June 6, 2024

Potential Impact of Vietnam’s New Land Law on the Energy Sector

On January 18, 2024, Vietnam’s National Assembly passed a new Land Law (“Land Law 2024”) that is scheduled to take effect on January 1, 2025, replacing the current Land Law 2013. To mitigate challenges faced by the real estate market, in late May 2024, the government proposed amendments to the Land Law that would move the effective date up five months, to August 1, 2024, pending approval by the National Assembly.

One of the key sectors to be impacted by the Land Law 2024 is the energy sector, which requires large land areas for power plants and infrastructure, especially given Vietnam’s 2050 net zero emissions commitment. Below are highlights of how the new Land Law 2024 will affect Vietnam’s energy sector.

Annual payment of land rental

Under the Land Law 2013, investors implementing energy projects (e.g., solar power projects) are entitled to choose to lease land with either (i) an annual rental payment or (ii) a single upfront payment for the entire term of use. Under the Land Law 2024, these investors are only allowed to use land in the form of an annual rental payment.

As the annual land rental is calculated in five-year cycles, based on the land price table decided by the state, this new restriction means that investors in energy projects will face an additional risk of a sudden increase in land rental, disrupting their financial planning.

Investors using land sites leased with annual rental payments are also not allowed to mortgage their land-use rights, but can only mortgage assets attached to the land, at credit institutions licensed to operate in Vietnam. Accordingly, this may affect the ability of energy projects to obtain financing during the development stage, because they no longer have assets that can be mortgaged.

Obtaining land

Under the Land Law 2024, investors can obtain land through a lease without any auction or bidding process; through an auction process (for selecting the land user of a land site); or through a bidding process (for selecting the investor implementing an investment project with the need to use land).

Investors in energy projects using public investment capital and public-private partnership (PPP) projects can lease a land site from the state without an auction or bidding process. Further details on these conditions are to be provided by the government.

An auction process will apply to energy projects that intend to use land obtained from the land fund managed by the state if the following conditions are satisfied: (i) the land site is clean and does not require compensation or site-clearance work; (ii) the land site is included in the annual land-use plans approved for auction; and (iii) a 1/500 plan and auction plan are approved by the competent authorities.

A bidding process will apply to energy projects that must conduct bidding to select investors according to specialized laws, such as the laws on electricity, if the following conditions are satisfied: (i) the land is on the list of land sites subject to bidding for selection of investors for an investment project as decided by the provincial People’s Council; (ii) a detailed plan or a 1/2000 zoning plan is approved by the competent authorities; and (iii) other conditions under the laws on bidding are met.

Compared to the Land Law 2013, the Land Law 2024 supplements the bidding for projects using land as a new method for investors to gain access to land. This addition aims to increase competition and fairness for investors.

Compensation, support, and resettlement procedure

If the land for implementing an energy project is currently occupied, a compensation, support and resettlement procedure must be carried out. Under the current Land Law 2013, the decision on land recovery and the decision on the plan for compensation, support and resettlement are issued concurrently. Under the new Land Law 2024, the decision on land recovery will only be issued within 10 days after, among other conditions, the plan on compensation, support, and resettlement has been issued, if resettlement is not required; or the person whose land is recovered has had another land site allocated or handed over by a competent authority to build their own resettlement housing.

These new regulations will extend the length of the land clearance procedure considerably when the recovered land requires resettlement, as the decision on land recovery will only be issued after the resettlement is deemed completed.

Commercial arbitration as a dispute resolution mechanism

Another crucial aspect of the new law is that commercial arbitration is clearly recognized as a dispute resolution mechanism for land-related disputes. Previously, there was uncertainty surrounding whether disputes relating to land could be adjudicated by arbitration. Pursuant to the Land Law 2024, Vietnamese commercial arbitration can resolve disputes arising from commercial activities related to land in accordance with the law on commercial arbitration.

Outlook

The new Land Law aims to address overlapping and conflicting issues of related land policies and laws, while tackling practical challenges in land management and land use. It promotes the commercialization of land-use rights, fostering transparent real estate markets, modernizing land management systems, and implementing administrative and digital reforms to improve land accessibility, especially for energy projects.

RELATED INSIGHTS​ 

May 25, 2026
After several years of policy discussion and continued efforts led by the Ministry of Commerce (MOC) to relax the list of reserved businesses under the Foreign Business Act B.E. 2542 (1999) (FBA), the reform process has now reached a significant milestone. On May 12, 2026, the Thai cabinet approved in principle two draft subordinate legislative instruments aimed at delisting certain reserved business activities under the FBA and reducing licensing requirements for foreign business operators. These developments signal a renewed and concrete effort by the government to modernize Thailand’s business regulatory framework in order to attract foreign investment and boost Thailand’s competitiveness in the global market. Nine Businesses Set for FBA Delisting Below is a list of the nine businesses that are being targeted for delisting from the FBA’s restrictions. A draft ministerial regulation would delist the first eight reserved businesses, while a royal decree has been drafted to delist the ninth business: Telecommunications services (Type 1 license only, covering operators without their own telecommunications infrastructure), under the supervision of the Office of the National Broadcasting and Telecommunications Commission. Treasury center services subject to the Foreign Exchange Control Act B.E. 2485 and under the supervision of the Bank of Thailand. Securities-collateralized lending, pursuant to the laws governing securities and exchange and derivatives regulated by the Securities and Exchange Commission. Agency, dealer, advisory, or fund management services relating to derivatives where the underlying assets fall outside the scope of the Derivatives Act B.E. 2546 (2003) Intra-group shared services, including administrative, human resources, and IT functions Intra-group domestic debt guarantee services Leasing of partial space for installation of financial service machines and automatic vending machines for employee use Petroleum drilling services Trading of agricultural product derivatives through a futures exchange, with physical delivery or receipt of agricultural products at a futures exchange–designated
February 10, 2026
Data center and cloud investments are forming a major focus of private-sector investment in Thailand, with tech giants like Amazon, Google, Microsoft, and TikTok, as well as numerous telecom and data center companies, committing significant outlays to data center and cloud development. The country’s Board of Investment (BOI) approved projects worth THB 1.87 trillion in 2025, and THB 746 billion of this was from planned data center investments—by far the largest amount from any single industry. Thailand’s swift rise as a regional data center hub is fueled by surging demand for cloud, AI, and digital services, as well as large-scale investments from global tech firms. The country’s strategic location, competitive power costs, robust fiber infrastructure, expanding IT talent, and supportive government policies—including BOI incentives and streamlined approvals—have made it an attractive destination for scalable and sustainable digital infrastructure investments. The BOI’s proactive approach in updating promoted categories and providing both tax and non-tax incentives further ensures Thailand’s continued growth in this sector. 2025 BOI Changes for Data Centers In the middle of 2025, the BOI responded to the remarkable trend by updating investment‑promotion categories across various sectors (e.g., machinery and electrical equipment, public utilities, digital and innovative industries) to accommodate growing investment in data‑center projects. Before the change, which was detailed in a notification that has applied to investment promotion applications submitted from July 1, 2025, onward, data‑center projects under BOI promotion were granted a single A1 incentive (an eight‑year corporate income‑tax exemption) and subject to one uniform set of conditions. The July 2025 notification restructured promotion for data centers into two categories based on power‑usage efficiency: high‑efficiency data centers and other data centers. Under these rules, qualified high‑efficiency data centers are eligible for an eight‑year corporate income tax (CIT) exemption, while for other data centers this exemption is
November 21, 2025
On November 17, 2025, Thailand’s Ministry of Interior introduced significant regulatory changes to make rooftop solar adoption easier and more cost-effective for property owners. Ministerial Regulation No. 72 B.E. 2568 (2025), issued under the Building Control Act B.E. 2522 (1979), was published in the Government Gazette on November 19, 2025, with immediate effect. Background Under the Building Control Act (BCA), any alteration made to a building requires either notification of the relevant authority or application for a building alteration permit—unless the alteration falls under a separate list of exceptions specified in the ministerial regulations issued under the BCA. In 2015, installation of solar rooftops on any residential building under 160 square meters was added to this list of exceptions, subject to inspection and notification requirements. The newly enacted regulation now eliminates many of these requirements and introduces a broader and more permissive framework to promote solar adoption nationwide. Key Changes Specifically, the regulation introduces three major changes: Expanded exemption from the definition of “building alteration”: The installation of solar panels on any building roof—regardless of the type of building or the total area of the installation—is no longer considered a building alteration under the BCA, provided that the total weight of the installation does not exceed 20 kg/m2. Removal of structural integrity certification requirement: The new regulation eliminates the obligation to obtain a structural stability certificate from a licensed civil engineer. Removal of notification requirement: Property owners or possessors are no longer required to notify the local authority before installation of a solar rooftop. Impact This significant streamlining of requirements for solar rooftop installation is expected to accelerate the adoption of renewable energy in the country, particularly for residential and commercial properties—similar to the way Thailand’s December 2024 removal of licensing requirements for factory solar rooftop installations encouraged such
September 25, 2025
Tilleke & Gibbins’ labor and employment team in Hanoi and Ho Chi Minh City has contributed the Vietnam chapter to Labor and Employment Disputes 2026. Drawing on the expertise of three of the firm’s employment specialists, the chapter provides practical guidance for navigating employment disputes in Vietnam and covers: Pre-action considerations: key requirements, third-party funding, contingency fee arrangements Issuing a claim: forum, territorial jurisdiction, standing, commencing claims, fees, service, defendants and legal personality, types of claims, time limits, counterclaims Case management: procedure, rules, amendments to claims, adding parties, consolidating proceedings, class and collective actions, evidence, witnesses, tactical considerations Interim relief: availability, requirements Trial: hearings conduct and time frames, confidentiality and public access, media reporting, elements of successful claims and burden of proof Alternative dispute resolution: available types, requirements and expectations, enforcement Collective employment and labor rights: enforcement and standing Remedies and enforcement: available remedies, assessing compensation, enforcement mechanisms Appeals: procedure, time frames, other means of challenge Updates and trends: recent cases and developments, technology developments, other issues The Vietnam chapter is available for download below. Tilleke & Gibbins also contributed the Cambodia and Thailand chapters to Labor and Employment Disputes 2026. Readers can also gain 30 days of complementary access to the full Labor and Employment Disputes 2026 guide and the rest of Lexology Panoramic’s varied offerings through this link.