December 2, 2011

The Thailand Floods: Can Force Majeure Excuse Your Liability?

Bangkok Post, Corporate Counsellor Column

Force majeure is an event that occurs beyond your reasonable control or anticipation. When that event prevents you from performing your contractual obligations, you are ordinarily released from liability for damages caused by that breach. The rationale is that it would not be just to blame you for breach of contract when the contract became impossible to perform through no fault of your own.

The massive flood arriving in early October from northern Thailand has attacked at least seven industrial estates, including Saha Rattana Nakorn, Rojana, Hi-Tech, Bang Pa-in, Factoryland, Nava Nakorn, and Bangkadi in Ayutthaya and Pathum Thani. The Ministry of Industry estimated that the flood affected 9,859 factories in eight provinces, with the total value of damages amounting to approximately THB 237 billion as of November 21. The floods have upset supply chains worldwide, and made it difficult or even impossible for many businesses to perform their ordinary contract obligations.

After the flood recedes, a large amount of litigation may ensue over the damages caused directly and indirectly by the flooding and the resulting contract liabilities. A typical defendant may have failed to deliver goods or services to the plaintiff in time because the defendant’s facility was directly affected by the flood, or perhaps because the defendant’s own supply chain was interrupted by the floods that hit its suppliers. Whether or not the defendant’s contract with the plaintiff has a force majeure clause, it may be possible to avoid liability on grounds of force majeure, but the outcome is not a foregone conclusion and will depend on the facts surrounding each situation.

Meaning of Force Majeure

Many commercial contracts contain force majeure clauses that include an itemized list of events that the parties have agreed will constitute force majeure. Oftentimes “floods” or other “acts of God” are included in that list. A typical force majeure clause might read as follows: “A party’s failure to perform any term or condition of this Agreement as a result of conditions beyond its control such as, but not limited to, war, strikes, fires, floods, terrorism, power failures, or damage or destruction of any network facilities or servers, shall not be deemed a breach of this Agreement.” A clause of this nature provides a contractual definition of force majeure, plus a contractual allocation of risk when such an event prevents performance.

It is always preferable to have a clear force majeure clause in a contract, but the general principle of force majeure also applies even when the contract is silent. Under Section 8 of the Civil and Commercial Code (CCC), force majeure is defined as “any event the happening or pernicious result of which could not be prevented even though a person against whom it happened or threatened to happen takes such appropriate care as might be expected from him in his situation and in such condition.” Thereafter, Sections 205 and 219 of the CCC provide that a debtor is relieved from his contractual obligations if performance becomes impossible because a circumstance for which he is not responsible occurs after creation of the obligation.

These provisions (and others scattered throughout the CCC) relieve a party of liability for many breaches of contract if the breach is caused by force majeure, even if the contract does not include a force majeure clause. That said, force majeure is not always a magic wand that will prevent a party’s liability for failure to perform an obligation.

Force majeure necessarily includes two important conditions: (1) the event cannot be prevented; and (2) the use of proper care. To examine whether these conditions existed at the time of breach, the breaching party needs to assemble information, evidence, and witnesses to confirm that he had professionally-appropriate mitigation plans in place before, during, and after the flood arrived. If he can establish that he had appropriate plans in place and that he implemented those plans, he can reasonably argue that the speed and size of the flood could not have been anticipated and was overwhelming even in the face of such measures.

Once a particular flood situation is proven to be force majeure, the breaching party still needs to prove that the flood prevented him for performing the contractual obligation. Inconvenience is probably not an excuse. For example, if flooding prevented a supplier from delivering parts to a manufacturer, the supplier might be forgiven on grounds of force majeure, but it is unlikely the manufacturer will be released from its downstream obligations unless the manufacturer tried without success to obtain the same inputs elsewhere. While the Thailand flooding has affected supply chains worldwide, it is unlikely that all parties in the supply chains will be able to blame the floods in Thailand if there was any reasonable means available to mitigate the disruption.

Thai Court Interpretations Regarding Floods

The Thai courts do not agree that every flood is considered an event of force majeure. In Supreme Court Case 1194/2531, a contractor sued an owner to recover the late fees that the owner withheld due to the contractor’s failure to complete a pipeline project on time. The contractor argued that one delay occurred because heavy rains caused damage to a bridge en route to the construction site, interrupting the delivery of machinery and materials. The contractor argued that another delay occurred when rains made the river level too high to complete construction.

The Court agreed that the bridge incident was an event of force majeure because it could not be reasonably anticipated and prevented. But the Court did not agree that high water level during the rainy season constituted force majeure, because one should anticipate that water levels will rise dramatically during the rainy season. The Court dismissed the contractor’s claim.

In Supreme Court Case 2377/2542, an insurance company sued a warehouse for damages caused to cargo that the insurer’s customer was storing in the warehouse at the Bangkok port. A heavy rain caused flooding at the warehouse and flood damage to the cargo inside. The Court ruled that the flood was not an event of force majeure, because the warehouse was engaged in a professional service and bore a warehouseman’s duty to provide facilities that keep its customers’ cargo in good condition. The defendant should have designed and constructed safeguards against this particular type and magnitude of flooding at its facility, and the Court ordered the warehouse to pay for the flood damage to the cargo.

When contracts do not include a force majeure clause, a party arguing that the recent Thailand flooding is an event of force majeure will bear the burden of proving that he took preventive measures at an appropriate level considering the person’s profession, and in spite of these measures the floods were too sudden and extreme to be prevented. That party will need to establish that it planned and implemented preventive measures before and during the flooding, plus mitigation efforts after the flooding. All of these issues will be considered when determining whether a party is relieved of liability due the recent Thailand floods or other catastrophes that arguably amount to force majeure.

RELATED INSIGHTS​ 

August 20, 2026
Vietnam’s Law on Bankruptcy and Rehabilitation No. 142/2025/QH15, passed by the National Assembly on December 11, 2025, does something many regional counterparts do not yet attempt: it instructs parties and arbitral tribunals on exactly what happens to an arbitration once a debtor becomes insolvent. Together with the Law on Commercial Arbitration No. 54/2010/QH12, the new law improves upon what used to be an uncertain area of practice, now providing an explicit, mandatory sequence of procedures. Suspension and Termination of Arbitration Proceedings Under article 40(2) of the law, once a Vietnamese court accepts a bankruptcy petition, any arbitration that concerns the debtor’s financial obligations must be temporarily suspended as soon as the tribunal receives the court’s notification. If the court subsequently issues a decision commencing bankruptcy proceedings, article 59(2) takes a further step: the suspended arbitration is terminated outright, and the underlying case file is transferred to the court handling the insolvency for resolution. The two provisions work as a sequence: first suspension, then termination and transfer, rather than as independent triggers. Meanwhile, article 60(4) reinforces this effect by vesting the bankruptcy court with exclusive jurisdiction over all claims against the debtor from the date the petition is accepted. Notably, this mechanism operates automatically, without the need for the insolvency court to issue a separate anti-arbitration order. The tribunal simply suspends or terminates the proceeding by operation of law once notified; however, Vietnamese law currently provides no procedure by which a party can apply to the insolvency court for permission to continue the arbitration despite the statutory effect. Practitioners with a Vietnamese counterparty in arbitration should treat notification of a bankruptcy filing as something to flag to the tribunal immediately since continuing to arbitrate a claim that has become subject to article 40(2) or 59(2) risks producing an award vulnerable
August 20, 2026
Thai law contains no provision that speaks directly to what happens to an arbitration when one of the parties becomes insolvent. The interaction between arbitration and insolvency is derived instead from the general operation of two separately drafted laws: the Bankruptcy Act B.E. 2483 (1940) and the Arbitration Act B.E. 2545 (2002). Because Thai courts have had few opportunities to interpret how these two statutes apply together, the practical answer to many questions, such as who represents an insolvent party in arbitration, whether an award will be enforced, and what happens to a foreign proceeding, depends on inference from general principles of insolvency, arbitration, and procedural law rather than on settled rules. Liquidation and Restructuring The Bankruptcy Act governs both liquidation, which winds up a debtor’s affairs, and restructuring (rehabilitation), which aims to preserve a business. The consequences for arbitration differ accordingly. In liquidation, the debtor’s assets vest in the official receiver, who alone can conduct or continue any arbitration affecting the estate; the debtor loses the authority to act on its own behalf. In restructuring, the plan preparer or administrator takes over that role, but there is more room for the debtor to remain involved, since the objective of rehabilitation is to keep the business operational. Restructuring carries an automatic stay that takes effect once the Bankruptcy Court accepts the restructuring petition. This stay can halt an arbitration regardless of where it is seated. In contrast, liquidation does not work through a stay; instead, the debtor’s loss of authority over its own assets and disputes is what constrains the arbitration. Neither proceeding provides a party a formal route to apply for permission to continue arbitrating—the Bankruptcy Act contains no such mechanism—though in restructuring cases the Bankruptcy Court may allow proceedings to continue where doing so will not prejudice
August 20, 2026
As part of its membership in Lex Mundi, Tilleke & Gibbins has released the latest edition of its Guide to Doing Business in Thailand, providing an overview of the legal, regulatory, and commercial considerations for companies establishing or expanding operations in Thailand. The 2026 edition offers practical insight into the country’s business environment, investment framework, and operational requirements. The guide covers a wide range of topics relevant to foreign and domestic investors, including: Investment incentives and promotion schemes Financial facilities and banking regulations Exchange controls and money transfers Import and export regulations Business structures and incorporation options Requirements for establishing a business Operational and compliance considerations Business cessation and insolvency procedures Employment and labor laws Taxation Immigration and visa requirements Prepared by Tilleke & Gibbins lawyers across multiple practice areas, the publication outlines key aspects of doing business in Thailand, including foreign investment restrictions, regulatory compliance obligations, corporate structures, employment requirements, and recent legal and economic developments affecting investors. The publication forms part of Lex Mundi’s Country Guides series, a global collection of jurisdiction-specific reference materials prepared by member firms around the world. Together, these guides help companies evaluate opportunities, compare regulatory environments, and plan international business activities across multiple markets. The full Guide to Doing Business in Thailand 2026 is available through the button below.
August 19, 2026
Arbitration clauses and national court jurisdiction have long existed in a delicate equilibrium, and nowhere is that equilibrium tested more often than in the drafting of multitier dispute resolution clauses. Such clauses—requiring negotiation before arbitration—are ubiquitous in international construction contracts, and they frequently employ permissive vocabulary at the arbitration tier. The formulation “either party may submit the dispute to arbitration” is intended to signal that either side is entitled to initiate proceedings. Yet it is periodically seized upon by claimants who prefer national courts, on the theory that “may” preserves a parallel right to litigate. Each apex-court pronouncement on this question is therefore significant for drafting practice and forum predictability. In 2019, the Thai Supreme Court delivered Thailand’s clearest answer to date (Judgment No. 3427/2562). Reversing an appellate court decision, the Supreme Court held that permissive wording at the point of commencement does not dilute the parties’ antecedent agreement to withdraw their disputes from the courts—doing so in regard to an International Chamber of Commerce (ICC) arbitration clause seated in Singapore, a configuration typical of foreign-invested projects in Thailand. This article examines the court’s reasoning, situates the decision within comparative jurisprudence, and draws out its practical lessons for parties and drafters operating in the Thai market. Background of the Dispute The dispute arose from a subcontract for civil engineering and architectural works concluded on September 25, 2014. Clause 19 of the subcontract governed dispute resolution. Clause 19.1 required the parties, at the request of either, to seek to resolve any dispute “in connection with, arising out of, or relating to” the subcontract through mutual consultation within sixty days of written notice. According to clause 19.2.1, if the dispute could not be resolved within that period, “either party may submit the dispute to arbitration,” to be conducted under the ICC