November 13, 2015

Groundwork Laid for Public-Private Partnerships in Solar Energy

Bangkok Post, Corporate Counsellor Column

In August 2014, the Energy Regulatory Commission (ERC) announced a new scheme aimed at expanding solar power generation to meet the government’s Alternative Energy Development Plan.

To encourage more solar power generation, the scheme allows the establishment of solar farms through public-private partnerships, which are funded and operated by the government or agricultural cooperatives as public partners, with the private sector as project supporters.

Formally known as the Ground-Mounted Solar Energy Project for the Government Sector and Agricultural Cooperatives, the scheme is governed by regulations passed in March. It has an overall peak capacity of 800 megawatts and maximum capacity of 5 megawatts per project. Only certain projects are eligible to participate, and there are a number of requirements and provisions to be aware of.

Eligibility

To generate and sell electricity under the scheme, a project supporter must be a juristic person (a limited or public limited company) registered in Thailand. A foreign company is eligible only if it is registered in Thailand as a foreign majority-owned company.

A project supporter must obtain certification of standardized equipment for generating power, which includes equipment such as crystal solar cells or thin solar cells. In addition, the supporter must be an experienced company or affiliate with at least one year’s experience in solar energy power production, counted from the project submission date.

Alternatively, a project supporter must have staff with knowledge of and at last one year’s experience in solar energy power production. In addition, it must have a related license such as a Control Engineering Professional License over the ordinary level or the equivalent.

The selection process is carried out by a draw as opposed to competitive bidding.

Minimum Investment

A project supporter must fulfill the following criteria:

  • Registered capital of at least THB 2 million per megawatt, with at least 25 percent paid up, in accordance with rules set by the Ministry of Commerce; and
  • Investment credit and all types of capital circulating in the company, both of the financial institution and/or the supplier, must be backed by evidence showing the financial institution and/or supplier can provide various types of support to cover the required financial amounts of the project.

A project supporter is entitled to support more than one project, but its total selling capacity must not exceed 50 megawatts and its minimum capital qualification must cover the total capacity of all projects.

Power-Purchase Agreement

Approved project owners will be granted a power-purchase agreement (PPA) for a term of 25 years, starting from the scheduled commercial operation date specified in the agreement, the commercial operation date, or the actual operation date, whichever comes first.

In the PPA, the sale of power in the portion not exceeding the “capacity factor” will be granted a feed-in tariff (FiT) rate of THB 5.66 per kilowatt-hour. Capacity factor refers to the percentage of total energy produced annually compared with a multiple of installed capacity and the number of hours in a year. For example, for 1 kW installed, 100 percent capacity would be 8.76 million kWh. With a capacity factor of 16 percent, the FiT would apply to a maximum of 1,401,600 kWh per kW installed in a year.

The regulation restricts the assignment of rights under the PPA and introduces a three-year shareholding lock-up period. The rights and obligations under an application to sell electricity or an agreement to sell and purchase electricity cannot be assigned unless the authority responsible for the sale gives consent and the ERC approves it. In addition, the regulation does not permit the PPA to:

  • change the number of shareholders in a way that causes the original shareholders of the project to subscribe to less than one half of the project; and
  • change the distribution of shares among the new shareholders in a way that causes the original shareholders to subscribe to less than 51 percent of shares during the first three years after the commercial operation date.

Summary

The ERC has set out a clear framework for private participation in ground-mounted solar energy projects owned by the government and agriculture cooperatives. Private-sector participation is essential.

In the future, the regulation may allow foreign companies to participate as project owners and not only as supporters. Power production is considered a manufacturing business under the Foreign Business Act, meaning foreigners can operate a power-production business without a foreign business license. If the current trend continues, Thailand will be on its way to making renewable energy a sustainable alternative to fossil fuels and imported oil.

RELATED INSIGHTS​ 

May 25, 2026
After several years of policy discussion and continued efforts led by the Ministry of Commerce (MOC) to relax the list of reserved businesses under the Foreign Business Act B.E. 2542 (1999) (FBA), the reform process has now reached a significant milestone. On May 12, 2026, the Thai cabinet approved in principle two draft subordinate legislative instruments aimed at delisting certain reserved business activities under the FBA and reducing licensing requirements for foreign business operators. These developments signal a renewed and concrete effort by the government to modernize Thailand’s business regulatory framework in order to attract foreign investment and boost Thailand’s competitiveness in the global market. Nine Businesses Set for FBA Delisting Below is a list of the nine businesses that are being targeted for delisting from the FBA’s restrictions. A draft ministerial regulation would delist the first eight reserved businesses, while a royal decree has been drafted to delist the ninth business: Telecommunications services (Type 1 license only, covering operators without their own telecommunications infrastructure), under the supervision of the Office of the National Broadcasting and Telecommunications Commission. Treasury center services subject to the Foreign Exchange Control Act B.E. 2485 and under the supervision of the Bank of Thailand. Securities-collateralized lending, pursuant to the laws governing securities and exchange and derivatives regulated by the Securities and Exchange Commission. Agency, dealer, advisory, or fund management services relating to derivatives where the underlying assets fall outside the scope of the Derivatives Act B.E. 2546 (2003) Intra-group shared services, including administrative, human resources, and IT functions Intra-group domestic debt guarantee services Leasing of partial space for installation of financial service machines and automatic vending machines for employee use Petroleum drilling services Trading of agricultural product derivatives through a futures exchange, with physical delivery or receipt of agricultural products at a futures exchange–designated
February 10, 2026
Data center and cloud investments are forming a major focus of private-sector investment in Thailand, with tech giants like Amazon, Google, Microsoft, and TikTok, as well as numerous telecom and data center companies, committing significant outlays to data center and cloud development. The country’s Board of Investment (BOI) approved projects worth THB 1.87 trillion in 2025, and THB 746 billion of this was from planned data center investments—by far the largest amount from any single industry. Thailand’s swift rise as a regional data center hub is fueled by surging demand for cloud, AI, and digital services, as well as large-scale investments from global tech firms. The country’s strategic location, competitive power costs, robust fiber infrastructure, expanding IT talent, and supportive government policies—including BOI incentives and streamlined approvals—have made it an attractive destination for scalable and sustainable digital infrastructure investments. The BOI’s proactive approach in updating promoted categories and providing both tax and non-tax incentives further ensures Thailand’s continued growth in this sector. 2025 BOI Changes for Data Centers In the middle of 2025, the BOI responded to the remarkable trend by updating investment‑promotion categories across various sectors (e.g., machinery and electrical equipment, public utilities, digital and innovative industries) to accommodate growing investment in data‑center projects. Before the change, which was detailed in a notification that has applied to investment promotion applications submitted from July 1, 2025, onward, data‑center projects under BOI promotion were granted a single A1 incentive (an eight‑year corporate income‑tax exemption) and subject to one uniform set of conditions. The July 2025 notification restructured promotion for data centers into two categories based on power‑usage efficiency: high‑efficiency data centers and other data centers. Under these rules, qualified high‑efficiency data centers are eligible for an eight‑year corporate income tax (CIT) exemption, while for other data centers this exemption is
November 21, 2025
On November 17, 2025, Thailand’s Ministry of Interior introduced significant regulatory changes to make rooftop solar adoption easier and more cost-effective for property owners. Ministerial Regulation No. 72 B.E. 2568 (2025), issued under the Building Control Act B.E. 2522 (1979), was published in the Government Gazette on November 19, 2025, with immediate effect. Background Under the Building Control Act (BCA), any alteration made to a building requires either notification of the relevant authority or application for a building alteration permit—unless the alteration falls under a separate list of exceptions specified in the ministerial regulations issued under the BCA. In 2015, installation of solar rooftops on any residential building under 160 square meters was added to this list of exceptions, subject to inspection and notification requirements. The newly enacted regulation now eliminates many of these requirements and introduces a broader and more permissive framework to promote solar adoption nationwide. Key Changes Specifically, the regulation introduces three major changes: Expanded exemption from the definition of “building alteration”: The installation of solar panels on any building roof—regardless of the type of building or the total area of the installation—is no longer considered a building alteration under the BCA, provided that the total weight of the installation does not exceed 20 kg/m2. Removal of structural integrity certification requirement: The new regulation eliminates the obligation to obtain a structural stability certificate from a licensed civil engineer. Removal of notification requirement: Property owners or possessors are no longer required to notify the local authority before installation of a solar rooftop. Impact This significant streamlining of requirements for solar rooftop installation is expected to accelerate the adoption of renewable energy in the country, particularly for residential and commercial properties—similar to the way Thailand’s December 2024 removal of licensing requirements for factory solar rooftop installations encouraged such
September 25, 2025
Tilleke & Gibbins’ labor and employment team in Hanoi and Ho Chi Minh City has contributed the Vietnam chapter to Labor and Employment Disputes 2026. Drawing on the expertise of three of the firm’s employment specialists, the chapter provides practical guidance for navigating employment disputes in Vietnam and covers: Pre-action considerations: key requirements, third-party funding, contingency fee arrangements Issuing a claim: forum, territorial jurisdiction, standing, commencing claims, fees, service, defendants and legal personality, types of claims, time limits, counterclaims Case management: procedure, rules, amendments to claims, adding parties, consolidating proceedings, class and collective actions, evidence, witnesses, tactical considerations Interim relief: availability, requirements Trial: hearings conduct and time frames, confidentiality and public access, media reporting, elements of successful claims and burden of proof Alternative dispute resolution: available types, requirements and expectations, enforcement Collective employment and labor rights: enforcement and standing Remedies and enforcement: available remedies, assessing compensation, enforcement mechanisms Appeals: procedure, time frames, other means of challenge Updates and trends: recent cases and developments, technology developments, other issues The Vietnam chapter is available for download below. Tilleke & Gibbins also contributed the Cambodia and Thailand chapters to Labor and Employment Disputes 2026. Readers can also gain 30 days of complementary access to the full Labor and Employment Disputes 2026 guide and the rest of Lexology Panoramic’s varied offerings through this link.