Appeals: procedure, time frames, other means of challenge Updates and trends: recent cases and developments, technology developments, other issues The Vietnam chapter is available for download below. Tilleke & Gibbins also contributed the Cambodia and Thailand chapters to Labor and Employment Disputes 2026. Readers can also gain 30 days of complementary access to the full Labor and Employment Disputes 2026 guide and the rest of Lexology Panoramic’s varied offerings through this link.